Presentation is loading. Please wait.

Presentation is loading. Please wait.

Group 14 Jerrod Stock David Villers.  Location: between Tacoma and Gig Harbor, Washington  Total Length: 5,939 ft.  Longest Span: 2,800 ft.  Width:

Similar presentations


Presentation on theme: "Group 14 Jerrod Stock David Villers.  Location: between Tacoma and Gig Harbor, Washington  Total Length: 5,939 ft.  Longest Span: 2,800 ft.  Width:"— Presentation transcript:

1 Group 14 Jerrod Stock David Villers

2  Location: between Tacoma and Gig Harbor, Washington  Total Length: 5,939 ft.  Longest Span: 2,800 ft.  Width: 39 ft.  Clearance: 195 ft.  Construction: Sept. 27, 1938  Opened: July 1, 1940

3  Original plan made by Clark Eldridge - $11 million.  Redesigned by Leon Moiseiff with drastic modifications - $7 million.  Significant Modifications: 25 ft. deep trusses replaced by 8 ft. deep girders.  Bidding contractors complained about revised foundation piers. Original plans were shown, and they agreed.

4  “Creative Techniques” were used → packing girders with dry ice.  One death during construction.  “As soon as floor forms were started, oscillation occurred.”  Nicknamed “Galloping Gertie”

5  Tie-down cables from girders to 50-ton concrete blocks → snapped after installation.  Pair of inclined cable stays connected main cabled to deck at mid-span → ineffective.  Hydraulic buffers between towers and deck floor system → seals damaged when bridge was sand-blasted before painting.

6  Washington Toll Bridge Authority hired Professor Frederick Farquharson.  Conducted wind-tunnel tests on 1:200-scale bridge and 1:20-scale deck section models.  2 Solutions:

7  November 7, 1940 – 40 to 45 mph winds  7AM – Bridge begins transverse vibrations (3 ft. amplitude).  10AM – North cable collar loosens; violent torsional oscillations begin (28 ft. amplitude).  10:30AM – Bridge begins cracking.  11:10 AM – Center span collapses.

8  One fatality:

9  http://www.youtube.com/watch?v=lXyG68_c aV4 http://www.youtube.com/watch?v=lXyG68_c aV4

10  Convinced contractors to bid by showing plans for foundation piers that weren’t part of decided design.  Moisseiff’s design was new and hadn’t been modeled and tested:  8 ft. girders meant shallow roadway sections → bridge deck was insufficiently rigid.  Flat outward facing surfaces of girders weren’t aerodynamic.

11  Rejected initial conventional design based solely on cost.  Chose unproven design which had insufficient research. Combined Ethical Issue:  Opened bridge to public despite:  Oscillations which they knew would have to be fixed.  Early failure of vibration control systems.

12  Used a standard and proven design rather than the new “elegant” design.  Halted new design acceptance until a scale model was built and passed testing.

13  Shut bridge down or delayed opening until permanent solution was reached.  Replace hydraulic buffers to help stable bridge for construction of permanent fix.  Expedite Professor Farquharson’s research.  Then expedite implementation of determined solution.

14  Safety of users  Mechanical parts could cause injury:  Motors, gears, springs.  Prevention: Inner workings of devices are in sealed location. Necessary user input devices are away from moving parts.  Predictability of projectiles Prevention: Both automatic timed shut off and manual stop button.

15 ?


Download ppt "Group 14 Jerrod Stock David Villers.  Location: between Tacoma and Gig Harbor, Washington  Total Length: 5,939 ft.  Longest Span: 2,800 ft.  Width:"

Similar presentations


Ads by Google