What’s Next for the DoD Audit
Office of the Under Secretary of Defense (Comptroller) What’s Next for the DoD Audit Mr. Mark Easton, Deputy Chief Financial Officer, OUSD(C) Ms. Alaleh Jenkins, Director, OUSD(C)/FIAR Washington-ASMC NCR PDI March 3, 2015 v13
2
Agenda The Requirement: Why Financial Improvement and Audit Readiness (FIAR) Is Important FIAR Strategy and Audit Strategy: How We Are Meeting the Deadline Where Are We Now? FIAR Guidance and Timeline: Less Than Two Years Remain Your Role: How You Can Help Final Thoughts
3
The Requirement: Why FIAR is Important
4
It’s the Law The Chief Financial Officers Act of 1990: Created a CFO position within each cabinet-level agency, required all federal agencies to prepare timely and reliable financial statements for Congress and the Administration to use in managing and evaluating federal programs, and directed OMB to prepare a year Federal Financial Management Improvement Plan The Government Management Reform Act of 1994: Required annual auditable financial statements Refined Guidance: Sec NDAA FY 2012: Requires the plan to include the interim objectives and a schedule of milestones for each Military Department and Defense Agency to support the goal established by the Secretary of Defense that the SBR be validated for audit by not later than September 30, 2014 Sec NDAA FY 2010: requires the Department to develop and maintain a plan that ensures DoD financial statements are validated as ready for audit by not later than September 30, 2017 Continued interest from Congress, GAO, OMB, and the media
5
If DoD were a public company, would you invest?
Stewardship Stewardship Reassures the American public and Congress that the Defense Department is a good steward of its funds Demonstrates accountability Helps to safeguard assets and is a tool for guarding against fraud, waste, and abuse The DoD IG was unable to complete an audit and issued a Disclaimer of Opinion: “ … we could not obtain sufficient appropriate evidence to provide a basis for an audit opinion. Accordingly, we do not express an opinion on the DoD FY 2014 and FY 2013 Basic Financial Statements. Thus, the basic financial statements may have undetected misstatements that are both material and pervasive.” If DoD were a public company, would you invest?
6
History of Audit Efforts to Date
2017 FY 2017 Statutory Direction Achieve Full Agency Financial Statement Audit Readiness The Big Picture… …and Challenge 2014 FY 2014 Statutory Direction Achieve Audit Readiness of General Fund Statement of Budgetary Resources (SBR) 2009 Pre-2009 Audit emphasis largely within only the comptroller organizations Post-2009 Audit efforts involve all functional areas enterprise-wide Initial Priorities Established 2005 FIAR Office Established 1994 Initial DoD Efforts Began
7
FIAR Strategy and Audit Strategy: How We Are Meeting the Deadline
8
DoD Consolidated Audit Strategy Overview
DoD has developed a strategy to move to full financial statement audit by FY 2018 in accordance with the NDAA for FY 2010 The audit strategy builds on audit readiness momentum and demonstrates interim progress toward the FY 2018 target using a phased approach Propose that audits of select reporting entities’ financial statements be accelerated Other reporting entities will undergo progressively more complex examinations The phased approach will allow for continual growth and expansion of DoD’s audit infrastructure to support the increasing number of audits Strategy assigns each of DoD’s reporting entities to one of four categories: Tier 1: Large Caps (OMB Designated Entity Audits) Tier 2: Mid Caps (DoD Designated Audits) Tier 3: Small Caps (DoD Designated Examinations) Tier 4: Micro Caps (Remaining Defense Agencies, Organizations, and Funds (Not Material for Audit)) The Resulting DoD Consolidated Financial Statement Audit Starting in FY Will Likely Be the Largest Financial Statement Audit Ever Performed
9
The DoD Agency-Wide Audit Will Involve
Presenting Our Complete Portfolio Categories as Percentage of Total Budgetary Resources 0.9 % Not Material for Audit Tier 4 Tier 3 3.6% DoD Designated Examinations Micro Caps Small Caps WHS (Pentagon admin) DoDEA (education) MDA (missile defense) DARPA (R&D) DSCA (security cooperation) Many others Selected Activities in the Fourth Estate are participating in mock audits Tier 2 21.9% DoD Designated Audits Mid Caps Defense Logistics Agency DHA (healthcare) USTRANSCOM (transport) USSOCOM (special ops) DISA (IT / communication) Others already under audit Tier 1 73.6% OMB Designated Entity Audits Large Caps Department of the Army (GF and WCF) Department of the Navy (GF and WCF) (includes Marine Corps GF and WCF) Department of the Air Force (GF and WCF) Military Retirement Fund (MRF) Trust Fund U.S. Army Corps of Engineers (USACE)– Civil Works Entities in red are under audit
