2
Provide a safe crossing and maintain mobility › The bridge is identified as structurally deficient. Meet regional traffic demands and improve mobility along the US 202 corridor › The existing bridge does not meet current design criteria for the amount of traffic.
3
Replace and widen existing bridge Improve Limekiln Pike approach to Butler Avenue Add right turn lane to Butler Avenue onto W. Main St. Upgrade signals Install ADA ramps Temporary Pedestrian Bridge
8
E&S measures staged to coincide with traffic control plan. Include: › Access road, on PennDOT property › Causeways accessing the bridge for construction › Cofferdams: in the stream › Sediment Basin / Stormwater Management Basin