Presentation is loading. Please wait.

Presentation is loading. Please wait.

Integer Linear Programming

Similar presentations


Presentation on theme: "Integer Linear Programming"— Presentation transcript:

1 Integer Linear Programming
Chapter 6 Integer Linear Programming MT 235

2 Integer Linear Programming
All-Integer Linear Program All variables must be integers Mixed-Integer Linear Program Some, but not all variables must be integers 0-1 Integer Linear Program Integer variables must be 0 or 1, also known as binary variables MT 235

3 Integer Programming – All Integers
Northern Airlines is a small regional airline. Management is now considering expanding the company by buying additional aircraft. One of the main decisions is whether to buy large or small aircraft to use in the expansion. The table below gives data on the large and small aircraft that may be purchased. As noted in the table, management does not want to buy more than 2 small aircraft, while the number of large aircraft to be purchased is not limited. How many aircraft of each type should be purchased in order to maximize annual profit? Small Large Capital Available Annual profit $1 million $5 million Purchase cost $5 million $50 million $100 million Maximum purchase quantity 2 No maximum MT 235

4 Define Variables - Northern Airlines
Let: S = # of Small Aircraft L = # of Large Aircraft MT 235

5 General Form - Northern Airlines
Max 1S + 5L s.t. 5S + 50L <= 100 S <= 2 S, L >= 0 & Integer MT 235

6 Northern Airlines – Graph Solution
LP Relaxation (2, 1.8) Budget Small AC MT 235

7 Northern Airlines – Graph Solution
Budget Small AC Rounded Solution (2, 1) MT 235

8 Northern Airlines – Graph Solution
Optimal Solution (0, 2) Budget Small AC MT 235

9 MT 235

10 MT 235

11 MT 235

12 MT 235

13 Integer Linear Programming
All-Integer Linear Program All variables must be integers Mixed-Integer Linear Program Some, but not all variables must be integers 0-1 Integer Linear Program Integer variables must be 0 or 1, also known as binary variables MT 235

14 Integer Programming – Mixed Integer
Hart Manufacturing, a mixed integer production problem: Hart Manufacturing makes three products. Each product goes through three manufacturing departments, A, B, and C. The required production data are given in the table below. (All data are for a monthly production schedule.) Production Department Product 1 Product 2 Product 3 Hours available A (hours/unit) 1.5 3 2 450 B (hours/unit) 1 2.5 350 C (hours/unit) 0.25 50 Profit Contributions per Unit $25 $28 $30 Setup Costs per production run $400 $550 $600 Max Production per production run (Units) 175 150 140 MT 235

15 General Form – Hart Manu.
Let: X1= units of product 1 X2= units of product 2 X3= units of product 3 Y1= 1 if production run, else = 0 Y2= 1 if production run, else = 0 Y3= 1 if production run, else = 0 MT 235

16 General Form – Hart Manu.
Max 25X1 + 28X2 + 30X3 – 400Y1 – 550Y2 – 600Y3 s.t. 1.5X1 + 3X2 + 2X3 <= Dept. A 2X1 + X X3 <= Dept. B .25X + .25X + .25X <= Dept. C X1 <= 175Y1 X2 <= 150Y2 X3 <= 140Y3 Xi >= 0 Yi = integer 0,1 MT 235

17 MT 235

18 MT 235

19 MT 235

20 MT 235

21 MT 235

22 Integer Linear Programming
All-Integer Linear Program All variables must be integers Mixed-Integer Linear Program Some, but not all variables must be integers 0-1 Integer Linear Program Integer variables must be 0 or 1, also known as binary variables MT 235

23 0-1 Integer Linear Program (Binary Integer Programming)
Assists in selection process 1 corresponding to undertaking 0 corresponding to not undertaking MT 235

24 0-1 Integer Linear Program (Binary Integer Programming)
Allows for modeling flexibility through: Multiple choice constraints k out of n alternatives constraint Mutually exclusive constraints Conditional & co-requisite constraint MT 235

25 Integer Programming - Binary
CAPEX Inc. is a high technology company that faces some important capital budgeting decisions over the next four years. The company must decide among four opportunities: 1. Funding of a major R&D project. 2. Acquisition of an existing company, R&D Inc. 3. Building a new plant, and 4. Launching a new product. CAPEX does not have enough capital to fund all of these projects. The table below gives the net present value of each item together with the schedule of outlays for each over the next four years. All values are in millions of dollars. R&D Project Acquisition of R&D Inc. New Plant Launch New Product Capital Available Net Present Value (NPV) 100 50 30 Year 1 10 5 40 Year 2 15 60 Year 3 80 Year 4 20 70 MT 235

26 General Form – CAPEX Inc.
Let: X1= 1 if R&D Project funded, else = 0 X2= 1 if acquire company, else = 0 X3= 1 if build new plant, else = 0 X4= 1 if launch new project, else = 0 MT 235

27 General Form – CAPEX Inc
Max 100X1 + 50X2 + 30X3 + 50X4 s.t. 10X1 + 30X2 + 5X3 + 10X4 <= Yr 1 15X1 + 0X2 + 5X3 + 10X4 <= Yr 2 15X1 + 0X2 + 5X3 + 10X4 <= Yr 3 20X1 + 0X2 + 5X3 + 10X4 <= Yr 4 Xi = 0,1 MT 235