10
Audit Readiness Deal-Breakers
Fourth Estate reporting entities must be able to address a handful of “critical elements” or deal-breakers to support the proposed audit and examination schedule: Collect a universe of accounting transaction details reconciling the TI-97 accounting systems to the DoD financial statements Conduct reconciliations from source feeder systems where transactions occur and the DoD’s accounting systems and reconcile TI-97 Fund Balance with Treasury account to U.S. Treasury Complete IT controls discovery and corrective action for material financial systems Identify root causes for journal vouchers, eliminate unnecessary journal vouchers, and ensure all remaining journal vouchers are reviewed, approved, and supported by documentation Validate corrective action plans have been effectively implemented for critical internal controls processes Much of the effort related to addressing these deal-breakers requires strong participation from DFAS for success.
11
Where Are We Now?
12
Significant Progress Made
Although the Department did not achieve the September 30, 2014, Statement of Budgetary Resources deadline, significant progress was made. Military Departments asserted audit readiness on their services’ General Fund Schedules of Budgetary Activity Audit contracts awarded December 2-4, 2014 Audits began in January 2015 Audits will include financial transactions related to appropriation received in FY2015 and will not include financial transactions related to appropriations received in prior fiscal years DoD OIG oversees the IPA-conducted SBA audits Other Defense Organizations (ODOs) By June 30, 2014, each of the other Defense organizations asserted audit readiness of their applicable assessable units or of specific SBR line-items In FY 2015, the ODOs material to the DoD Consolidated Financial Statements will undergo with SBA mock audits or IPA examinations Over 90 percent of the Department’s FY 2015 General Funds will be under audit. Funds under audit represent most of the financial information reported in the SBR.
13
FY 2015 General Funds Planned for Audit
Over 90 % Currently Planned for Audit, but Remainder Involves Fourth Estate Organizations 4th Estate (TI-97) $132.21B (13.6%) Full Financial Statements General Fund (GF) Planned Under Audit in FY 2015 – $883.08B Military Retirement Fund (TI-97) $54.67B (5.6%) Full Financial Statements Payments to MRF DoD Component Level Accounts DHA, Contract Resource Management MERHCF (healthcare entitlement) Payment to MERHCF (healthcare) DCAA DeCA, General Fund Army (TI-21) $266.48B (27.3%) GF (SBA) 4th Estate (TI-97) $91.15B (9.4%) Not Under Audit Funds Provided by OSD to MilDeps DHA USSOCOM Foreign Allies Burden Sharing Defense Agencies (e.g., DLA, MDA, DCMA, DISA) DoD Field Activities (e.g., DHRA, DMA, DPMO, DTIC, DTSA, OEA) Other Defense Organizations (e.g., DAU, DOT&E, NDU, OIG) Military Housing Privatization Initiative Other Trust Funds U.S. Army Corps of Engineers- Civil Works (TI-96) $30.28B (3.1%) Full Financial Statements Air Force (TI-57) $187.77B (19.3%) GF (SBA) Navy (TI-17) $181.86B (18.7%) GF (SBA) Marine Corps (TI-17) $29.81B (3.0%) GF (SBR) FY 2013 Total Budgetary Resources
14
FIAR Guidance and Timeline: Less than Two Years Remain
15
Expanded Priorities and Guidance
With less than three years remaining, the Department has expanded its priorities from budgetary data to all financial transactions including: Valuing and reporting over $1 trillion in assets Accurately reporting environmental and other liabilities Preparing Working Capital Fund financial statements for audit Revised FIAR Guidance soon to be issued and will include: Requirements that apply to General Fund and Working Capital Fund statements Critical interim requirements, such as opening balances MilDeps and ODOs will update financial improvement plans accordingly Leadership and Governance Former Secretary Hagel and recently confirmed Secretary Carter, who previously served as Deputy Secretary, have continued to stress accountability, sound business and management systems, and audit readiness Deputy Secretary Work launched the DEXCOM and addressed leaders of the Fourth Estate Mike McCord sworn in as USD(C) and CFO Leadership is confident this expanded focus will keep the Department on the right path to full audit readiness.
