Sept. 30, 2004 NIKHEF-1 Hans de Vries Status NIKHEF Mechanics Secondary vacuum box Bellows Vacuum system CO 2 cooling: Bart Verlaat
2
Sept. 30, 2004 NIKHEF-2 Hans de Vries System overview Sec. vacuum box Rectangular bellow Vacuum vessel on stand
3
Sept. 30, 2004 NIKHEF-3 Hans de Vries Vacuum vessel Is being produced Thermo Electron Corporation Delivery: November Will be equipped with silicon insulated heaters from Watlow
4
Sept. 30, 2004 NIKHEF-4 Hans de Vries Center frame Accuracy and reproducibility: 2 μm; Complete opening/closing: 2 minutes
5
Sept. 30, 2004 NIKHEF-5 Hans de Vries Detector Lifting Device
6
Sept. 30, 2004 NIKHEF-6 Hans de Vries Transport trolley
7
Sept. 30, 2004 NIKHEF-7 Hans de Vries Detector installation rail
8
Sept. 30, 2004 NIKHEF-8 Hans de Vries Secondary vacuum box
9
Sept. 30, 2004 NIKHEF-9 Hans de Vries Secondary vacuum box (2)
10
Sept. 30, 2004 NIKHEF-10 Hans de Vries Measurements on box Mechanical performance –Tolerances, accuracy Vacuum performance –Leak rate Mechanical response to pressure differences Influence of torlon coating –Bake-out NEG coating (November)
11
Sept. 30, 2004 NIKHEF-11 Hans de Vries NEG coating The detector box in the vacuum vessel
12
Sept. 30, 2004 NIKHEF-12 Hans de Vries NEG coating (2) NEG coating will be tested at CERN in November
13
Sept. 30, 2004 NIKHEF-13 Hans de Vries Production bellows
14
Sept. 30, 2004 NIKHEF-14 Hans de Vries Testing of Bellows
15
Sept. 30, 2004 NIKHEF-15 Hans de Vries New bellows design Old camera bellows
16
Sept. 30, 2004 NIKHEF-16 Hans de Vries PLC programming Vacuum system SIMATIC manager step7 version V5.2+SP1 Simulation test conditions The vacuum simulator equipped with Altera EP20K200EQC240-3 chip, program language is VHDL
17
Sept. 30, 2004 NIKHEF-17 Hans de Vries Vacuum control cabinets
18
Sept. 30, 2004 NIKHEF-18 Hans de Vries Vacuum system
19
Sept. 30, 2004 NIKHEF-19 Hans de Vries Scheme evacuation set-up 400 l RF box Primary vacuum volume: 1700 liter Secondary vacuum volume: 500 liter Simulation volumes 1600 liter and 400 liter -Two vessels for NEG coating -Test set-up for integral leak test of bellows and RF box
20
Sept. 30, 2004 NIKHEF-20 Hans de Vries Membrane switches Modifications of the PS 115 - laser welded membrane - ref. vacuum separated from measuring chamber
21
Sept. 30, 2004 NIKHEF-21 Hans de Vries Membrane switches
22
Sept. 30, 2004 NIKHEF-22 Hans de Vries Valves
23
Sept. 30, 2004 NIKHEF-23 Hans de Vries Vacuum Test System Beam vacuum 1600 l Detector Vacuum 400 l PUMP ACP28 Venting Restrictions Membrane Switches Schakelaars MKS 120AA MKS 120AD Nupro Valves
24
Sept. 30, 2004 NIKHEF-24 Hans de Vries Vacuum test set-up
25
Sept. 30, 2004 NIKHEF-25 Hans de Vries Follow up evacuation set-up Assemble the set-up with the final parts Determine the resistance(conductance limiter) for RS 301 and RS 302 During evacuation test : registration of dP Optimize the conductance limiter with the dP Translate the result to the final experiment
26
Sept. 30, 2004 NIKHEF-26 Hans de Vries Venting procedure Total venting time: 90 minutes Actions membrane switches: 50 times
27
Sept. 30, 2004 NIKHEF-27 Hans de Vries Evacuation Total evacuation time: 300 minutes Actions membrane switches: 7 times
28
Sept. 30, 2004 NIKHEF-28 Hans de Vries Summary Good progress on realization components Vacuum vessel has been ordered: delivered in November New foils for secondary vacuum box have been produced New design bellows Vacuum system with membrane switches looks promising NEG coating will be tested: November