CPV DCS STATUS REPORT Mikhail Bogolyubsky (IHEP, Protvino) Serguei Sadovsky (IHEP, Protvino) CERN, DCS meeting, 30 January, 2007.
2
2006 DCS planning, CPV DCS planning meeting 13.03.2006: Detector CPV: D = 01.12.07 = > D = 1-st Shut Down in 2008 (D - Date of the detector installation in the pit) CPV FSM Pre-commissioning in Lab/CERN/SXL2 Who responsible Ready when? – –Integrate all sub-systems in the DETECTOR FSM A.M., M.B. 01.07.07 – –Implement software interlocks (if required) A.M., M.B. 01.07.07 – –Implement operations panels A.M., M.B. 01.07.07 < D-4 weeks Commissioning at P2 – –Hand-over PVSS project to ACC for verific.& integrationS.S., M.B., A.M.D-4 weeks – –Install PVSS project in server at P2ACCD-2 – –Commission with sub-systems at P2 A.M., M.B. D-2 – –Commission the DETECTOR DCS with PHOS A.M., M.B. D – –Commission together with other detectors A.M., M.B.,VO +All D+?
3
2006 DCS planning, CPV (2) LV PS Pre-commissioning in Lab/CERN/SXL2 Who responsible Ready when? –Implement a “Lab setup”: PVSS-OPC-device M.B., A.M. 01.07.07 –Implement FSMM.B., A.M. 01.07.07 –Implement the PVSS configuration, archival and alarmsM.B., A.M. 01.07.07 –Implement software interlocks (if required)M.B., A.M. 01.07.07 –Implement operations panelsM.B., A.M. 01.07.07 < D-4 weeks Commissioning at P2 Hand-over PVSS project to ACC for verific.& integrat.S.S., M.B, A.M.D-4 weeks –Install PVSS project in server at P2ACCD-2 –Install, cable & commission the LV PS devices at P2V.V. D-2 –Commission the LV PS devices with detectorM.B., A.M. D D = 1-st Shut Down in 2008 (D - Date of the detector installation in the pit)
4
2006 DCS planning, CPV (3) HV PS Pre-commissioning in Lab/CERN/SXL2 Who responsible Ready when? –Implement a “Lab setup”: PVSS-OPC-device M.B., V.O. 01.07.06 –Implement FSMM.B., V.O. 01.07.06 –Implement the PVSS configuration, archival and alarmsM.B., V.O. 01.07.06 –Implement software interlocks (if required)M.B., V.O. 01.07.06 –Implement operations panelsM.B., V.O. 01.07.06 < D-4 weeks Commissioning at P2 Hand-over PVSS project to ACC for verific.& integrat.S.S., M.B, V.O.D-4 weeks –Install PVSS project in server at P2ACCD-2 –Install, cable & commission the HVPS devices at P2V.V. D-2 –Commission the HV PS devices with detectorM.B., V.O. D D = 1-st Shut Down in 2008 (D - Date of the detector installation in the pit)
5
2006 DCS planning, CPV (4) Temperature Monitor Pre-commissioning in Lab/CERN/SXL2 Who responsible Ready when? –Implement a “Lab setup”: CRW-DAQ A.M., M.B. 01.08.07 –Implement FSM A.M., M.B. 01.08.07 –Implement the PVSS configuration, archival and alarms A.M., M.B.01.08.07 –Implement software interlocks (if required) A.M., M.B.01.08.07 –Implement operations panels A.M., M.B.01.08.07 < D-4 weeks Commissioning at P2 Hand-over PVSS project to ACC for verific.& integrationS.S., A.M., M.B.D-4 weeks –Install PVSS project in server at P2ACCD-2 –Install, cable & commission the COOLING plant at P2V.V. D-2 –Commission the COOLING plant with detectorV.V., A.M., M.B. D D = 1-st Shut Down in 2008 (D - Date of the detector installation in the pit) GAS (Ar+CO2) Commissioning at P2 Who responsible Ready When? -- Hand-over PVSS project to ACC for verific. & integrationGWG1.08.06 -- Install PVSS project in server at P2ACC 1.08.06 -- Install, cable & commission the GAS system at P2GWG 1.08.06 -- Commission the GAS system with detectorS.S., V.V., M.B. D < D-4 weeks
6
Detector PVSS II Detector Ethernet Database(s) OPC client DIM client 3020 Detector (Ni100 sensors) 32 High VoltageLow VoltageTemp. Monitor User interface PVSS II HVLV PHOS-CPV Control room (ACR) [UI node] ELMB 27/10/05 CR4-Y10 SY2527 (2*A18833P) Ethernet E CR3 CAEN OPCserver PVSS II OPC client 1 UX-C16 Wiener E CR3 Wiener OPCserver PVSS II OPC client 3 CR3 PCI-CAN ELMB OPCserver PVSS II OPC client C 1 ACC 1 CR3 SG2 CR5 SG2 Gas system PLC Gas E Detector PVSS II DIP [GWG] Gas Gas PVSS 1 222
7
FSM of the CPV Detector
8
CPV Top Level Diagram
9
Wiener Crate State Diagram Wiener Channel State Diagram Wiener Control State Diagram Wiener State Diagrams
10
Start Menu PVSS II 3.1 Console
11
Launching of the CPV DCS, screenshots
12
CPV top level, screenshots
13
Manage Wiener LV PS
14
LV channel setting, screenshots
15
Wiener power supplies in the Lab
16
Devise Editor and Navigator, screenshots
17
NOT_READY -> GO_READY Remote Monitoring:
18
What is Ready & in Progress CPV FSM – in a good progress (the first prototype exists) LV Power supplies of the Wiener type – almost ready HV Power supplies of the CAEN type – TBD (the same as in HMPID) Temperature monitoring (ELMB) – TBD (the same as in PHOS) Gas system – almost ready (GWG) Connection of top the CPV Level with the top PHOS Level – TBD