1
Mid-Bay Bridge Connector Phase II and III December 2011 Project Update
2
Milestone Highlights - Start Date:February 14, 2011 - November Completion Date:January 28, 2014 - December Completion Date:January 28, 2014 - December CPM Schedule:Approved Time Highlights - Original Contract Day:298 of 1080 - Weather Days:3 - Change Order Days:0 - Total Contract Days:298 of 1083 Contract Amount Highlights - Contract Amount:$ 48,732465.03 - Change Order Amount:$ 25,000.00 - Fuel and Bits Adjustment:$ 343,237.83 - New Contract Amount:$49,100,702.86 - Amount Paid To Date:$ 14,969,680.06
3
Turkey Creek Bridge Rocky Creek Bridge Range Road Bridge Phase II Completion Dates
4
Range Road Bridge Range Road Bridge – Milestones
5
Range Road Bridge – Deck
6
Phase II Roadway (North of Range)
7
Rocky Creek Bridge Rocky Creek Bridge – Milestones
8
Phase II Bridge – Rocky Creek
9
Turkey Creek Bridge Turkey Creek Bridge – Milestones
10
Range Road Bridge Phase III Completion Dates SR285 Bridge Swift Creek Bridge Fox Head Branch Bridge Mill Creek Bridge SR85 Bridge
11
Range Road Bridge SR 285 Bridge – Milestones SR285 Bridge
12
Phase III – SR285 MSE Wall
14
Range Road Bridge Swift Creek Bridge – Milestones Swift Creek Bridge
15
Phase III – Bridge (Swift Creek)
16
Range Road Bridge Fox Head Branch Bridge – Milestones Fox Head Branch Bridge
17
Phase III – Bridge (Fox Head Creek)
18
Range Road Bridge Mill Creek Bridge – Milestones Mill Creek Bridge
19
Phase III – Bridge (Mill Creek)
20
Range Road Bridge SR 85 Bridge – Milestones SR85 Bridge
21
Phase III – Pond No. 14
22
QUESTIONS ?