Gasoline Spill Cleanup (Volatile Components) Rose Adam Allison Rose Adam Allison
2
Problem Statement To Design a System for Removing Harmful Petroleum Contaminants from a Spill at a Large Fuel Distribution Facility in Central Minnesota
3
Methods Determine Biodegradation for Natural Conditions Vapor Extraction System Design to remove volatile components from Soil Bio-filter to Breakdown Contaminants in Air Determine Biodegradation for Natural Conditions Vapor Extraction System Design to remove volatile components from Soil Bio-filter to Breakdown Contaminants in Air
4
Natural Attenuation through Biodegradation Benzene Breakdown in Natural Conditions µ = 0.0077 days^-1 -First Order Reaction Coefficient of Benzene -Reaction Pathways: Benzene Breakdown in Natural Conditions µ = 0.0077 days^-1 -First Order Reaction Coefficient of Benzene -Reaction Pathways:
5
Natural Attenuation through Diffusion Diffusion of Benzene chiefly through air pores in soil Partition coefficients of other diffusion possibilities unfavorable Diffusion of Benzene chiefly through air pores in soil Partition coefficients of other diffusion possibilities unfavorable Diffusion through a porous media (gasoline through soil) using C/C++ Applications
6
Total Natural Attenuation Or analytically
7
Time for Natural Attenuation
8
Soil Vapor Extraction Separates Contaminants from the Soil Air Injection Extraction Wells Increase System Airflow Vacuum Applied to Underground Wells To Remove Volatiles as Gas or Vapor Separates Contaminants from the Soil Air Injection Extraction Wells Increase System Airflow Vacuum Applied to Underground Wells To Remove Volatiles as Gas or Vapor Typical System Schematic:
9
Diffusion Coefficient in Moist Sand Determining Concentrations:
10
Ground-Water Pump Ground Water Located 4 ft Below Soil Surface A sump Pump will be Utilized to Lower the Groundwater Level Remove as much of the pure gasoline as possible Ground Water Located 4 ft Below Soil Surface A sump Pump will be Utilized to Lower the Groundwater Level Remove as much of the pure gasoline as possible
11
Typical SVE Flow System
12
Or analytically Forced Attenuation
13
Time for Forced Attenuation
14
Flow Rate: 76607m^3/day The system will replace the air filled porosity 1.2 times per day Assume ROI ~ 1000 m^2/well 15 Wells Required Flow Rate: 76607m^3/day The system will replace the air filled porosity 1.2 times per day Assume ROI ~ 1000 m^2/well 15 Wells Required
15
Number of Extraction Wells Required The team has determined that 15 wells will be required for the SVE cleanup system
16
Air-Forcing Pump Centurion II CP-HRV5-6 Specifications: * 5 Horsepower, Heavy Duty 1800RPM Motor * Champion Splash Lubricated RV15A Pump * Pump RPM 760 * Delivers 16.5CFM @ 175PSI or 19.1CFM @ 125PSI * Centrifugal Unloader for Loadless Starts * Dimensions: L=51 1/2, W=22 3/4, H=47 1/4 With a total required turnover of 76607 m^3 daily with 100 wells, 18.7 cfm is the minimum pump capacity. http://www.allensaircompressors.com/cart.php?target=product&product_id=16386&category_id=266
17
Biofilter Vapors extracted by the SVE process are typically treated using carbon adsorption, incineration, catalytic oxidation, or condensation. Other methods, such as biological treatment and ultraviolet oxidation, also have been used with SVE systems. The type of treatment chosen depends on which contaminants are present and their concentrations.
18
Governing Transport Equation Or analytically:
19
Bio-filter Pump http://www.bullard.com/Respi ratory/air_accessories/air_pu mps/index.shtml http://www.bullard.com/Respi ratory/air_accessories/air_pu mps/index.shtml Image and cfm data Electricity draw data Operating Cost: $0.068 / kw-hr http://www.bullard.com/Respi ratory/air_accessories/air_pu mps/index.shtml http://www.bullard.com/Respi ratory/air_accessories/air_pu mps/index.shtml Image and cfm data Electricity draw data Operating Cost: $0.068 / kw-hr
20
Design Specifications Number of Extraction Wells Biofilter Number of Extraction Wells Biofilter
21
Safety
22
Social Considerations Drinking Water MCL EPA Limit is 1ppb EPA suggestion is 0 ppb Beneficial to operate pumps longer than 6mo. if funds sufficient to lower concentration further. Drinking Water MCL EPA Limit is 1ppb EPA suggestion is 0 ppb Beneficial to operate pumps longer than 6mo. if funds sufficient to lower concentration further.
23
Cost Analysis Energy cost of water pump Pump Operating Cost ( at $0.068/kw-hr ) $109,572.48 Energy cost of air pump Capital cost of $1,538*100 Capital cost of well drilling Energy cost of water pump Pump Operating Cost ( at $0.068/kw-hr ) $109,572.48 Energy cost of air pump Capital cost of $1,538*100 Capital cost of well drilling