16
Timeline to Move to Stand-Alone Audit
The five TI-97 reporting entities below will move towards stand-alone financial statement audits. Tier 2: Mid Cap Reporting Entities FY 2015 FY 2016 FY 2017 FY 2018 FY 2019 Forward DLA Examination – SBA (General Funds) Annual Audits – Full Financial Statements Defense Health Examination – SBA USSOCOM DISA Undergoing Internal Validation USTRANSCOM Continuing Audit Readiness Activities Examination – Full Financial Statements The Defense Agencies already under audit are not included in this list. The Defense Agencies already undergoing financial statement audit will continue to receive annual full financial statement audits.
17
Timeline to Move to Stand-Alone Examination
The 10 TI-97 reporting entities below will move towards stand-alone audit readiness examinations of their financial statements. Tier 3: Small Cap Reporting Entities FY 2015 FY 2016 FY 2017 FY 2018 FY 2019 Forward WHS Examination – SBA Annual Examinations – Full Financial Statements MDA DSCA Mock Audit DoDEA Other TI-97 Funds Provided to the Army DARPA ChemBio DTRA DCMA JCS
18
DoD Designated Audits – Tier 2:
Critical Path Audit Readiness Milestones Critical Path Audit Readiness Milestones Present assertion strategy for critical financial statement line items to FIAR Directorate (2/20/2015): Critical Line Items: Fund Balance with Treasury; General Property, Plant, and Equipment, including Real Property, General Equipment, and Internal Use Software; Inventory and Related Property, including Inventory and Operating Materials and Supplies; Environmental and Disposal Liabilities; and Other Line Items Material FIAR Directorate obtains DoD OIG/GAO approval on assertion strategy/methodology for critical line items (3/31/2015) Implement corrective action plans to address critical line items (4/30/2015) Undergo FIAR audit readiness validation (5/1/2015 – 5/31/2015) Implement corrective action plans to address deficiencies (6/30/2015) Undergo IPA financial statement audit (10/1/2015 – 11/15/2016)
19
DoD Designated Examinations – Tier 3:
Critical Path Audit Readiness Milestones Critical Path Audit Readiness Milestones Present assertion strategy for critical financial statement line items to FIAR Directorate (2/20/2015): Critical Line Items: Fund Balance with Treasury; General Property, Plant, and Equipment, including Real Property, General Equipment, and Internal Use Software; Inventory and Related Property, including Inventory and Operating Materials and Supplies; Environmental and Disposal Liabilities; and Other Line Items Material FIAR Directorate obtains DoD OIG/GAO approval on assertion strategy/methodology for critical line items (3/31/2015) Implement corrective action plans to address critical line items (9/30/2015) Undergo IPA examination (10/1/2015 – 3/31/2016) Implement corrective action plans to address deficiencies (9/30/2016) Undergo IPA examination (10/1/2016 – 3/31/2017) Implement corrective action plans to address deficiencies (6/30/2017)
20
Overview of Working Groups
Five Working Groups for Critical Balance Sheet Line Items: Real Property General Equipment Internal Use Software Inventory and Related Property Environmental and Disposal Liabilities The OSD Working Groups Were Established to: Address DoD-wide policy and process challenges to audit readiness Provide implementation guidance Review progress toward achieving audit readiness milestones Expectations: Address issues quickly to expedite solutions, and elevate issues where needed Estimating beginning balances Developing systems and process agreements to sustain asset and liability valuations OSD will vet decisions with the DoD OIG and GAO over the next 3 months; decisions targeted for June to allow for implementation
21
Your Role: How You Can Help
22
Roles and Responsibilities
Planning Phase Internal Control Phase Test Phase Report Phase Auditors Submit Document Requests to gain an understanding of operations and perform data analytics while planning the audit procedures Assess control risk and determine the nature, timing, and extent of control, compliance, and substantive testing Identify control weaknesses and, if appropriate, form an opinion and report on internal controls over financial reporting Plan the nature, timing, and extent of procedures to be performed on budgetary transactions and effectiveness of controls Perform substantive, control and compliance tests Issue Notices of Findings and Recommendations (NFRs) to outline problem areas within accounting, internal controls, IT systems, and business processes FM HQ Organizations Provide strategic guidance and technical expertise to consolidate and coordinate the audit response and communication across the organization Provide coordination and communication to facilitate a close working relationship between auditors, Commands, and functional owners Direct, oversee, and provide quality control and quality assurance for all audit response activity before delivery to the Independent Public Accountant (IPA) Communicate outcomes of the audit and coordinate NFR remediation and Corrective Action Plans (CAPs) implementation with assigned stakeholders Financial and Functional Owners Respond to Document requests – a function that will continue throughout the audit cycle Facilitate the review of internal controls and processes to include MICP and system access & segregation of duties, etc. Respond to sample data requests from the auditor in a timely manner and provide insight into the quality of line item supporting documentation Assigned stakeholders develop CAPs
