BRIEF NATIONAL HIGHWAY AUTHORITY ON CONSTRUCTION WING PROJECTS

Similar presentations


Presentation on theme: "BRIEF NATIONAL HIGHWAY AUTHORITY ON CONSTRUCTION WING PROJECTS"— Presentation transcript:

1 BRIEF NATIONAL HIGHWAY AUTHORITY ON CONSTRUCTION WING PROJECTS
GOVERNMENT OF PAKISTAN MINISTRY OF COMMUNICATIONS NATIONAL HIGHWAY AUTHORITY BRIEF ON CONSTRUCTION WING PROJECTS Islamabad, Jan 10, 2014 1

2 COMPLETED DEVELOPMENT PROJECTS SINDH
Rs in Million Road/ River Construction Project Km PC-1 Cost Start Contractor Contract Cost PSDP Status Original Revised 1 Indus *Larkana Khairpur Bridge (5 Packs) 57 4831 11588 May-07 Sachal SMADB SMC MB: 1444 PI: 4016 PII: 1422 PIII: 1634 PIV: 148 500 Subst. Completed Except 6 Km Asphalt on Approach road Larkana side. 2 N-105 Rehabilitation of Larkana-Naudero Lahki Road (2 Packs) 61 1925 4000 Apr-09 Zarghoon PI: 1263 PII: 1383 201.6 3 N-305 Dualization of Sakrand – Benazirabad Road 20 1129 1419 Oct-09 NAK USMANI PI: 942 PII: 598 33.6 4 N-655 Rehabilitation of Ratodero Naudero Road 15 612 847 Sep-09 794 5 DW Hyderabad- Badin Road to Mir Wah-Sanjar Chang Road 2(Packs) 52 880 1794 Jun-10 Maqbool SARCO PI: 802 PII: 656 168 6 M-10 Karachi Northern Bypass (Including collapsed segment) 2928 5224 Apr-02 NLC Usmani P1: 2405 P2: 793 CS : 434 67.2 Completed 2 2

3 ONGOING DEVELOPMENT PROJECTS
SINDH Rs in Million Road/ River Construction Project Km PC-1 Cost Start Contractor Contract Cost PSDP Progress Exp Comp Original Revised 1 LEP Lyari Expressway 32 5081 10443 May-02 FWO 8554 600 80% Dec-14 2 N-455 Kamber – Shahdadkot 29 966 1050 Sep-09 RMC 1043 336 46% Jun-14 3 Indus Qazi Ahmed - Amri Bridge (4 Packs) 18 3683 7292 Mar-10 Sachal SMADB 2017 (P1) 1714 (P2) 638 77% Sep-14 4 N-110 *Gharo-Keti Bunder (3 Packs) 84 3036 3300 QKC MAJ&FE Zarghoon 776 (P1) 1292 (P2) 957 (P3) 497.67 74% 5 N-255 *Larkana-Nasirabad (Rehab) 34 1214 Jul-10 Lilley 1587 374.1 44% 6 N-155 **Larkana- Mohenjodaro upto Airport (2 Packs) 28 1931 3041 May-09 SMC 1529 (P1) 1533 (P2) 168 83% 7 **Larkana – Kamber 20 608 855 Al-Mehran 845 3 3

4 BALOCHISTAN COMPLETED PROJECTS Rs in Million PSDP No 1 102 MCHP 653 2
Road/ Bridge Project/ Section Km PC-1 Cost Todate Expenditure Sep-13 Contractor Contract Cost PSDP Original Revised 1 102 MCHP Makran Coastal Road 653 15010 17262 15,189 FWO AL-Khan Nazir (JV) SMADB PI: 4880 PII: 820 PIII: 825 PIV: 1050 PV: 2656 PVI: 2487 PVII: 1166 300 2 90 N-65 Improvement of N - 65, Nutal - Sibi – Dhadar Section ( 3 x Packs) 106 2266 3262 2070 AGHA PI: 1575 PII: 452 PIII: 180 50 3 113 Realignment near Jacobabad & Dera Allah 27 478 671 629 MAB 526 46.6

5 BALOCHISTAN ONGOING DEVELOPMENT PROJECTS Rs in Million 1 M-8 193 2 143
Road/ Bridge Project/ Section Km PC-1 Cost Contractor Contract Cost PSDP Prog Start Exp Comp Original Revised 1 M-8 Gwadar -Turbat-Hoshab (3 Packs) 193 5687.4 18379 Left over work to be awarded 2494(S-1, P IIA) 3687(S-1, P IIB) 3166(S-2, P IIA) 3,433 68% Sep-04 18 Months after re-tendering 2 Khuzdar-Ratodero 143 4010 6672 AMCC SMADB FWO 2207(S-IV, P-IV) 1908(S-IV, P-III) 2306 (S-IV, P-V) 73% Oct-04 Dec-14 3 N-85 Hoshab- Basima - Sorab 454 22412 14,452) 5,000 22% Sep-07 Dec-16 4 N-70 Waigum Rud - Khajuri 132 2841 3473 1331 599 50% Mar-14 5 N-65 Kolpur Bypass 5.7 639.24 1065 Sapna 696 172 55% Dec-10 Jun-14

