THE DEVELOPMENT OF LABUAN WATER-SUPPLY GIS (LWS GIS)
By Ir.Noor Azahari Zainal Abidin 4/11/2017
2
Location Map
3
Labuan Island FEDERAL TERRITORY OF LABUAN
4
CONTENTS OBJECTIVES OF LWS GIS CHRONOLOGY OF IMPLEMENTATION
GIS DEVELOPMENTS NETWORK HYDRAULIC SIMULATION & MODELING UPGRADING LWS-GIS & CREATION OF NRW CONTROL MANAGEMENT SYSTEM CURRENT & FUTURE LABUAN’S WATER SUPPLY MANAGEMENT SYSTEM 4/11/2017
5
LWS-GIS OBJECTIVES - AS A SOURCE OF DATA AND INFORMATION
- TO INCREASE OPERATIONAL EFFICIENCY OF LABUAN WATER SUPPLY SYSTEM FOR STATISTICAL AND FUTURE PLANNING FOR ENGINEERING APPLICATIONS USING GEOSPATIAL ANALYSIS 4/11/2017
6
Chronology of LWS GIS Development
Year GIS Developments 1996 Identifying GIS needs/applications, schematic database design and procurement of Base Map 1997 Tender No.1 - The setting up of Basic Micro-Computer System 1998 Tender No.2 - Database design & data capture 2000 Tender No.3 – Customizing for GIS Applications 2004 Tender No.4 - Enhancing Hydraulic Pipe Modeling & Design Module (still using ArcView Project File & Aquanet) 2009 Tender No.5 - Upgrade existing GIS, hydraulic modeling using Infoworks, creation of an Integrated Management System for NRW using NETBASE. 4/11/2017
7
Location : 8 km West of Sabah Area : 90 km.square Year 2000 GIS Data
* 07/16/96 Location : 8 km West of Sabah Area : 90 km.square Year 2000 GIS Data Population : 50,000 No. of Connections : 10,000 Daily Demand : 22,730 m3/day Total Length of mains : 350 km 4/11/2017 *
8
Year 2012 GIS Data Population : 80,000 Nos of Connections :14,847 Daily Demand : 54,000 m3/day Total Length of Mains : 540 km
9
WITHIN ArcVIEW PROJECT FILE)
GIS DEVELOPMENTS 1996 – 2004 (ALL CUSTOMIZATIONS WITHIN ArcVIEW PROJECT FILE) 4/11/2017
10
LAYANGAN PROCUREMENT BASE MAP, DATA CAPTURE OF PIPES,
SLUICE VALVES, HYDRANTS, PIPE ENDS. WATER METERS ETC. LAYANGAN 4/11/2017
11
Creating Relational Database (using ArcView 3)
* 07/16/96 Creating Relational Database (using ArcView 3) 4/11/2017 *
12
GIS DEVELOPMENTS 1996 – 2004 FILING SYSTEM MAP PRODUCTION
JKR Labuan.apr an ArcView project file had been customized to perform the following functions. FILING SYSTEM MAP PRODUCTION LEAKAGE RECORDS REGISTRATION HYDRAULIC ANALYSIS & MODELING
13
FILING SYSTEM – LINKING SHAPE FILE
CUSTOMIZED POP OUTS FOR FILE LINKAGE
14
LINKING AUTOCAD FILE LINKING VIDEO FILE LINKING IMAGE FILE LINKING TEXT FILE
15
MAP PRODUCTION FILLING INFORMATION
16
MAP PRODUCTION PREVIEWING & EDITING MAP PRINTOUT
17
REGISTERING PIPE’S LEAKS/BURST RECORDS
LOCATIONS OF LEAKS/BURST
18
REGISTERING PIPE’S LEAKS/BURST RECORDS
INSERTING NEW RECORDS
19
LEAKS/BURST RELATIONAL DATABASE
ATTRIBUTES
20
Pipe Hydraulic Simulation & Modeling
Assemble to form pipe network ( 2 ) Assign Elevation Data To Pipe Fittings & Demand Nodes ( 9 ) GIS Pipe Database ( 1 ) Proofing of Network With on-site inspection ( 3 ) Initial Pipeline Model ( 5 ) Update GIS Database ( 4 ) Carryout Hydraulic Simulation ( 11 ) Insert Flow Pattern ( 10 ) Assign each meter consumption To Demand Node ( 8 ) Calibrate & Validate Model base on Measured flow & pressure ( 13 ) Field’s Measurement ( 12 ) Calibrated Pipeline Model Update and Check Metering Database ( 7 ) Create Demand Node & Demand Polygon ( 6 ) 14. Customized All the Above into Labuan GIS