28 MT 235

29 MT 235

30 MT 235

31 MT 235

32 Review Problems Electrical Utility Distribution Co. Alpha Airlines
MT 235

33 Integer Programming - Review
Electrical Utility, a mixed integer set-up problem: A problem faced by an electrical utility each day is that of deciding which generators to start up in order to minimize total cost. The utility in question has three generators with the characteristics shown in the table below. There are two periods in a day, and the number of megawatts needed in the first period is The second period requires 3900 megawatts. A generator started in the first period may be used in the second period without incurring an additional startup cost. All major generators (e.g. A, B, and C) are turned off at the end of the day. (Assume all startups occur in time period 1.) Generator Fixed Startup Cost Cost Per Period Per Megawatt Used Maximum Capacity In Each Period (MW) A $3,000 $5 2,100 B $2,000 $4 1,800 C $1,000 $7 3,000 MT 235

34 General Form – Electrical Utility
Let: XA1 = Power from Gen A in Period 1 XB1 = Power from Gen B in Period 1 XC1 = Power from Gen C in Period 1 XA2 = Power from Gen A in Period 2 XB2 = Power from Gen B in Period 2 XC2 = Power from Gen C in Period 2 YA = 1 if Generator A started; else = 0 YB = 1 if Generator A started; else = 0 YC = 1 if Generator A started; else = 0 MT 235

35 General Form – Electrical Utility
Min 5(XA1+XA2) + 4(XB1+XB2) + 7(XC1+XC2) YA YB YC s.t. XA1 + XB1 + XC1 >= 2900 XA2 + XB2 + XC2 >= 3900 XA1 <= 2100YA XA2 <= 2100YA XB1 <= 1800YB XB2 <= 1800YB XC1 <= 3000YC XC2 <= 3000YC Xij >= 0 Yi = 0, 1 MT 235

36 MT 235

37 MT 235

38 MT 235

39 MT 235

40 MT 235

41 Integer Programming - Review
Distribution Company, a integer transportation problem: A distribution company wants to minimize the cost of transporting goods from its warehouses A, B, and C to the retail outlets 1, 2, and 3. The costs (in $’s) for transporting one unit from warehouse to retailer are given in the following table. The fixed cost of operating a warehouse is $500 for A, $750 for B, and $600 for C, and at least two of them have to be open. The warehouses can be assumed to have adequate storage capacity to store all units demanded, ie., assume each warehouse can store 525 units. Retailer Warehouse 1 2 3 A $15 $32 $21 B $9 $7 $6 C $11 $18 $5 Demand 200 150 175 MT 235

42 General Form – Distribution Co.
Let: Xij = units shipped from i to j YA = 1 if warehouse A opens, else = 0 YB = 1 if warehouse B opens, else = 0 YC = 1 if warehouse C opens, else = 0 MT 235

43 General Form – Distribution Co.
Min 500YA + 750YB + 600YC + 15XA1 + 32XA2 + 21XA3 + 9XB1 + 7XB2 + 6XB3 + 11XC1 + 18XC2 + 5XC3 s.t. XA1 + XB1 + XC1 = 200 XA2 + XB2 + XC2 = 150 XA3 + XB3 + XC3 = 175 XA1 + XB1 + XC1 <= 525YA XA2 + XB2 + XC2 <= 525YB XA3 + XB3 + XC3 <= 525YC YA + YB + YC >= 2 Xij >= 0 Yi = 0, 1 MT 235

44 MT 235

45 MT 235

46 MT 235

47 MT 235

48 Integer Programming - Review
Alpha Airlines, a integer scheduling problem: Alpha Airlines wishes to schedule no more than one flight out of Chicago to each of the following cities: Columbus, Denver, Los Angeles, and New York. The available departure slots are 8 A.M., 10 A.M., and 12 noon. Alpha leases the airplanes at the cost of $5000 before and including 10 A.M. and $3000 after 10 A.M., and is able to lease at most two per departure slot. Also, if a flight leaves for New York in a time slot, there must be a flight leaving for Los Angeles in the same time slot. The expected profit contribution before rental costs per flight is shown below (in K$) Time Slot Cities 8:00 AM 10:00 AM 12:00 Noon Columbus 10 6 Denver 9 Los Angeles 14 11 New York 18 15 MT 235

49 General Form – Alpha Airlines
Let: Xij= 1 if flight to i occurs in time slot j, else = 0 Yj = number of planes leased for time slot j MT 235

50 General Form – Alpha Airlines
Max 10XC1 + 6XC2 + 6XC3 + 9XD1 + 10XD2 + 9XD3 + 14XL1+ 11XL2 + 10XL3 + 18XN1 + 15XN2 + 10XN3 – 5Y1 – 5Y2 – 3Y3 s.t. XC1 + XC2 + XC3 <= 1 XD1 + XD2 + XD3 <= 1 XL1 + XL2 + XL3 <= 1 XN1 + XN2 + XN3 <= 1 XC1 + XD1 + XL1 + XN1 = Y1 XC2 + XD2 + XL2 + XN2 = Y2 XC3 + XD3 + XL3 + XN3 = Y3 Y1 <= 2 Y2 <= 2 Y3 <= 2 XN1 <= XL1 XN2 <= XL2 XN3 <= XL3 Xij= 0,1 Yj = INTEGER MT 235

51 MT 235

52 MT 235

53 MT 235

54 MT 235


Download ppt "Integer Linear Programming"

Similar presentations


Ads by Google