6 RECENTLY COMPLETED DEVELOPMENT PROJECTS Substantially Completed
PUNJAB Rs in Million Sr PSDP # Road/ Bridge Project/Section Km PC-1 (Orig / Rev) Contract Cost PSDP Start Completion Status 1 66 Sutlej Moosa Pak Shaheed Bridge 0.6 2130 1616 201.6 Jul-09 May-11 Completed 2 62 Chenab Chund Bridge 0.79 1086 805.19 19.03 Jan-08 Feb-11 3 65 Head Muhammadwala Bridge 2508 712 (P1) 405 (P2) 970 (P3) 16.8 Jun-09 Dec-11 4 82 N-5 Jinnah Chowk - Bahawalpur Chowk 8 1078 234 (P1) 532 (P2) 134.4 Jul-08 5 67 Wah Gate Underpass at Taxila 1.27 993 873 7 Dec-08 Oct-11 6 91 IMDC Islamabad Murree Dual Cariageway 42 13,600 3414 Sep-99 Apr-11 106 N-115 Nag Shah Chowk Flyover (4-Lane) 1530 835 266.27 Jul-10 Jul-13 Substantially Completed 96 Link to BZU Khanewal- Multan Inter District Road (Bosan Road) (2x Packs) 7.5 4570 461 (P1) 531 (P2) 450 Mar-11 Aug-13 9 104 Link to Jinnah Chowk Multan Inner City Ring Road Multan -- / 10,918 1204 (P1) 1202 (P2) 1596 (P3) 400 Feb-10 Jan-13 10 88 M-2 Hiran Minar Interchange 0.5 260 / 730 (Under process) 234 150 Jul-11 Dec-12

7 ONGOING DEVELOPMENT PROJECTS
PUNJAB Rs in Million PSDP # Road/ River Project/Section Km PC-1 (Orig / Rev) Contract Cost PSDP Progress Start Expected Completion Remarks 1 117 N-115 Tri District Link (Jalalpur Pirwala - Uch Sharif) (Pkg-3) 27 3171 (Global) 1566 (Pack-3) 350 (Global) 44% Dec-09 Jun-14 Work in progress 2 68 Chenab Sultan Bahoo Bridge (Shorkot - Garh Maharaja) Main Bridge 0.85 1603 / 4,354 (under process) 770 403.2 (Global) 84% Jun-10 Garh Maharaja Side Approach Road 3.2 678 55% Sep-10 Shorkot Side Approach Road 4.09 572 68% Sep-11 Flood Protection Bund on Garh Maharaja Side 8 147 6.18% Dec-12 J-Spur at Garh Maharaja side 1.72 204 -- Jun-13 J-Spur & raising of Existing Dyke on Shorkot Side 1.6 296 15.5%

8 PUNJAB ONGOING DEVELOPMENT PROJECTS Rs in Million 1.2 5459 (Global)
PSDP # Road/ River Project / Section Km PC-I (Orig / Rev) Contract Cost PSDP Progress Start Expected Completion Remarks 3 59 Indus Nishtar Ghat Bridge (Shaheed Benazir Bhutto) Main Bridge 1.2 5459 (Global) 929 658 51% Feb-12 Jul-14 Work in progress Approach Road Zahir Pir To Chachran Sharif 12.24 594 43% Nov-11 4 70 Ravi Syedwala Bridge -- 1164 829 268.8 7% Oct-12 Apr-14 5 64 Link to Northern bypass Multan Gillani Road (Khad Factory to Pul Khadal) Multan (5.6 Km) 5.06 809 211 201.6 13% 6 100 N-115 6 Lane Highway from Double Phatak – Chowk Naagshah (Old Shujabad Road) 8 4028 1440 300 26% Jan-13 Jun-14 7 61 Sutlej Baba Farid Bridge 1108 67.2 69% Feb-08 9 months from resumption of work Work suspended

9 COMPLETED DEVELOPMENT PROJECTS (GOP)
KHYBER PAKHTUNKHWA Rs in Million PSDP Road Project Km PC-1 Cost Contract Cost Start Completion Remarks Orig Rev 1 103 N-15 Mansehra Naran Jalkhad road 43.3 5125.6 5350.6 50 1369 May-02 Dec-08 Completed 2 78 N-55 CRBC-Sara-e-Gambila 70 1585 1903 183 1126 Feb-07 Dec-09 3 89 N-45 Takht Bhari – Shergarh – Daregai 30 2399 (Global) 3405 (Global) (under process) 101 917 Aug-10 Dec-12 9

10 KHYBER PAKHTUNKHWA ONGOING DEVELOPMENT PROJECTS (GOP) Rs in Million 10
PSDP Road Project Km PC-1 Cost Contract Cost Progress Start Expected Completion Remarks Orig Rev 1 97 N-80 Khushalgarh Bridge (Pack-1, 2 Bridge & Kohat side approach) 1538 3108 (under process in CDWP) 336 1008 93% Oct-11 Jun-2014 Work in progress Jand Side Approach Road & Over Head Bridge 1.23 165 50% Mar-13 Mar-2014 2. 92 N-15 Jhalkhad - Babusar Top 28.5 4017 -- 1206 68.4% Oct-04 Dec-2014 Babusar Top - Chillas 38 1313 82.5% Jan-05 3 98 N-45 Lowari Tunnel 7984 18,132 1000 6047 40% Sep-05 Oct-2017 4 109 E-2 Peshawar Northern Bypass (Pack-I) 7.6 9003 (Global) 1458 2219 70% Feb-10 Apr-2014 Pack IIIA 5.4 1545 7% Jul-13 Oct-2014 5 89 Takht Bhai Flyover on Noshera Chakdara Dir Road (N-45) 0.22 Bridge Approach 2399 3405 (Global) (under process) 101 582 5% Feb-13 Aug-14 6 KKH Shatial Thor Nala Bypass 37 3844 WAPDA 3518 3% Sep-12 Sep-14 7 Torkham Jalalabad Road Afghanistan (ACW) 73 4341 58% Jan-07 FWO Demobilized on Aug-08 Work suspended 10