OFFSHORE PIPELINE CONSTRUCTION PHASE
Pipe Laying : Normal S-Laying Method
2
OFFSHORE PIPE LAYING: Normal S-Laying Method
3
Step 1: PIPE BEVELING Lift the pipe out of the supply barge onto the incoming rack Pipe Tallying (pipe number, length, joint number) Making the J-Bevel on pipe ends for Auto welding
4
Step 2: Station 1 (Fit up, Root and Hot Pass)
Preheat on pipe end prior to welding (based on approved WPS) Fitting pipe ends to be aligned by means of internal clamp Root weld followed by Hot pass
5
Step 3: Station 2,3,4&5 Filler passes on Station 2 and 3
Cap welding on Station 4 Visual Inspection on Station 5 Sta #4 Sta #2 Sta #5 Sta #3
6
Step 4: Station 6 (X-Ray) X-ray operators control the movement of
the X-ray crawler inside the pipe Radiographic intrepeters from HHI, Client and Migas are reviewing the X-ray result Wrapping the film around the intended joint
7
Step 5: Station 7& 8 (Brush up and Cold Wrap)
Sta #7: Brush up Sta #8: Cold Wrap
8
Step 6: Station 9 (FIELD JOINT COATING) & PULLING
Foam Coating performed by OJS (Offshore Joints Service)
9
WELDING
10
X - Ray
11
Coating
12
Laying
13
HD 423 Laying
14
HD 423 LINE PIPE ON SEA BED
15
How the Barge Moves P5 P4 P2 P1 S1 S5 S4 S2
16
P5 P4 P2 P1 S1 S5 S4 S2
17
P5 S5 P5 S5 P4 S4 P2 P1 S1 S2
18
P5 S5 P4 S4 P4 S4 P2 P1 S1 S2
19
P5 P4 P2 S2 P2 S2 P1 S1 S5 S4
20
P5 P4 P2 P1 S1 S5 S4 S2