Washington Avenue Reconstruction Project City of Chelsea Public Informational Meeting May 31, 2011
2
Why Project is Occurring Poor Roadway Conditions Separation of Sewer and Stormwater Replacement of Water Replacement of Gas (by National Grid)
3
What Does the Project Entail? Project Details Geographic Scope of the Work Heard St to Route 16 Back of Sidewalk to Back of Sidewalk Reconfiguration of Cary Square Full-Depth Roadway Reconstruction Explanation 1. New Street Surface 2. New Sidewalks 3. Streetscape Amenities (Benches, Bike Racks, Trees, Etc.)
4
What Does the Project Entail? Funding Sources Municipal Borrowings through General Obligation Sewer and Water Bonds Chapter 90 Funds Community Development Block Grant Funding MWRA Grant and Zero Interest Loans Total of $6M+
5
What Does the Project Entail? Project Construction Schedule Water, Sanitary & Drain - Spring/Summer/Fall 2011 Streetscape – Spring/Summer/Fall 2012 Completion – Spring 2013
6
Project Schedule Contract has been awarded to J. Marchese and Sons Work starts Monday June 6 th Work hours approximately 7 AM to 3:30 PM, Monday through Friday
7
Construction Schedule
9
June Construction
10
July Construction
11
August Construction
12
Questions/Comments/Concerns?