23
Critical Success Factors
Tone from the Top Stress importance Emphasize deadlines Strong Audit Infrastructure Well organized audit support team Continual and effective communication Access to Supporting Documentation Correct, clear, and timely Auditor must be able to follow (plain English)
24
Setting Expectations Be Prepared Own Your Information Communicate
Auditor will interview personnel and observe operations Auditor will test account balances and trace to source All organizations, locations, processes, and systems may be subject to audit Assign point personnel for supporting documentation Expect large sample sizes for testing Own Your Information Provide correct audit evidence in a timely manner Be able to respond to an auditor’s questions Communicate Continually communicate with audit liaisons and your organizations Don’t assume auditors know your business…clear communication is key Embrace feedback
25
Final Thoughts
26
Final Thoughts This is a massive enterprise change management effort The scale of DoD’s consolidated financial statement audit is unprecedented DoD is much more like a country than a corporation There is significant value in moving into an audit regimen Until audit opinions become routine, sustained emphasis will be needed from: DoD senior leadership Congress Oversight organizations Budget stability is critical to our success This will be a multi-year effort Federal Government experience indicates this is a 3-5 year process once audits begin We plan to do better, but need to manage expectations The Department is Fully Committed to Improving the Quality of Our Financial Information and Achieving Audit Readiness
27
Stay Connected Visit the FIAR website Read the FIAR Plan Status Report
Read the FIAR Plan Status Report Subscribe to DCFO mailings by ing The Department is Fully Committed to Improving the Quality of Our Financial Information and Achieving Audit Readiness
28
Backup
29
Example Issues and Solutions in Development Solutions in Development
Real Property Example Issues and Solutions in Development Example Issues Solutions in Development Policy Issue – Unclear Financial Reporting Responsibilities The Department has struggled for years to develop a GAAP-compliant real property reporting policy that is also doable in a practical sense. Preponderance of use, operational control, and Title X have all been considered at various times. The group looked at options from GAAP compliance, audit risk, and operational perspectives. The pending solution focuses on the funding Component and Components that have exclusive use of a space. Implementation Issue – Valuation of Existing RP Assets Following significant Wave 3 (existence and completeness) work, a significant amount of the Department’s real property still lacks documentation to support historical costs. Leveraging SFFAS 35 (Estimating the Cost of PP&E), a methodology was developed by the group to use a deflated plant replacement value for existing real property. The methodology uses information already included in property systems, and can be quickly and consistently deployed across the Department. The result will be an auditable value for approximately 65% of the Department’s real property assets.
30
Example Issues and Solutions in Development Solutions in Development
General Equipment Example Issues and Solutions in Development Example Issues Solutions in Development Implementation Issue – Valuation of Existing Assets (Baseline) The Department lacks an auditable valuation methodology that can consistently be deployed across all Components. Using SFFAS 35, the group is developing an estimating methodology that includes the use of budget and contract documentation. The methodology will focus on identifying and allocating capitalized costs to end items using contract and budget data. Policy Issue – Contracts Do Not Differentiate Capital vs. Expense Major Defense Acquisition Programs include a significant percentage of DoD equipment value. Current program structures don’t isolate capital costs or associate them to specific end items. Major Defense Acquisition Programs will likely require some estimates to value equipment but should be minimized to the extent possible. This includes differentiating between capital and expense costs and liquidating construction in progress accounts as end items are delivered. New CLIN structures are being embedded in future acquisition contracts to map capital costs to end items.
