Coronado Elementary School Project Status Update 05/13/14.

Similar presentations


Presentation on theme: "Coronado Elementary School Project Status Update 05/13/14."— Presentation transcript:

1 Coronado Elementary School Project Status Update 05/13/14

2 Construction Manager:Cary Talbott (SGI) Project Engineer:Marcus Blackmon (Amanco) Inspector of Record:Kris Gilbert Architect of Record:Sisi Meng (WLC Architects) General Contractor: Lathrop Construction Associates

3 View: Southeast. Project Architect Rendering. Building A (2 Story Administrative Building). Main Drop-off. l

4 Project Architect Rendering of Playground (Conceptual)

5 The Coronado E.S. Reconstruction Project consists of 64,738 square feet of new classroom, administrative, multipurpose, kindergarten and support facilities. The Project also includes extensive site work, a bio-swale, site furnishings, covered walkways, State-of-the-Art Technologies, and a myriad of upgrades that will greatly enhance WCCUSD Student’s learning experience.

6

7  Project Duration:510 (Calendar Days)  Notice To Proceed Date: January 6, 2014  Completion Date:May 31, 2015  Percent Complete: 13%  Base Contract Amount:$26,974,910.00

8 View: Northeast. Activity: Clear & Grub; Demo. Coronado Elementary School Project View: Northeast. Activity: Clear & Grub: Demo.

9 View: Southwest. Activity: Mass Grading Coronado Elementary School Project View: Southwest. Activity: Mass Grading.

10 View: Eat. Activity: Lime Treat Soil for Building Pads only. Coronado Elementary School Project View: Eat. Activity: Lime Treat Soil for Building Pads only.

11 View: Northeast. Activity: Building Pad A (East) Layout. Coronado Elementary School Project View: Northeast. Activity: Building Pad A (East) Layout.

12 View : East. Building A. Activity : Excavate Trenches for Footings. Coronado Elementary School Project View: East. Building A. Activity: Excavate Trenches for Footings.

13 View: East. Building K (Kindergarten). Activity: Footing Placement Coronado Elementary School Project View: East. Building K (Kindergarten). Activity: Footing Placement

14 View: West. Building A. Activity: Preparation for Slab on Grade by placing vapor barrier and rebar. Coronado Elementary School Project View: West. Building A. Activity: Preparation for Slab on Grade by placing vapor barrier and rebar.

15 View: South. Building M (multipurpose room). Activity: Slab on Grade. Coronado Elementary School Project View: South. Building M (multipurpose room). Activity: Slab on Grade.

16 . Coronado Elementary School Project View: North. Building C (classrooms). Activity: Slab on Grade.

17 View: Southeast. Building M (multipurpose room). Activity: Structural Steel Erection. Coronado Elementary School Project View: Southeast. Building M (multipurpose room). Activity: Structural Steel Erection.


Download ppt "Coronado Elementary School Project Status Update 05/13/14."