Capital Improvement Program (CIP) Overview Dean Fisher, P.E., PMP, CCM July 25, 2013.

Similar presentations


Presentation on theme: "Capital Improvement Program (CIP) Overview Dean Fisher, P.E., PMP, CCM July 25, 2013."— Presentation transcript:

1 Capital Improvement Program (CIP) Overview Dean Fisher, P.E., PMP, CCM July 25, 2013

2 OCSD Service Area 479square miles 210million gallons per day 2.5million population 21cities, 3 special districts 580miles of sewers 15pump stations 2treatment plants Service Area Los Angeles San Diego Orange County

3 Reclamation Plant No. 1 Fountain Valley Treatment Plant No. 2 Huntington Beach

4 Background EPA Consent Decree Secondary Treatment 2002 - 2012 Full Secondary December 2012 Future Renewal, Replacement and Rehabilitation

5 Strong Financial Position Revenues from user fees and connection fees Proactive forecasting and planning AAA Bond Rating

6 More than 70 ProjectsMore than 70 Projects $1.8 Billion Dollars invested in our Infrastructure

7 Secondary Treatment Expansion Six EPA Consent Decree Milestones Job No.MilestonesDue Date P1-76Construction Plant 1 Trickling Filters3-15-06 P1-102Advertise for Bid of Plant 1 AS System11-15-06 P2-90Advertise for Bid Plant 2 Trickling Filters1-15-07 P2-74Rehab of Plant 2 AS System1-15-09 P2-90Construction Plant 2 Trickling Filters2-15-11 P1-102Construction Plant 1 AS System11-15-12 Full compliance with permit12-31-12

8 Trickling Filters at Plant No. 2 Designer: Brown & Caldwell Contractor: J.F. Shea Construction Construction Cost: $182M - Capacity: 60 MGD

9 New Secondary Treatment at Plant No.1 Designer: Black & Veatch Contractor: Kiewit Infrastructure West Construction Cost: $207M – Capacity 60 MGD

10 Headworks at Plant No. 2 New Facility Demolition of Existing Headworks Designer: Carollo Engineers Contractor: J.F. Shea Construction Construction Cost: $196M - Capacity 340 MGD

11 Outfall Land Section & OOBS Piping Rehabilitation Designer: Black & Veatch Contractor: J.F. Shea Construction Construction Cost: $11.8M

12 Central Generation Automation Designer: Black & Veatch Contractor: Morrow Meadows/Sachs Electric Construction Cost: $14.6M

13 Sludge Dewatering & Odor Control at Plant No. 1 Exterior finishGround level Designer: HDR Engineering Contractor: W. M. Lyles Construction Cost: $127M

14 Pump Stations Rocky Point Pump Station Bitter Point Pump Station Designer: Malcolm Pirnie Contractor: Kiewit Inf. West Construction Cost: $9.2M Designer: Lee & Ro Contractor: Kiewit Inf. West Construction Cost: $20.2M

15 Magnolia Trunk Sewer Rehabilitation Design/Build: Kiewit/Malcolm Pirnie Design/Build Cost: $15.5M

16 Santa Ana River Interceptor Pipeline Construction Joint project: Orange County, SAWPA & OCSD Designer: TetraTechCM: MWH Contractor: W.A. Rasic/L.A. Engineering Const Cost: $49M

17 Increasing Level of Service 100% Secondary Standards 70 mgd Reclamation Increased System Reliability Lower Engine Emissions Less Odors Disinfection Treat Urban Runoff Fire & Safety Code Compliance

18 CIP Drivers Enhanced Planning Methodology Plant or Collection System Capacity Condition Of Assets Business Efficiency & Research Outcome Level of Service or Regulatory Change

19 CIP Drivers Enhanced Planning Methodology Plant or Collection System Capacity Condition Of Assets Business Efficiency & Research Outcome Level of Service or Regulatory Change

20 CIP Drivers Transition to Rehabilitation Dome Support Primary Influent Line Outer Wall Mechanism Coating Failure

21

22 Current Projects in Design/Construction Biosolids Dewatering Digester Improvements Ocean Outfall Rehabilitation Plant Utility/Safety Rehabilitations Newport Beach Collections

23 Upcoming Newport Beach Projects

24 Upcoming Planned Projects Headworks Rehabilitation - $50 Million Outfall Pump Station Rehabilitation - $20 Million Primary Clarifier Rehabilitation - $120 Million Digesters Rehabilitation - $50 Million Digester Gas Facilities Rehabilitation - $40 Million Collections Rehabilitations - $100 Million Odor Control Master Planning - $20 Million Admin. Facilities Master Planning - $40 Million

25 Upcoming Design Proposals Next 2 Years (2013-2015) No. of Projects Construction Estimate Trunk / Collections6$ 51.1 M Treatment Plant9$ 191.7 M Total17$ 242.8 M Also – Upcoming Planning Studies RFP in August

26 Upcoming Construction Bidding Next 2 Years (2013-2015) No. of Projects Construction Estimate Trunk / Collections7$ 57.0 M Treatment Plant12$ 108.4 M Total19$ 165.4 M

27

28 Questions? www.ocsewers.com


Download ppt "Capital Improvement Program (CIP) Overview Dean Fisher, P.E., PMP, CCM July 25, 2013."