Harding Elementary School Exterior Repairs & Select Roofing Replacement 08/12/2014
3
General ContractorBest Contracting Services, Inc. Architect of RecordGrossman Design Group Construction ManagerWillie Robinson
4
Contract Amount $918,600 Notice of Award06/17/14 Notice to Proceed07/21/14 Duration56 days Completion Date09/15/14
5
Contractor has mobilized & installed site surveillance Set up stairs & scaffolding to access roof and walls for demolition Demolition of exterior walls Removal of windows on west side of building A
6
Removal of Cement Plaster at Exterior Wall
8
Removal of Existing Window at Exterior Wall
9
Scaffold Installed at Rear Courtyard to Access Roof
10
Guardrail Installed at Lower Roof
11
Play Yard Equipment Protection