Download presentation
Presentation is loading. Please wait.
Published byRachel Tutt Modified over 9 years ago
1
Transmission Transporting Electricity by Wire Darcy Neigum Montana-Dakota Utilities Co.
2
Substation Transformer Residential Commercial Coal Storage Distribution Substation Transmission Substation Primary Transmission Lines Power Station Electric Supply System
4
The electricity market has some features in common with just about any other market: Product Sellers Buyers Transportation
5
Market Features Product – electricity is there 24/7 Sellers – generators must continually match load Buyers control the light switch Transportation – transmission system must reliably deliver electricity from Sellers to Buyers
6
No way to store electricity Production = Consumption Transmission grid is the ultimate “just in time” manufacturing
7
History – 1880-1900 Edison’s Pearl Station produced Direct Current (DC) power Westinghouse’s power plant at Niagara Falls used Alternating Current (AC) power AC became the standard because of its ease in stepping up (transmission) or stepping down voltages (distribution)
8
Transmission Choices Since distribution systems are also AC, it’s easy to distribute power from AC transmission lines The majority of U.S. transmission of electricity is by alternating current (AC) DC transmission lines have less line loss than AC but require conversion facilities – so DC is used for long distances with no distribution systems between conversion points
9
High voltage AC transmission lines
10
New Transmission Line Costs Bulk of transmission costs are initial capital expenditures. Secondary cost is on-going maintenance $125,000 per mile for 60 KV lines $250,000 per mile for 115 KV lines $375,000 per mile for 230 KV lines $1,000,000 per mile for 345 KV lines
13
Three Power Grids Operate independently, but connected in a few places by direct-current (DC) ties The Eastern and Western Interconnects have limited interconnections with each other DC ties bridge the national electric system by taking AC electricity on one side, converting it to DC, and then converting it back to AC so that it is synchronized with the AC electricity on the other side of the system separation
14
Electric Power Transmission Delivery of electricity to consumers, usually transmitted over long distances through overhead power lines It is complex, costly and critical to the economy and way of life Due to the large amount of power involved and to reduce losses, transmission normally takes place at high voltages Electricity follows the “path of least resistance”
15
Sounds Simple, What’s the Catch? Electricity cannot be stored so supply (generation) must be produced exactly when needed to meet customer demand or risk system failure Level in “lake” must be kept constant at all times Laws of physics dictate that power flows on a path of least resistance, not necessarily where we’d like it to
16
Let’s Add Some Complexity Lake levels must remain the same Streams must remain within their banks What if some beavers built a dam across one of the streams? Immediately water has to flow to keep customers happy—yet the water level in the lakes must remain constant and the rivers must not overflow their banks In the electric system all of this is happening at the speed of light Reliability of design
21
Blackout of 2003 August 14, 2003, 11:15 p.m. EST About 9 hours after blackout Congressional action for North American Electric Corporation (NERC) Reliability Standards for the Bulk Electric System - “NERC Standards”
22
Current Transmission Challenges Facing Region The current transmission system was developed to move power from a power plant to a utility’s service area
23
Issues Facing North Dakota Bottleneck occurs between North Dakota and other states Adding generation in ND can aggravate other bottlenecks in the region
24
Issues Facing North Dakota Demand for new wind generators to access market Wind generation ultimately built to serve load to the east Transmission constraints Competition with existing generators Age of existing system
25
Issues Facing North Dakota Adding or upgrading transmission is difficult Physical constraints – Long distances, complex system, stability, overloads, and voltage limitations Regulatory constraints & uncertainties Cost of $1,000,000 per mile for 345 kV Financial risk! Who pays?
26
Siting Quagmire Exists Struggle between states and federal government Federal Energy Regulatory Commission has ‘backstop’ siting authority if states refuse to site critical facilities Only one utility has attempted to initiate the FERC siting process Fourth Circuit Court of Appeals held that FERC’s limited authority is not available where a state agency has denied an application on a timely basis
27
Initiatives MISO Regional Generation Outlet study Determine how to transmit wind across the MISO footprint MISO RECB Task Force Develop equitable cost-sharing methodology Upper Midwest Transmission Development Initiative (UMTDI) – Five-state study (ND, SD, MN, IA & WI) Encourage construction of interstate transmission lines Develop equitable cost-sharing methodology
28
MISO Regional Generation Outlet Study $15 to $30 Billion of needed transmission upgrades
29
Other Material http://videos.howstuffworks.com/media link/3049-how-the-power-grid-works- video.htm http://videos.howstuffworks.com/media link/3049-how-the-power-grid-works- video.htm
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.