2
OBJECTIVES OF PMS PMS is a web based application for monitoring progress of all projects undertaken by CPWD Monitoring of projects both at pre and post construction stages Review of projects with MIS reports Monthly and total expenditure on a project Login to ministries, clients to review progress Guest login for general public
3
SALIENT FEATURES OF PMS Project : All works comprised in AA & ES Package : A component of a project which could be made functional independent of other packages Sub-work : A component of a package which has separate TS and NIT Agreement: Sub-work awarded to a contractor
4
PROJECT OWNER Project owner : Authority competent to send preliminary estimate for the project Functions of project owner To register a project To send preliminary estimate To decide packages, sub-works after receipt of AA and ES, and register packages To periodically review progress reports
5
PMS PROCESSES One time processes Online registration of projects and packages by the project owner Offline registration of projects and agreements on Divisional Accounting System. Separate registration by the EEs concerned if the agreement is composite Online registration of sub-works by the EEs
6
PMS PROCESSES Periodical processes Edit, delete and transfer projects, packages and sub-works Uploading of monthly accounts by the divisions Uploading of project documents like letters, architectural and structural drawings, images Update of monthly progress reports Update of cash flow statement
7
REGISTRATION OF PROJECTS Project owner can register a project at any stage Data required for registration Client type (CAPF or Non-CAPF), client name, designation and address Fund type (Budgetary, LOA, Deposit, CSSA) Name of project, city, state Details of planning and execution offices
8
REGISTRATION OF PROJECTS
9
REGISTRATION OF PACKAGES Project owner registers packages after receipt of AA and ES Data required for registration Package description Package amount
10
REGISTRATION OF PACKAGES
11
REGISTRATION OF SUB-WORKS Step 1: Offline registration of projects and agreements on Divisional Accounting System by the EE. The system generates NIJ TS code. EEs register separately for composite contracts Step 2: Online mapping with NIJ TS code and registration of agreements on PMS by the EE Data required for registration Agreement title, amount, stipulated dates of start and completion, agency, NIJ TS code
12
REGISTRATION OF AGREEMENTS IN ACCOUNTING SYSTEM
13
REGISTRATION OF SUB-WORKS
14
MONTHLY PROGRESS REPORTS Pending updates displayed on login Items to be updated periodically Budget allotment Up to date physical progress Target date of physical completion Physical status Physical status field shows when last updated
15
PENDING UPDATES IN MPR List of items to be updated SNoITEMNos 1.MONTHLY ACCOUNT 2.BUDGET 3.TARGET DATE OF COMPLETION 4.PHYSICAL % PROGRESS 5.PHYSICAL STATUS Monthly email reminders to Zone, Circle, Division
16
PENDING UPDATES IN MPR Data deficiency SNoITEMNos 1.INCOMPLETE PROJECT DETAILS 2.HEAD OF ACCOUNT NOT DEFINED 3.DIVISION NOT ASSIGNED 4.PACKAGES NOT DEFINED 5.SUB-WORKS NOT DEFINED 6.AGREEMENT DETAILS NOT UPDATED
17
PENDING UPDATES IN MPR Pending updates in MPR
18
MONTHLY PROGRESS REPORTS Requisition received, PE to be sent
19
MONTHLY PROGRESS REPORTS PE sent, AA and ES awaited
20
MONTHLY PROGRESS REPORTS Works sanctioned, to be awarded
21
MONTHLY PROGRESS REPORTS Works in progress
22
DIVISIONAL ACCOUNTING SYSTEM LINK TO PMS Monthly divisional account is linked to PMS Divisions upload monthly account on PMS Expenditure against each sub-work, package and project is shown in MPR on uploading Monitoring of uploading of monthly account If the account is not uploaded, it is shown in pending updates on login page
23
MIS REPORTS Monthly progress reports for client type : CAPF and non-CAPF For each of the following stages Requisition received, PE to be sent PE sent, AA and ES awaited Works sanctioned, to be awarded Works in progress Completed works ….continued
24
MIS REPORTS Filters available for Each client Each head of account Each state A range of sanctioned amount ….continued
25
MIS REPORTS ….continued Monthly Progress Report – Requisition received, PE to be sent
26
MIS REPORTS ….continued Monthly Progress Report - PE sent, AA and ES awaited
27
MIS REPORTS ….continued Monthly Progress Report - Works sanctioned, to be awarded
28
MIS REPORTS ….continued Monthly Progress Report - Works in progress
29
MIS REPORTS ….continued Monthly Progress Report - Completed works
30
MIS REPORTS Review of delayed projects Review the number and details of delayed projects under the following stages Requisition received, PE to be sent Requisition received, PD to be sent PD approved, PE to be sent Work sanctioned, to be awarded Works in progress ….continued
