Project Overview Central Artery / Tunnel = The Big Dig of Boston Largest infrastructure project in the U. S. Replace the elevated Central Artery with Tunnel Two Bridges over the Charles River Extend I-90 to Logan Airport Planning Starts, 1987; Construction begins, 1991; Complete, 2007 Original estimate $2.6B; Actual Completion: $14.7B ($5.6B in constant $) Organizations Involved Mass. Department of Transportation and Mass. Turnpike Authority Bechtel and Parsons Brinckerhoff – “management consultants” Origin – The Need Historic congestion The elevated Central Artery – out of date when it was completed Fred Salvucci’s brain child: a subterranean highway The Challenges Persuading the public Mitigation – the key to sell it and the Achilles heel How to pay for it? The “10-cent dollar” (90% Federal Funding) The technological barriers Problems Thousands of leaks Fatal Ceiling collapse Corruption Results / Benefits Reduced traffic congestion Increased property values The North End reunited BEFORE AFTER Andy Demana
3
Outcome of Project and major issues All of the original project scope and all of the project’s construction goals were achieved The budget and schedule were not close to meeting the original estimates Largest Issue was a very large cost overrun Several factors contributed: Environmental Mitigation/Compliance - $3 billion Scope Creep - $2.7 billion Public Image Problems Dennis Farley
4
Retrospective: Risk Management State’s Responsibility was unclear Unreliable Cost Estimates New technology Health and Safety The EGAP Principle Mitigating Risk Transferring Risk Sharing Risk Carlos Arguello-Mirazo
5
Jim Varghese Management Style Issues Collaborative/Integrated Project Management Late integration After 99 percent design was complete After 45 percent construction was complete - Organizational Structure Separated design from construction Traditional design-bid-build model James Kerasiotes assumed the role of Project Manager
6
Major issues: Known’s, Known Unknowns, Unknown Unknowns BIG DIG TEAM KNOWLEDGE FACTORS AFFECTING THE PROJECT OUTCOMES Sub-Surface Conditions Final construction Design from preliminary design with amendments Flawed designs Geological & archaeological barriers Constant water leaks Fatal ceiling collapse Sept. 11 2001 terrorist attacks Maintaining Traffic Flow during construction Public Safety Coordination between 110 contractors Funding for Contingencies Inflation Known Unknown KnownUnknown Chetan Rao
7
Lessons Learned Planning Politics Organization and Accountability Risk Management Lack of risk oversight Need for independent auditing Highly technical designs Unknown soil conditions, existing underground utilities Ignoring safety warnings Integrated Project Management is essential Project status disclosures Planning Politics Integrated Project Management is essential Project status disclosures Timely and accurate Risk Management Highly technical designs require contingencies Unknown soil conditions, existing underground utilities Lack of risk oversight Ignoring safety warnings Andy Demana