Presentation is loading. Please wait.

Presentation is loading. Please wait.

The CSO Abatement Project Presented by: Paul Nordstrom Director of Operations and Engineering.

Similar presentations


Presentation on theme: "The CSO Abatement Project Presented by: Paul Nordstrom Director of Operations and Engineering."— Presentation transcript:

1 The CSO Abatement Project Presented by: Paul Nordstrom Director of Operations and Engineering

2

3 CSO CONTROL PROGRAM To be completed in three phases To be completed in three phases Phase 1 under construction and scheduled for completion in October 2008. Construction cost = $320 million Phase 1 under construction and scheduled for completion in October 2008. Construction cost = $320 million Phase 2 design to be initiated in August 2007 Phase 2 design to be initiated in August 2007

4

5 GENERAL LOCATION PLAN

6 COMBINED SEWAGE OVERFLOW- DIVERSION AND STORAGE

7

8

9

10 SITE S1 CONFIGURATION OF PUMP STATION OPERATING FACILITIES

11 S1 CONSTRUCTION SITE STAGING PERIOD: COMPLETION OF C6 TUNNEL LINING TO COMPLETION OF C6 CONTRACT CONTRACT C6 CONTRACT C14

12 FOUNDRY WORK SHAFT/ WOONASQUATUCKET INTERCEPTOR DROP SHAFT

13 Field’s Point WWTF Design Average Daily Flow – 45 MGD Average Daily Flow – 45 MGD Design Capacity – 65 MGD Design Capacity – 65 MGD Peak Secondary Flow Capacity – 77 MGD Peak Secondary Flow Capacity – 77 MGD Wet Weather Treatment Capacity (Primary Treatment and Disinfection) – 123 MGD Wet Weather Treatment Capacity (Primary Treatment and Disinfection) – 123 MGD

14


Download ppt "The CSO Abatement Project Presented by: Paul Nordstrom Director of Operations and Engineering."

Similar presentations


Ads by Google