21
Pipe Hydraulic Simulation
& Modeling
22
Hydraulic Simulation Customization
WARIS-DATA Updating View WARIS Tool Menu
23
EXPECTED BENEFITS OF NETWORK MODELING
Distribution Study Done In-House Tool for Troubleshooting Network Problems External Linkage With SCADA System For Network Modeling Quick Assessment Of Distribution System Pipe Flow/Pressure NETWORK MODELING Ensure Minimum Water Quality by Network Simulation Efficient Water Supply Distribution Locate Areas of Low Pressure For Upgrading Planning For New Supply Areas Other Research Studies
24
AN INTEGRATED MANAGEMENT SYSTEM FOR NRW CONTROL
YEAR UPGRADING OF LWS GIS & CREATION OF AN INTEGRATED MANAGEMENT SYSTEM FOR NRW CONTROL USING NETBASE 4/11/2017
25
Scope of Works Upgrade & update Existing GIS DMA Design & Construction
Hydraulic Modeling Using Infoworks Integrated Water Distribution Management System Using NetBase Recommendation for Consumer Meter Replacement Active Leakage Detection
26
GIS System Upgrading Supply & install ArcGIS Software (ArcGIS Server, ArcEditor & ArcView). Purchased new Cadastral Base map Purchased Satellite Image Updated Pipe Registration (added 137 km pipes) Geo-Coded all 14,800 consumer meters.
27
An Integrated Water Distribution Management System Using NetBase
Integrated with Logger & Telemetry System Water Supply Input Flow-meters at WTP & Import Terminal Reservoir Outlet time series data DMA Flow and Pressure time series data Storage Tanks Level time series data Integrated with Corporate Data Sources GIS System incl Pipe Registration & Consumer Geo-Coding Consumer Billing System Hydraulic Modeling
28
Netbase Concept Corporate Data Sources
Required for Supply, Demand Balance & Leakage Add for Modelling, AMP, LOS Netbase 28
29
Summary of Established DMAs
No DMA DMA Name No of Properties Pipe Length (km) 1 DMA.01 Ranca-Ranca 1,505 38.8 2 DMA.02 Arsat 778 15.8 3 DMA.03 SGI 93 10.7 4 DMA.04 Kerupang 2,741 64.5 5 DMA.05 RMAF 2.9 6 DMA.06 Membedai 196 21.2 7 DMA.07 Layangan 847 32.4 8 DMA.08 IPS Layangan 417 14.8 9 DMA.09 IPS Pohon Batu 587 23.9 10 DMA.10 Pohon Batu 772 43.6 11 DMA.11 UMS 330 13.1 12 DMA.12 Kiamsam 2,505 37.2 13 DMA.13 Bandar 1 790 21.4 14 DMA.14 Bandar 2 691 16.5 15 DMA.15 Bandar 3 1,847 42.5 TOTAL LABUAN 14,100 399.3
30
DMA.02 ARSAT – STV Record Plan
DMA.02 - Jln.Arsat Service Reservoir Supply Area DMA.02 ARSAT – STV Record Plan STV 6 STV 8 STV 7 STV 4 STV 5 STV 1 STV 2 STV 3
31
CURRENT & FUTURE LABUAN’S WATER UTILITY MANAGEMENT SYSTEM
GIS SCADA Aset & Inventory Info System Non Revenue Water - Existing application Water Crisis Management Sys. Water Billing System Customer Complaint & Support System Network Modeling - Existing application Water Resource Management Sys. Water Quality Surveillance Water Network & Operation Management Sys. Planning Water Maintenance Management Sys. NETBASE
32
THE END 4/11/2017