WG 2 Progress Report to TP#13 Group Name: oneM2M TP#13 Source: WG2 leadership Meeting Date: 2014-09-22/2014-09-26 Agenda Item: TP#13, Item 10, Reports.

Similar presentations


Presentation on theme: "WG 2 Progress Report to TP#13 Group Name: oneM2M TP#13 Source: WG2 leadership Meeting Date: 2014-09-22/2014-09-26 Agenda Item: TP#13, Item 10, Reports."— Presentation transcript:

1 WG 2 Progress Report to TP#13 Group Name: oneM2M TP#13 Source: WG2 leadership Meeting Date: 2014-09-22/2014-09-26 Agenda Item: TP#13, Item 10, Reports from Working Groups

2 Issues for DECISION in TP WG2 requests TP approval of the following CRs (agreed at WG2 level) for TS-0001 1.1.0 © 2013 oneM2M Partners 2 ARC-2014-1574R03AE-ID, App-ID CleanupLG Electronics ARC-2014-1542R02Annex GEricsson ARC-2014-1516R02attribute access modeLG Electronics ARC-2014-1582R01call flow correction_CSEBase_contentInstanceInterDigital ARC-2014-1573R01Clarification of schedule resourceLG Electronics ARC-2014-1569R02Clarification_TS0001_use_of_square_bracketsQualcomm Inc. (TIA) ARC-2014-1564R01Cleaning section 5 of TS0001 ALU, Ericsson, Qualcomm ARC-2014-1577R01Cleaning service subscriptionALU ARC-2014-1556R01cleanup accessControlPolicyLG Electronics ARC-2014-1557R01cleanup AELG Electronics ARC-2014-1558R02cleanup CSEBase remoteCSELG Electronics ARC-2014-1552R03Cleanup of ZTE, Huawei ARC-2014-1536R01Clean-up of Annex B NTT DOCOMO - Syed Husain ARC-2014-1522R02Clean-up of Clause 6 NTT DOCOMO - Syed Husain ARC-2014-1572Cleanup pollingChannel and pollingChannelURILG Electronics ARC-2014-1539R02Cleanup Section 7 IdentifiersQualcomm, Ericsson ARC-2014-1531R01cn in retrieve requestLG Electronics ARC-2014-1591R05contentInstance Update SupportLG Electronics

3 Issues for DECISION in TP WG2 requests TP approval of the following CRs (agreed at WG2 level) for TS-0001 1.1.0 ARC-2014-1521R02Corrections to Resource Type summary tableInterDigital ARC-2014-1595R03CR_TS-0001_Common_Attributes_clarificationInterDigital, ZTE ARC-2014-1543R02CSEResource-remoteCSE-editorialCorrectionEricsson ARC-2014-1551R02Discovery clean-upInterDigital ARC-2014-1565R01Local CSE and Registrar CSE_cleanupHaier ARC-2014-1520 m2mServiceSubscriptionProfile Resource Type CorrectionLG Electronics ARC-2014-1547R03Mandatory content in requests and responsesQualcomm Inc. (TIA) ARC-2014-1526R01 Modification of Clause 10.2.18 for conforming to new Resource Operation TemplateRajesh Bhalla, ZTE ARC-2014-1570R01modification-of-the-objectID-objectPath Huawei Technologies Co.,Ltd. ARC-2014-1559multiplicity of announcedAttributeLG Electronics ARC-2014-1562R01parentID clarificationLG Electronics ARC-2014-1571R02procedure-for-service-layer-managements Huawei Technologies Co.,Ltd. ARC-2014-1561R01resourceID clarificationLG Electronics ARC-2014-1566R01response message aggregationHaier ARC-2014-1550R01SCA Call Flow clean-upInterDigital ARC-2014-1549R01SCA resources clean-upInterDigital ARC-2014-1545R01Section9.4Ericsson ARC-2014-1546R01Section9.5Ericsson ARC-2014-1590R01Service Role CleanupLG Electronics ARC-2014-1533Slight revision at section 7.1KT

4 Issues for DISCUSSION in TP © 2013 oneM2M Partners 4 ARC-2014-1574R02 (AE-ID, App-ID Cleanup)AE-ID, App-ID Cleanup Comments & Issues Discussion occurred regarding the registration authority for an Application Identifier and its feasibility. Does the registration authority need to be defined? Questions are still outstanding regarding the Registration Authority; it was recommended the oneM2M Steering Committee be asked to examine the issue.

5 Items for INFORMATION Meeting objectives summary – Progress cleaning plan for TS-0001 - DONE – Progress TS-0007 towards stable content - DONE

6 Highlights WI-0002 TS-0001 Architecture – 38 agreed CRs for TS-0001 WI-0011 TS 0007 (Services) – 11 agreed contributions: © 2013 oneM2M Partners 6

7 Next Steps Drive TS0001 towards approval of 1.x.x by TP15. TS1.x.x will solely be based on essential corrections. Work shall: – Support Stage 3 (not only WG3) work with high priority – Improve the readability of specification Cleaning plan established and will rampup run until TP13 © 2013 oneM2M Partners 7

8 Open Action Items for alignment in TP © 2013 oneM2M Partners 8 Item #Document Number(S)Short nameSourceStatus A-PRO- 11.9-003 PRO-2014-0292 PRO-2014-0292 ARC-2014-1492 ARC-2914-1502 AE_CSE_ID_IssueShingo: Fujitsu & Others Open To be solved in WG2 A-PRO- 11.9-006 ARC-2014-1487 ARC-2014-1487 PRO-2014-0304R03 email Partial Updates – differentiate the primitivesNicolas: ALU, Qualcomm & Huawei Closed A-PRO- 11.9-013 PRO-2014-0374 PRO-2014-0384 ARC-2014-1547 Presence of attributes in response messageNobuOpen A-PRO- 12.4-001 PRO-2014-0489R01 PRO-2014-0488R01 Align the Recourse descriptions with the New template in Annex I AllOpen A-PRO- 13.0-001 ARC-2014-1592 Inter-release version negotiation at the APIMadhiOpen A-PRO- 13.0.003 ARC-2014-1595R01 ARC-2014-1596 Common Attributes Phil & Rajesh Open A-PRO- 13.0.003 PRO-2014-0496R01 Direct Upload/Download M2M dataShingo Open

9 Next Meetings / Calls © 2013 oneM2M Partners 9 ARC 13.1 Thursday 10/09/2014 12:00 - 13:30 GMT ARC 13.2 Thursday 10/16/2014 12:00 - 13:30 GMT ARC 13.3 Thursday 10/23/2014 12:00 - 13:30 GMT ARC 13.4 Thursday 10/30/2014 12:00 - 13:30 GMT