31
MIS REPORTS Each stage can be reviewed under the following categories of delay Upto 6 months Beyond 6 months upto 1 year Beyond 1 year upto 2 years Beyond 2 years ….continued
32
MIS REPORTS Review of delayed projects ….continued
33
MIS REPORTS Review of projects costing above Rs.20 crore Review the number and details of projects under the following stages Requisition received, PE to be sent PE sent, AA and ES awaited Works sanctioned, to be awarded Works in progress Completed works ….continued
34
Review of projects costing above Rs.20 crore MIS REPORTS ….continued
35
MIS REPORTS Other MIS reports Project wise cash flow statement Pending final bills Review by project owner Works with a selected contractor ….continued
36
MIS REPORTS Project wise cash flow statement ….continued
37
MIS REPORTS Pending final bills ….continued
38
MIS REPORTS Review by project owner ….continued
39
MIS REPORTS Works with a selected contractor
40
VACANT LAND AND ENCROACHMENT REPORT
41
PROJECT HISTORY View history of a project Requisition and client details Name of project, package and sub-works AA and ES details Agreement details Project images, drawings, documents Remarks, percentage progress
42
PROJECT HISTORY
44
EXPENDITURE STATEMENT Expenditure against each project comes from Divisional Accounting System Expenditure Statement can be customized head wise and office wise Ratio of expenditure and turnover (E/T Ratio) for each office
45
EXPENDITURE STATEMENT
46
E/T RATIO
47
MISCELLANEOUS Generate letters Online update of stage after letter generation Important phases for letter generation Upto submission of PE From sanction to tender receipt Acceptance and award of work
48
GENERATE LETTERS Upto submission of PE Activity Letter generation Letter to be generated by Data captured Receipt of requisition letter from client Project registration letter Project ownerRequisition letter number and date, client address, executing office details Sending architectural drawings to client for approval Forwarding letter to client Architect / Senior Architect Date of sending architectural drawings for approval Conveying of approval of preliminary drawings Forwarding letter to field unit Architect / Senior Architect Date of approval of architectural drawings Sending PE for AA and ES Forwarding letter of PE to client Project ownerAmount of PE, date of sending PE to client
49
GENERATE LETTERS From sanction to tender receipt Activity Letter generation Letter to be generated by Data captured AA and ESConveying of AA and ES, packages and sub-works Project ownerAmount of AA and ES, packages and sub- works by project owner TS and NITApproved copy of TS and NIT to be conveyed Technical sanction authority Estimated cost of sub- works and date of TS and NIT Call of tenderPress notice can be generated Field unitDate of calling tender, other details of tender Forwarding tenders for acceptance Tender forwarding letter Field unitAll other details of tender is captured
50
GENERATE LETTERS Acceptance and award of work Activity Letter generation Letter to be generated by Data captured Acceptance of tender Tender acceptance letter Project ownerTender acceptance, final tendered amount Award of workLetter of acceptance and final award letter EE of field unitDate of start, date of completion, final tendered amount etc.
51
MISCELLANEOUS QCTA para details
52
MISCELLANEOUS Special features of a project ISO certification and GRIHA rating Awards won Details of consultants
53
MISCELLANEOUS Provisional extension of time for agreements Monitoring of provisional extension of time for agreements where performance is delayed Email reminder sent to division, circle, zone If completion is due within next 30 days, the project is included in pending updates
54
MISCELLANEOUS Provisional extension of time for agreements
55
ARCHIVE Previous monthly progress reports Completed works Login history Expenditure statement E/T ratio
56
MINISTRY LOGIN Ministries can login on CPWD website to : View monthly progress reports under various stages of work with options to filter MPRs under client name, head of account and state Communicate with project owner Comment on execution programme Review delayed projects Review expenditure on a project View photographs, documents of a projects
57
MINISTRY LOGIN
66
CLIENT LOGIN Clients can login on CPWD website to : View monthly progress reports under various stages of work with options to filter MPRs under client name, head of account and state Communicate with project owner Comment on execution programme Review delayed projects Review expenditure on a project View photographs, documents of a projects
67
CLIENT LOGIN