PURBECK RAILWAY CIRCLE
2
Signal & Telegraph Dept.
“Signalling the Link” A presentation by Mike Walshaw, Swanage Railway Signal & Telegraph Dept.
3
Network Rail Partnership.
“Project Wareham” will see the Swanage Railway linked with the Main Line at Worgret Junction under a Swanage Railway – Network Rail Partnership.
4
Signalling Solutions Ltd
Show No.2 We look at the work being done by Network Rail and its contractor Signalling Solutions Ltd at Wareham and on the Swanage Branch Line.
5
Re-Signalling Project,
As part of the Poole to Wool Re-Signalling Project, Network Rail installed new crossover points at Wareham.
6
These dramatic pictures show the work done
on the night of 24/25 October 2012
7
The track train waits on the Swanage Branch
8
The new crossover points, pre-assembled off-site
9
Wareham Signal Box is to the left
Old track is lifted out. Wareham Signal Box is to the left
10
More track is lifted
11
Spent ballast is dug out
12
The new points are lifted into position
13
Hordes of workers get busy
14
More track is lifted
15
More spent ballast is lifted out
16
New ballast is shovelled into place
17
The track lining and tamping machine gets to work
18
The finished job ready for the next day’s trains
The finished job ready for the next day’s trains. But trains cannot yet cross over!
19
In December 2012, Network Rail renewed the points at Worgret Junction,
where the Swanage Branch leaves the Main Line
20
Here are the points at Worgret Junction before renewal
Here are the points at Worgret Junction before renewal. The Ground Lever Frame is in the tin shelter!
21
Engineers’ trains wait on the Main Line
22
Men at work at the Ground Frame
23
Heavy machinery at work digging out ballast
24
Rails are cut and lifted
25
Confusion reigns!
26
Spent ballast is dug out
27
Ballast is spread
28
Ballast is levelled.
29
The tamping machine at work
30
Just testing with a Class 66 loco!
31
Equipment Cabinets Swanage Railway
Network Rail have also installed Signals and Equipment Cabinets on the Branch Line for the link with the Swanage Railway
32
This will be the new Up Distant Signal near the Bridge over the River Frome.
33
This is where the signal is located
This is where the signal is located. The Bridge over the River Frome is in the background
34
At Wareham there is a Token Instrument Cabinet on each platform
35
On the Down Platform
36
And on the Up Platform
37
The Token Instrument Cabinet is the larger one
38
Photo credits: Andrew P.M. Wright, and Mike Walshaw
39
Token Block Signalling System between Norden and Wareham
Show No.3 will highlight the work done by the Staff of the Swanage Railway to introduce the new Token Block Signalling System between Norden and Wareham