Bond Construction Update Citizen’s Oversight Committee Long Beach Community College District January 31, 2011 EDUCATE ENGAGE EMPOWER 1
2
Agenda Completed Construction Projects District Wide – Electronic Signage Plan Current Construction Projects LAC Building A – Student Services Retrofit LAC Parking Structure LAC Building O Complex LAC Infrastructure Improvements Project and District Wide – Energy Efficiency Project LAC Building I (Bookstore) LAC South Walkway Extension PCC MDAB (Multi-Disciplinary Academic Building) PCC Walnut Ave. Arrival Court District Wide – Monument Signs Upcoming Construction Projects LAC W Trailers Demo PCC Building CC Retrofit Q & A 2
3
Completed Construction Projects District Wide – Electronic Signage Plan Measure E 2008 Measure E 2008 3 District Wide Signage Plan complete for LAC & PCC Construction completed Fall 2010
4
Current Construction Projects LAC Building A – Student Services Retrofit Measure E 2008 4 Adds 6,500 Sq. Ft. to existing building Notice To Proceed given to SMC Construction on 12/29/10 Will house A&R, Counseling, Health Services, Cashier, Transfer Ctr., etc. End of construction anticipated Summer 2012
5
Current Construction Projects LAC Parking Structure – Measure E 2008 5 Spaces for 900 Vehicles Finalizing installation of solar arrays, irrigation, signage, and data/telecom runs Anticipated end of Construction Spring 2011
6
Current Construction Projects LAC Building O Complex – Measure E 2008 6 Two structures totaling 87,000 square feet Occupants for Building O2 are Foundation, ERD, tenants, and ALCI (soon to come) Occupants for Building O1 will be IITS, BMT, and Warehouse Facility Anticipated completion February 2011
7
7 LAC Infrastructure Improvement Project and District Wide Energy Efficiency Project Measure E 2008 Current Construction Projects Total annual estimated savings of 1.5 mil. Kwh Project started Fall 2009; currently working on phase 6 (partial), 7, 8A, 9A (Landscape), and 10 (G and H Quad area) Majority of existing building HVAC systems to be upgraded and connected to the Central Plant Buildings G & H are connected Buildings B, C, D, E, and J will be scheduled in the next couple months Exterior lighting and controls upgrades All parking lots north of Lew Davis are on new system New Reclaimed Water tie-ins to irrigation still to come New gas lines installed for Buildings B, C, D, E, G, H, J, M, N, and P New domestic lines installed for Buildings B, C, D, E, F, G, H, I Trailers, J, K,L, M, N, P Anticipated end of construction Winter 2011
8
Current Construction Projects 8 Adds additional 4,000 square feet to existing building Architecture to match LAC Mediterranean Theme Notice To Proceed given to G2K Construction on 11/15/10 End of Construction anticipated Fall 2011 LAC Building I - Measure E 2008
9
Current Construction Projects LAC South Walkway Extension Measure E 2008 Measure E 2008 9 99% complete Currently going through final punch-list Continues Master Plan pedestrian corridor
10
Current Construction Projects PCC MDAB (Multi-Disciplinary Academic Building) Measure E 2002 and 2008 10 Notice To Proceed issued on 7/29/10 Currently in phase 1 of construction (DD and EE in construction) Portables for swing space installed Summer 2010 complete and occupied (MD Trailers) Project to be completed in two phases – estimated completion for DD and EE is Summer 2012
11
Current Construction Projects 11 UU/VV demo completed Currently grading site Site to be converted to a parking lot. Estimated end of construction Spring 2011 PCC Walnut Ave. Arrival Court - Measure E 2008
12
Current Construction Projects District Wide – Monument Signs Measure E 2008 Measure E 2008 12 District Wide Monument Signs Locations: LAC-Clark/Conant – installed January 8, 2011 PCC-20 th /Walnut Ave. – installation still to come Installation of building designators for LAC Bldg. O1 and O2 completed Estimated construction completion Spring 2011 LAC Bldg. Designator LAC Monument Sign PCC Monument Sign
13
Upcoming Construction Projects 13 Design for site completed W Trailers to be demolished Site to be converted to a parking lot and a bio-swale Board of Trustees approved on 1/18/11 to Green Giant Notice to Proceed to be issued once docs have been submitted by contractor LAC W Trailers Demo - Measure E 2008
14
Upcoming Construction Projects PCC Building CC Retrofit - Measure E 2008 14 Houses the Fitness Center, Gymnasium, Weight Room, and Faculty and Staff Offices Swing space located on PCC Campus (Bldg. GG) Approved by DSA on 1/27/11. Bid process to commence shortly To be completed concurrently with MDAB project phase 1 Anticipated end of construction 2012
15
l i b e r a l a r t s Liberal Arts Campus Site Plan
16
p a c i f i c c o a s t Pacific Coast Campus Site Plan
17
QUESTIONS & ANSWERS EDUCATE ENGAGE EMPOWER 17