PLATO PLATO TOU KO MEETING H. Rauer (DLR PF) H. Kinter/A. Salado (Kayser-Threde)
2
2 Activities Mission selection in Feb. 2014 Payload industrial management is being assigned for “bridging period” and B1 Phase to Kayser-Threde Status of payload teams, PDC, PSPM is reviewed „Kick-off“ Phase B1: July 16/17
3
3 Activities since selection Consortium: Consortium working groups have (re-)formed: CCD working group (chair D. Walton) Data Processing Algorithms Working Group (chair: R. Samadi) Telescope Optical Unit Working Group (chair: R. Ragazzoni)
4
Data processing group 4 A Data Processing Algorithms Working Group has been re-initiated PLATO-ALGO (chair: Réza Samadi): in charge of the study and the definition of the on-board and on-ground data processing algorithms (L0/L1) provide specifications for the development of the on-board and on-ground softwares The group includes members of the payload, PDC and PSPM teams
5
Telescope Optical Unit group 5 TOU team (chair: Roberto Ragazzoni): First meeting in B1 phase is scheduled on June 11 in Catania update on the status plan the next study phases.
6
Upcoming meetings 6 1 st P/L Meeting has been May 06/07, 2014 @ DLR, Berlin Consortium kick-off meeting on July 16/17, 2014, @ DLR, Berlin PDC meeting July 15, Berlin TOU meeting June 11, Catania, Italy 2 nd P/L Meeting proposed Fall 2014 Workshop on planet formation, Sept., London PLATO 2.0 Science Workshop December 2014, Italy
7
7
8
Image Copyright: Mark A. Garlick. Science Credit: Carole Haswell & Andrew Norton (The Open University) PLATO Camera Management Support Overview
9
KT Team Organization and responsibilities Main Phase B1 Preparation Activities B1 Schedule Overview: KT Questions to TOU team Agenda
10
PLATO Payload Consortium
11
PLATO Payload Management Key Personnel NameFunction Richard HaarmannPIPM Bernd SchulzPA/QA Manager Alejandro SaladoPayload Sys. Engineering (PTC) Hilda Kinter Camera Project Manager (CPM) PIPM Deputy Valery MogulskyCamera Systems Engineering Roberto MontedoriPayload AIV Manager (PAM) Gisbert PeterDPS Project Manager (DLR)
12
Camera Management at Kayser-Threde: Key Personnel roles and responsibilities defined Support the TOU in the preparation of phase B1 Interface to Camera consortium members Technical and managerial contact points Main Phase B1 Preparation Activities
13
Phase B1 Planning Detail roadmap until KO Phase B1 and beyond Synchronization of all partner activities Major Milestones for the Phase B1 Main Phase B1 Preparation Activities DateEvent 15.-16. July 2014Phase B1 Kick-Off March 2015PLATO Design Consolidation Review (PDCR) October 2015PLATO B1 data package delivery for SRR November - December 2015PLATO System Requirements Review (SRR) March 2016Mission Adoption & IPC approval April 2016Kick-off Phase B2/C/D January 2024PLATO Launch
14
Preparation B1 Kick-Off Data Package Main Phase B1 Preparation Activities Establish an updated Specification Tree to define the interrelation between the single PLATO P/L component specifications Basis for the traceability of single requirements and interface management Definition of all required documents for the B1 Kick-Off Comparison with existing documentation to identify necessary inputs Completion / annotation of existing specifications Utilization as applicable documents for the B1 work upon PDCR
15
1 st P/L Meeting has been on 06./07.05.2014 – –Bring P/L consortium together – –Start to resume P/L teams Phase B1 KO is scheduled for 16./17.07.2014 – –Official Start of Phase B1 – –All work packages are already defined – –Tasks to be done between KO and 2 nd P/L Consortium Meeting will be defined 2 nd P/L Meeting proposed Fall 2014 – –All specifications and belonging annotations/supplements are available as basis for the B1 development work Phase B1
16
PLATO Phase B1 Schedule
17
Overview of major Phase B1 Deliverables MeetingDateDeliverables KO16.07.14* Drafts of TOU Requirements Specification, Camera Development & Verification Plan, List of Deliverables, 2nd P/L Meeting15.09.14* First issue of above documents PM118.11.14Progress report + specified deliverables PM220.01.15Progress report + specified deliverables PDCR delivery02.03.15Progress report + specified deliverables PM312.05.15Progress report + specified deliverables PM421.07.15Progress report + specified deliverables PM522.09.15Progress report + specified deliverables SRR delivery02.11.15Camera Reports, models, Camera URDs and I/F documents * drafts to be prepared by KT Specified deliverables defined in the List of Deliverables, which may include Camera Reports (design, budgets, performance, straylight, thermal, structural, risk assessment), MAIV plan, Management Plan, mathematical models
18
Communication between TOU team and KT List of all deliverables to be defined and finalised by 2 nd P/L Meeting PMs to be held at TOU site or by Webex. Required documents and Progress Reports including status of AIs to be delivered at least five working days before the meeting Regular bi-weekly telecons between TOU lead team and KT: brief discussion of working progress, identified problems, needed inputs etc the traceability of single requirements and interface management Meeting when necessary with other Camera/Payload/PLATO teams by Webex (organised by KT). For critical topics, like I/F discussions, face to face meeting are preferable
19
Goals Phase B1: To achieve a sufficient level of technical maturity to ensure a successful SRR. system requirements for the selected architectures successfully validated system requirements derived confidence on the readiness levels of various technologies. Payload Camera Subsystem Status Summary: Goals Phase B1 consolidating the requirements on system and subsystem level and their traceability consolidating internal interfaces, assessing requirements for external interfaces consolidating performance models consolidating and defining operational modes of the payload and its various subsystems and components. validating the set of system and subsystem requirements Establish a verification strategy consistent with programmatic limitations and required scientific value. Develop technology maturation programs in order to achieve the required TRL levels at SRR
20
Team? Several Institutions (INAF, Univ. Bern, Stockolm Obs., Univ. Firenze) + Industrial Partners (Selex, Medialario-Sagem, Seso, RUAG, APCO Technologies) led by INAF (Interface to Camera team) Current Status? – –Optical Design + options available – –Breadboard/Prototypes: TOU AIV procedure already performed (TOU Optical and Thermal Performance) – –Further Breadboard with AIV and thermal behavior identified AIV procedures under development with serial production in mind Next Steps? – –Answer MEMO questions Telescope Optical Unit (TOU) Status Summary:
21
Image Copyright: Mark A. Garlick. Science Credit: Carole Haswell & Andrew Norton (The Open University) Issues/questions to the TOU Team
22
Questions to/inputs from TOU team: – –List of TOU team including percentage allocation for PLATO – –Is there a Central point for Camera document collection? – –List of available technical documents: – –List of MEMO Questions Component I/Fs Operational modes, states, and transitions Performance models or simulators Behavioural models or simulators Performance wrt requirements Model philosophy Assumptions employed in analyses Requirement specification Open issues and decisions Current risks and their mitigation strategies Main Phase B1 Preparation Activities