OFFSHORE PIPELINE CONSTRUCTION PHASE

Similar presentations


Presentation on theme: "OFFSHORE PIPELINE CONSTRUCTION PHASE"— Presentation transcript:

1 OFFSHORE PIPELINE CONSTRUCTION PHASE
Pipe Laying : Normal S-Laying Method

2 OFFSHORE PIPE LAYING: Normal S-Laying Method

3 Step 1: PIPE BEVELING Lift the pipe out of the supply barge onto the incoming rack Pipe Tallying (pipe number, length, joint number) Making the J-Bevel on pipe ends for Auto welding

4 Step 2: Station 1 (Fit up, Root and Hot Pass)
Preheat on pipe end prior to welding (based on approved WPS) Fitting pipe ends to be aligned by means of internal clamp Root weld followed by Hot pass

5 Step 3: Station 2,3,4&5 Filler passes on Station 2 and 3
Cap welding on Station 4 Visual Inspection on Station 5 Sta #4 Sta #2 Sta #5 Sta #3

6 Step 4: Station 6 (X-Ray) X-ray operators control the movement of
the X-ray crawler inside the pipe Radiographic intrepeters from HHI, Client and Migas are reviewing the X-ray result Wrapping the film around the intended joint

7 Step 5: Station 7& 8 (Brush up and Cold Wrap)
Sta #7: Brush up Sta #8: Cold Wrap

8 Step 6: Station 9 (FIELD JOINT COATING) & PULLING
Foam Coating performed by OJS (Offshore Joints Service)

9 WELDING

10 X - Ray

11 Coating

12 Laying

13 HD 423 Laying

14 HD 423 LINE PIPE ON SEA BED

15 How the Barge Moves P5 P4 P2 P1 S1 S5 S4 S2

16 P5 P4 P2 P1 S1 S5 S4 S2

17 P5 S5 P5 S5 P4 S4 P2 P1 S1 S2

18 P5 S5 P4 S4 P4 S4 P2 P1 S1 S2

19 P5 P4 P2 S2 P2 S2 P1 S1 S5 S4

20 P5 P4 P2 P1 S1 S5 S4 S2