31
Environmental and Disposal Liabilities
Example Issues and Solutions in Development Example Issues Solutions in Development Policy Issue – Required Support for Cost Models Cost models are used to estimate cost to complete. However, a recent audit of DLA E/L CTC highlighted the need for additional clarification to determine how models should be supported during an audit. The Group is reviewing RACER and NORM to determine appropriate procedures for validating and documenting model data sources, inputs, table updates, and supporting documentation, as well as responsibilities for supporting the audit. Implementation Issues – E&DL Completeness Challenge Environmental liabilities can be associated with DoD assets but can also exist outside fence lines or even in locations where the Department has not operated in 100 years. The group has developed a point of view on establishing a complete universe of E&DL that included several approaches. Establishing a complete universe may require more than one approach. Reconciling to APSRs Fence-to-fence survey Historical study Reconciling to other authoritative listings (e.g. EPA listings)
32
Example Issues and Solutions in Development Solutions in Development
Internal Use Software Example Issues and Solutions in Development Example Issues Solutions in Development Policy Issue – Terminology and Conceptual Gap Between FM and CIO Component FM and CIO organizations interpret SFFAS 10 and FMR IUS definitions in a variety of ways. Further guidance is needed for consistent application of the standards and financial reporting. The working group is collecting areas of misunderstanding or areas that lack clarity. For example, the SFFAS 10 IUS definition includes the term “operating system programs,” which CIO and FM personnel understand differently. This causes a significant disconnect in what IUS is reported and how. The group is also working with FASAB to help improve future guidance. Implementation Issue – Lack of a Complete IUS Universe IUS is dramatically underreported in many Components (e.g. Navy reports $5M in IUS on its GF balance sheet). To establish a baseline, a methodology is needed to identify the complete universe of IUS. A methodology is being developed to identify a complete universe of software by reviewing multiple software record repositories, such as electronic discovery reports, APSRs, contracts, and budget documents. Following the accumulation of a potential IUS universe, functional and FM personnel, reduce the list to potentially capital IUS. Lessons learned from Components that have completed this milestone will be briefed at the WG meetings.
33
Inventory and Related Property
Example Issues and Solutions in Development Example Issues Solutions in Development Policy Issue – Valuing existing OM&S Much of the Department’s OM&S predates the requirement for historical cost supporting documentation. As a result, an initial moving average cost cannot be supported without significant manual effort to estimate values. The group is working with the Federal Accounting Standards Advisory Board (FASAB) to consider other potential options. One option under consideration is the establishment of a baseline at latest acquisition cost (LAC) and using moving average cost (MAC) on a go-forward basis. 𝑀𝐴𝐶= 𝑆𝑡𝑎𝑟𝑡𝑖𝑛𝑔 𝐵𝑎𝑙𝑎𝑛𝑐𝑒+𝐻𝑖𝑠𝑡. 𝐶𝑜𝑠𝑡 𝑜𝑓 𝑁𝑒𝑤 𝐴𝑐𝑞𝑢𝑖𝑠𝑖𝑡𝑖𝑜𝑛𝑠 𝑄𝑢𝑎𝑛𝑡𝑖𝑡𝑦 Implementation Issue – Defining the “End User” for OM&S Components struggle to determine whether the purchases or consumption method is appropriate for OM&S. A significant contributor to this indecision is that there is no established criteria to define the “end user” of OM&S. The group is developing more specific criteria to help Components evaluate whether OM&S stored in locations such as on ships or field units can be expensed because they are in the hands of the end user or must be capitalized. Purchases Method “The purchases method provides that operating materials and supplies be expensed when purchased.” (i.e., no dollar amount reported on the Balance Sheet) Consumption Method “The cost of goods shall be removed from operating materials and supplies (i.e., the asset account) and reported as an operating expense in the period they are issued to an end user for consumption in normal operations.” (i.e., dollar amount of items held for issue is reported on Balance Sheet)