MnDOT Metro District State Aid Construction Thursday February 19 th, 2015
2
MnDOT State Aid is delegated oversight of Federal Aid projects administered by local agencies through the FHWA/ MnDOT Stewardship Agreement. Although our role is of regulators, we see ourselves more as advocates.
3
DBE Goal OJT Buy America Proprietary Items Independent Assurance Testing Independent Cost Estimate ADA Compliance
4
Electronic State Aid Manual (eSAM) Electronic State Aid Manual (eSAM) Process, and directions Construction Chapter ◦ Roles and responsibilities ◦ Precon ◦ Contract time and contract changes ◦ Documentation ◦ Materials ◦ Subletting and labor
5
State Aid for Local Transportation State Aid for Local Transportation Information on all types in the State Aid and Federal Aid process link to Metro State Aid link to the eSAM Construction chapter link to State Aid Construction page Multiple other tools Link to forms
6
Step by step guide to the Federal Process Construction starts on page 12
7
Contact Metro State Aid for eligibility discussion Funding groups are required MnDOT estimating Independent Cost Estimate (23 CFR 635.120) MnDOT estimating Karen Peters can review legal language if desired on Supplemental Agreements Karen Peters State Aid Signature for funding eligibility Change must fit into the original scope of the project and be within the environmental document review area. Who, What Where and Why
9
Contract Change Forms
10
The GOOD the engineer has determined engineering judgment safety change condition unforeseen condition differing site conditions The BAD damages higher standard preference/desired upgrades aesthetic upgrades surplus materials city/county requested resident requested incentives not in original contract acceleration plan error rework, rebuild, regrade, re- anything outside project limits
11
FHWA approval of changes over $100K PODI projects- all contract changes PODI projects - preapproval of contract changes over $100K
12
Send form to Metro State Aid at start and at completion of project To record the active use of federal funds Liquidated damages State Aid Forms State Aid Forms
13
Final checklist Final checklist ◦ Final DCP Payment Request ◦ Overrun form ◦ Copy of final voucher ◦ Copies of all COs, WOs, and SAs ◦ Materials exception summary ◦ Final Inspection report ◦ Cost distribution Spreadsheet ◦ State Aid Payment Request ◦ Backsheet Item Costs
14
List reviewed with FHWA quarterly No expenditures for a 12 months No expenditures for 9 months (future) Need explanation and plan to get finaled. Claims labor holds and staff shortages no longer acceptable No federal money has been pulled from project yet…
15
Contact Info incase of emergency Lane closure request form Changes to approved plan on TH R/W must be approved by MnDOT functional group (traffic, water resources, road section) Coordinate with metro traffic and signal offices during the project ADA Compliance Checklist MnDot Signing Review and Inventory
16
ADA Compliance Checklist ADA Compliance Checklist ADA Compliance Checklist Guidance ADA Compliance Checklist Guidance
17
Federal Aid Essentials for Locals Federal Aid Essentials for Locals
18
State Aid Manual: State Aid Manual: Contract Change Forms: Contract Change Forms: DCP Checklist: DCP Checklist: Metro State Aid Metro State Aid
19
MnDOT's Construction Tools Website: MnDOT's Construction Tools Website: MnDOT’s ADA website: MnDOT’s ADA website: MnDOT Construction Office Staff MnDOT Construction Office Staff Metro Traffic: Metro Traffic: Project Contact info and Lane Closure Requests: Project Contact info and Lane Closure Requests: