Reducing THM via Aeration: A Case Study November 21, 2013 by Gary Williams, P.E. Jones & Henry Engineers Southeast AWWA District Meeting 1
2
Agenda Location History Pilot Implementation Take Away Information 2
3
Location Map 3
4
Distribution System Map 4
5
5
6
Water Quality 2008 Raw Water Total Hardness285 mg/L as CaCO 3 Total Alkalinity133 mg/L as CaCO 3 pH8.2 Turbidity3.2 Total Organic Carbon4.5 mg/L Finished Water Total Hardness150 mg/L as CaCO 3 Total Alkalinity36 mg/L as CaCO 3 pH9.2 Total Organic Carbon (average)2.1 mg/L TOC Removal (average)51% 6
7
THM 2008 7
8
Water History 1972 Water Treatment Plant, Low Head Dam, and Reservoir Constructed 1993 Water Treatment Plant Study 1996 Reservoir Study 1999-2000 Water Treatment Plant Expansion $3,000,000 2002 Second Reservoir $2,300,000 2004 Water Distribution System DBP Reduction Study 2005 Chlorine Dioxide Benchtop Study 2005 MIEX Benchtop Study 2006 RSSCT for GAC Benchtop Study 2008 THM Reduction via Aeration Opflow Article 8
9
2008 THM Reduction via Aeration Opflow Article 9
10
Research Limited Research Available for Dynamic System One Company Marketed a System $$$$$$$$ Air : Water Ratios (cfm : gpm) 5 to 60 If A:W = 40 and processing water @ 700 gpm = 28,000 cfm blower Approximately 200 hp Blower 10
11
Pilot Assumed 20:1 A:W ratio or 14,000 cfm Determined Approximate Area Diffusors for 14,000 cfm in Clearwell 2 Assumed One/half Depth of Clearwell or 7 feet Calculated the Volume over the Diffusors Developed the Detention Times in the Three Celled Clearwell Influent Cell60 minutes Aeration Cell75 minutes Effluent Cell60 minutes Scaled down the flows of air and water to match a 4-inch PVC pipe 11
12
Pilot 12
13
Test Pipe Arrangement Pilot Air Requirements Air: Water RatioRequired (cfm) Total Air (cf) 2:10.1 9.5 5:10.25 23.8 10:10.5 47.5 20:11.0 95 13
14
Pilot Protocol Two Pilot Steps First Step Test Entire A:W Range Second Step Optimize Results of the First Step Goal was to Optimize Air Required Parameters Tested TOC THM HAA5 Chlorine Residual Stability pH Total Alkalinity Total Hardness Calcium Hardness TDS Chlorides Sulphates 14
15
Pilot Results Air: WaterAir Rate Trihalomethane Results (ug/L) Ratio(scfm)October 14November 11 ControlN/A47.138.0 2:10.1016.916.7 5:10.255.79.0 7:10.35N/A6.7 10:10.502.15.7 20:11.002.7 30:11.502.6 40:12.003.0 50:12.502.1 15
16
Pilot Results 16
17
Other Pilot Results TemperatureOctober 16 deg CNovember 12 deg C Control Sample (no aeration) TTHM Initial – 52.6 ug/LFinish – 47.1 ug/L pHInitial – 9.3Aerated – 7.9 Cl 2 Free mg/LInitial – 2.13Aerated – 1.96 Cl 2 Total mg/LInitial – 2.45Aerated – 1.19 @ A:W ratio > 10:1 CHBrCl 2, CHBr 2 Cl, CHB 3 below Detectable Limit 17
18
Project Costs Aeration System 5:1 A:W ratio 3,500 scfm Blower Stainless Steel Diffusors Caustic Soda Feed System to increase pH to 8.9 12-inch Air Piping to Clearwell Diffusors Electric and Controls Project Cost - $401,700 Annual O&M - $73,000 GAC System Project Cost - $1,225,600 Annual O&M - $145,000 18
19
Brand X 2011 SolarBee Aeration System Proposal Two 15 HP Blowers 580 scfm Each Three Submersible Mixers 86 Diffusor Assemblies Caustic Soda Feed System to increase pH to 8.9 8-inch Air Piping to Clearwell Diffusors Electric and Controls Project Cost - $571,700 Annual O&M - $21,000 SolarBee Offer Install Clearwell Equipment Provide Temporary Blower and Piping 6-month Trial If Satisfied, Purchase Price $360,000 19
20
20
21
Second Thoughts April 1, 2012 SolarBee Oops Further Testing Showed Spray Aeration Preferable Highly Recommended Spray System One GS-12 Submersible Mixer in Clearwell 1 Two SN-15 Floating 15 HP Pump/Mixer/Spray Systems Two Ventilation 2HP Blowers 750 scfm Each Caustic Soda Feed System to increase pH to 8.9 12-inch Air Piping to Clearwell Electric and Controls Project Cost - $369,900 Annual O&M - $22,000 SolarBee Offer Provide In-Clearwell Equipment and Two Blowers Install Clearwell Equipment 6-month Trial If Satisfied, Purchase Price $168,000 21
22
22
23
Schedule Bid – October 2012 Preconstruction Meeting – November 2012 Substantial Completion – March 2013 Total Completion – June 2013 23
24
TTHM Summary 24 Sample Date Water Temp (deg C) Clearwell 1 Effluent Clearwell 2 Effluent DS202 (Max TTHM) % Removal In Clearwell #2 Regrowth in System 4/3/2013729.618.431.838%13.4 5/6/20131547.220.443.457%23.0 5/20/20131856.224.864.756%39.9 6/17/20132262.721.262.366%41.1 7/1/20132463.230.764.751%34.0 8/13/20132353.320.352.162%31.8 9/9/20132056.020.552.663%32.1 Note: Baffle wall opening sealed on 4/12/2013 (all values TTHM in ppb, except where noted)
25
Maximum Residence Time Running Annual Average 25
26
Take Away Information 1. THMs Have to be Formed Aeration Does Not Reduce Formation Potential 2. Chloroform is Typical Target THM 3. Powered Air Supply for Ventilation Probably Required 4. Check pH/Stability 5. Check Chlorine Residual 26