Roadbed Instability Problems Chapter 19
2
Roadbeds built years ago Crude Methods Seasoned Time and Loading Problems Sinks Soft Spots Water Pockets Slides Subsidence
3
Instability leads to— Increased Maintenance Costs Slow Orders Reduction in Track Capacity Derailments
4
Typically a Soils/Drainage Problem Increase Strength/Stability of Soil Lower Moisture Content/Lower Plasticity Improve Drainage Separate Trackbed Support Layers
5
Divide Discussion into Three Parts: Subsidence Problems Slope Stability Problems Subgrade Support Problems
6
Subsidence Vertical Settlement Soil too Weak Occurs on Fills Weak Soils Shear Compresses
8
Height of Fill Should not exceed bearing capacity of soil, q d Normally a problem with fine-grained soils Or
9
Corrective Measures: Lower the Grade Excavate and Replace Allow for Settlement Use Surcharge Lower Water Table Relocate Line
10
(a) Excavation of much to firm ground; (b) overloading fill to accelerate settlement
12
Slope Stability—horizontal component Shear—upper Foundation—lower Sidehill Slides—lubricated surface
13
Shear—Slope of fill too steep Solutions: Flatten slope Surcharge toe Improve drainage
14
Foundation—too weak Solutions: In-place stabilize foundation Surcharge toe Lower ground water table
15
Solutions: Intercept drainage Retaining wall Pile and pole driving Sliding of sidehill fill
19
General Comments: Saturation Adjust Slope Rock Falls in Cuts Adjacent Disturbances High Water/Drawdown during Floods
20
Subgrade Support Too Weak to Support Loads Ballast not Properly Restrained Water/Ballast Pockets Develop Frost Heaving more Pronounced
26
Stabilization Solutions Improve Drainage Diversion ditches—Intercept Conveyance ditches—lateral and longitudinal French drains Deep ditching—lower water table
27
Soil Additives Blend in during new line construction Pressure inject in existing lines Advanages Increase strength—cementing Lower plasticity—base exchange Reduce affinity for water—lower PI
28
Geotextiles (Filter Blankets) Variable Success Must have drainage outlet Must protect GeoWeb is more effective
29
Separation mat or layer Asphalt successfully utilized Separate ballast from subgrade Confine ballast Waterproof subballast/subgrade Distribute reduced pressures Provide Consistent Support