Project Introduction Context Efficient energy usage Problem Inefficient vehicle use can be unavoidable in some applications Solution Improve efficiency with the hydraulic hybrid system
5
Overall Project Goal Validate Hydraulic Hybrid System can increase stop and go fuel efficiency by 40%
6
Design Norms Stewardship Caring Transparency
7
Hybrid Technologies Electric Toyota Prius Flywheel Formula 1 Hydraulic UPS
8
Benefits of a Hybrid System Regenerative braking Optimal engine performance Decreased brake maintenance
9
Benefit of Hydraulic Hybrids Less energy conversions Electric Hydraulic
10
Two Types of Systems www.Eaton.com Series Parallel
11
Hydraulic System
12
Hydraulic System: Accelerating
13
Hydraulic System: Coasting
14
Hydraulic System: Braking
15
Prototypes Base Case Hydraulic Hybrid
16
Base Case Cart: Frame
17
Base Case Cart: Gas Engine Mounting
18
Base Case Cart: Drive Train
19
Hydraulic Hybrid Cart Removed base case drive train Retrofitted cart with hydraulic components Hydraulic Pump Hydraulic Motor Accumulators Reservoir Hydraulic Valves
20
Hydraulic Hybrid Cart
21
Reservoir
22
Hydraulic Pump
23
Accumulators
24
Flow Control Valves
25
Hydraulic Motor (www.grainger.com)
26
Other Components Redundant Brakes Hydraulic Mechanical Linkages Gas pedal Brake pedal
27
Hydraulic Hybrid Retrofit Costs ComponentCost Eaton Hydraulic Pump$246.50 Accumulators Inc. Accumulators$3286.00 7 gal. Reservoir$100.00 Haldex Hydraulic Motor$200.25 Misc. Hydraulic Valves$843.00 Misc. Hoses and Fittings$550.00 Mechanical Couplers$60.00 Pressure Fixtures$1000.00 Total$6285.75
28
Test Procedure
29
Testing Video
30
Results Base Case CartHydraulic Hybrid Cart Stop and Go Fuel Economy13.9 mpg21.1 mpg 52.4% increase in average stop and go fuel economy
31
Improvements Different pump or hydraulic motor Variable displacement motor Check valves with lower cracking pressure Design to eliminate minor losses
32
Business Plan Target Market Package delivery, garbage trucks, city buses Introduction to the market O.E.M. Retrofit is to expensive Potential Savings Higher gas mileage, lower maintenance costs
33
Business Plan Feasibility High cost on prototype Pay back period is 19 years at current gas prices ($4.20) Longer than the life of the vehicle
34
Obstacles Budget Time Experience with Hydraulic Systems Component Failure
36
Conclusions Met our goal! Met efficiency expectations Proved our system works Very expensive system Learned a lot Had fun!
37
Acknowledgements Matt Mills & Kelly Dawley – Vermeer Corporation Vermeer Charitable Foundation – Financial Support Ned Nielsen – Team Advisor Ren Tubergen – Industrial Consultant Phil Jasperse – Calvin College Metal Shop Charlie Huizinga – Calvin College Physical Plant Bond Fluidaire, Inc – Hydraulic hose and fittings Great Lakes Fluid Power – Accumulator Charging Rex Sheler – Decals Mike Harris – Donor Acquisition Jim Kuipers – Cart Donation Family and Friends