1
Benefits of having Optimal Technical Staffing & Supervision Structure for SSA Civil Works Sarva Shiksha Abhiyan Mission Gujarat
2
Need to develop school infrastructure on “Whole School Development Concept” Need to utilize available spaces effectively School Building has higher Importance Factor as per IS Code Widely spread and remote sites School Committee (Executive Agency) require technical guidance The ancillary works are Small in Size More in number. All activities require close supervision to achieve SSAM objectives. Need for Specialized Efforts
3
Task for Civil Wing STATE LEVEL General Administration Appointment of Engineers Training to Engineers Planning AWP&B Prioritization Convergence with other Dept./Schemes Procurement planning Designing Site Survey Architectural Design Structural Design
4
Tasks for Civil Wing STATE LEVEL (Contd.) Project Management Estimation Preparation of Bid Document Work Order to Districts (for VCWC Mobilisation) Bid Process Management Appointment of Consultants Consultant Civil Architect Consultant Structural Consultant Geo Technical Consultant 3 rd Party Consultant Supervision & monitoring of Civil Works Reporting of Physical & Financial progress to GOI & GOG.
5
Task for Civil Wing District Level Planning Process Finalization of activity list Formation of VCWC / DCWC Training to VCWC Members Fund Release to VCWC Supervision & monitoring of Civil Works Reporting of physical & financial progress to SPO
6
Tasks for Civil Wing School Level Community Mobilisation Supervision by Technical Resource Person (TRP) Verification of activity elements as per Drawing, Specifications & Checklist Progress Monitoring & Quality Audit by Third Party Inspection (TPI) Consultant Testing of construction materials by TPI Consultant Issue of completion certificate by TRP / 3 rd Party Consultant Reporting of physical & financial progress to DPO
7
Civil Works Management Structure at different levels State District Block / Village
8
State Level – Civil Works Management Structure
9
District Level Management Structure District Project Engineer Block – 1 (40 to 45 Sites) One TRP Block – 2 (80 to 90 Sites) Two TRP Block – 3 & 4 (40 to 45 Sites) One TRP 26 District Project Engineer, Min. One / District, if work is more than Two or Three D.P.E. / District.
10
Optimal Technical Staff SR. NO. ACTIVITYPHYSICAL NO.NO. OF SITE 1Additional Classroom26831121 2Toilet Block1021900 3Compound Wall1105 4Rain Water Harvesting75 5Major Repairing812 6Model school250 7Mid Day Meal-Kitchen Shed87347879 8Primary Teacher's Staff Quarters7212 9KGBV20 1477212174 Total Activity/Sites for Year 09-10
11
District wise Distribution of TRP SR.NO.DISTRICTNO. OF ACTIVITYNO.OF SITESNO.OF TRPSITES/TRP 1AHMEDABAD6414601142 2AMRELI420317745 3ANAND4834101041 4BANASKANTHA4454301236 5BHARUCH321270645 6BHAVNAGAR6024481237 7DAHOD4844071041 8DANG9778420 9GANDHINAGAR246223545 10JAMNAGAR8687501550 11JUNAGADH7735801248 12KHEDA11608902045 13KUTCH121610752445
12
SR.NO.DISTRICTNO. OF ACTIVITYNO.OF SITESNO.OF TRPSITES/TRP 14MEHSANA6485461150 15NARMADA287225545 16NAVSARI318270645 17PANCHMAHA5375251731 18PATAN230189632 19PORBANDAR287252463 20RAJKOT8247681745 21SABARKANTHA11188301749 22SURAT5374391237 23SURENDRANAGAR3733451131 24VADODARA139510572444 25VALSAD462390943 147721217428742 District wise Distribution of TRP
13
TRP Workload
14
Supervision System TRP40 to 45 sites Visit of 4 to 5 site per day Compulsory visit at lay out, plinth, lintel, slab & finishing level DPE10 to 12 days in a month Visit of 5 to 7 site per day Compulsory visit before releasing the installment & at the time of casting slab Monitoring cellTwo team 2 days in a week Visit of 4 to 5 site per day SPE5 to 6 days in a month
15
DPE/TRP Recruitment Selection Contract/Bond Remuneration Review Renewal
16
Hiring services of Professional Consultant Consultant hired Independent Third Party Inspection & Quality Assurance Structural Consultant Geotechnical Consultant
17
Salient features of ITPI Consultant shall visit 6 times single storey classroom 9 times multi storey classroom 5 times other civil works activity Mandatory visit for single storey Plinth level Casting of slab & beam Completion Stage Mandatory visit for Multi storey Footing Casting of ground floor column & tie beam Casting of ground floor slab & beam Casting of first floor column Casting of first floor slab & beams Completion stage
18
Salient features of ITPI Collect sample of materials for testing Furnish verification certificate of foundation Carry out slump test of concrete Take action for casting concrete cube Communicate inspection note Furnish fortnightly report Furnish status of compliance report at every quarter Arrange workshop to share experience Furnish Completion Certificate
19
Benefits of Optimal Staffing Holistic planning Realistic AWP & B Whole School Development School Infrastructure Survey Environmental Assessment Holistic Design to make schools Child Friendly Climatically Comfortable More Functional & Usable from Educational Perspective Environmental Friendly Adaptable to new advancement in Pedagogy
20
Benefits of Optimal Staffing Training to Community and Masons Motivated Community Timely Completion with Desired Quality Prompt & Onsite problem solving Effective monitoring & reporting Cross sharing of knowledge / experience Due to GCEE track record other departments entrust works to SSAM – Gujarat Duplication of efforts reduced
21
Physical Progress Financial Progress Rs. In Lacs CUMMULATIVE 84% Achievement No. Upto 30/06/2009 90% Completion Rate
22
ADDITIONAL CLASSROOMS ZONE - V
23
ADDITIONAL CLASSROOMS ZONE - IV
24
ADDITIONAL CLASSROOMS ZONE - V
25
ADDITIONAL CLASSROOMS ZONE - V
26
CRC BUILDING ZONE - III
27
TOILET BLOCK
28
WATER FACILITY
30
COMPOUND WALL
32
MDM KITCHEN SHED
33
BRC BUILDING ZONE - V
34
BRC BUILDING ZONE - III
35
BRC BUILDING ZONE - III
36
NEW SCHOOL / BLS BUILDING ZONE - III
37
NEW SCHOOL / BLS BUILDING ZONE - III
38
NEW SCHOOL / BLS BUILDING ZONE - III
39
RAIN WATER HARVESTING
40
MCS ACR - NPEGEL
41
MCS - NPEGEL
42
Thank You