Steps taken to improve the progress and completion rate  Filling up all vacancies of (TC) Block Engineer & Sr. TC (District Engineer)  Funds released.

Similar presentations


Presentation on theme: "Steps taken to improve the progress and completion rate  Filling up all vacancies of (TC) Block Engineer & Sr. TC (District Engineer)  Funds released."— Presentation transcript:

1

2 Steps taken to improve the progress and completion rate  Filling up all vacancies of (TC) Block Engineer & Sr. TC (District Engineer)  Funds released to SMC a/c newly operationalised  Recruitment of teachers  State Government has sanctioned 17000 teachers under its own quota  Training to TC, Sr. TC & teachers  Training to SMC under a programme called “ SAHAYOG ”  Frequently monitoring at School, Block & District level.  Coordination meeting with RD Deptt. for completion of Drinking Water & toilets

3 Impact of steps taken Sl. No. DescriptionAs on May’2011Basing on 31-10- 11 1Completion rate (For 2010-11)16%66% 2Completion rate (upto 2010-11)79%89% 3Spillover (Upto 2010-11)186099598  The state was able to achieve the target as per Plan of Action presented on 8 th July 2011.

4 Impact of steps taken by end of September ’ 11 * -ve value says the State has able to achieve more than the targeted plan

5 Impact of steps taken by end of October ’ 11 * -ve value says the State has able to achieve more than the targeted plan

6 Spillover (upto 2010-11) ending 30-09-2011 Sl. No.ActivityNos. 1BRC01 2CRC24 3Primary (all type)1496 4Upper Primary (all type)829 5ACR (all type)9431 6Toilet (all type)1853

7 Spillover (upto 2010-11) ending 31-10-2011 Sl. No.ActivityNos. 1BRC01 2CRC23 3Primary (all type)1290 4Upper Primary (all type)732 5ACR (all type)5580 6Toilet (all type)1199

8 Plan of action for completing the spill over works up to 2010-11

9 GAP

10 Planning to complete all spillover work  Asst. Engineers monitoring frequently for progress of work  Filling all vacancies of TC & Sr. TC  Coordination meeting with Bankers for quick release of funds to School / SMC a/c  Zone wise assignment are given to State level Engineer for close monitoring

11 Commitment  By 31-03-2012 – all works (upto 2010-11) to be completed.  Balance gap to be covered by December-2012

12 THANK YOU


Download ppt "Steps taken to improve the progress and completion rate  Filling up all vacancies of (TC) Block Engineer & Sr. TC (District Engineer)  Funds released."