Melissa Owen Texas Department of Transportation Right of Way Division May 17, 2005 KATY FREEWAY PROJECT
3
OVERVIEW TxDOT Utility Program Cooperative Management Process Utility Adjustment Process
4
COST ESTIMATING
5
Supplemental Cost Estimates Actual Cost Lump Sum Agreement Cost Estimate
6
AGREEMENT COST ESTIMATE Regulations Equivalent Facility Functional Equivalent Facility Eligible Replacement Cost New Technology and Materials Industry Standards
7
AGREEMENT COST ESTIMATE Betterment Eligibility Ratio In-Eligible Cost
8
AGREEMENT COST ESTIMATE Actual Cost Estimate Example Supplemental Estimate Example Detail of Estimate Itemized Cost Estimate Unit Cost Estimate
14
INVOICING
15
Identical to Cost Estimate Form Detailed to Support Payment Supporting Documentation
16
KATY FREEWAY PROJECT
17
2.7 Billion Dollar Project 10 Construction Segments 25 miles
19
KATY FREEWAY PROJECT Utilities - Project Basis 32 Known Utility Companies 128 of Adjustments $315 Million
22
KATY FREEWAY PROJECT Managing Project Monitoring Progress Verification and Support of Invoices Reporting Progress
23
N Section 5 Highway Construction Contract
24
QUESTIONS