Solving Challenges Others Cannot PPEA Primer Southampton County Board of Supervisors Christopher D. Lloyd November 26, 2007.

Similar presentations


Presentation on theme: "Solving Challenges Others Cannot PPEA Primer Southampton County Board of Supervisors Christopher D. Lloyd November 26, 2007."— Presentation transcript:

1 Solving Challenges Others Cannot PPEA Primer Southampton County Board of Supervisors Christopher D. Lloyd November 26, 2007

2 Presentation Overview Legislative History Virginia Experience Understanding the PPEA How to Use the PPEA

3 PPEA History Built on the successes of the PPTA (895, 288, 28, Coalfields Expressway) Design-Build Review Board created in 1996, overly cumbersome process Passed General Assembly in 2002 Model Guidelines issued in October 2002, state guidelines in December First comprehensive agreement signed July 1, 2003 (Stafford County) Amendments occur in 2003, 2004, and 2005 Additional changes in 2006 regarding FOIA, public disclosure, oversight 2007 amendments require greater participation by the “appropriating body”

4 PPEA Implementation PPEA Guideline Implementation City of SalemChesterfield City of RichmondStafford City of WinchesterRoanoke City of Manassas ParkFrederick City of Virginia BeachLoudoun City of FredericksburgCity of Chesapeake City of Falls ChurchJames City City of ManassasYork City of LynchburgBedford Norfolk Airports AuthorityFairfax Clarke CountyFauquier County City of SuffolkCity of Norfolk SouthamptonCity of Roanoke Town of HerndonHenrico Bedford PSASpotsylvania Rockbridge CountyCampbell County City of StauntonCumberland NorthumberlandPrince William Service Authority Culpeper CountyFrederick County Public Schools

5 PPEA Implementation What is happening across Virginia? School facilities in Falls Church, Fredericksburg, Chesterfield, Winchester, Bedford County, Warren County, Stafford County, City of Harrisonburg - agreements signed Pending school projects in Cumberland, Frederick, and Northumberland Counties Public safety facilities in Roanoke, Stafford, and Frederick Counties Northern Virginia Forensics Lab James City County recreational facilities DOC Prison construction program (Balfour Beatty), regional jails Parking decks (Fredericksburg, Roanoke, Winchester) Technology projects (VITA) Prince William and Chesapeake human services offices Bedford County Public Service Authority, Prince William PSA, and Fredericksburg water and sewer projects Crater Regional Public Safety Training facilities Loudoun County government complex (pending) Virginia Department of Taxation headquarters (pending)

6 PPEA Overview What is it? - An alternative procurement tool that allows public entities to more efficiently develop infrastructure and achieve better value for the taxpayer - Vehicle to use design-build practices What it is NOT? - A panacea that resolves all procurement issues - A way to get something for nothing

7 PPEA Overview Allows for solicited and unsolicited proposals to develop or operate a qualifying project A qualifying project is: –education facility (public school and higher ed) –equipment to enhance public safety and security at public buildings –utility and telecommunications and other communications infrastructure –recreational facilities –Technology infrastructure –any building or facility that meets a public purpose and is developed or operated by or for any public entity –any improvements necessary or desirable to any unimproved locally- or state-owned real estate

8 PPEA Process Public body adopts PPEA guidelines Private entity submits proposal to public body or public body issues a solicitation for proposals Public body makes a written determination whether the project is developed using competitive bid or competitive negotiation Competitive negotiation can proceed if the public body determines that this method is “likely to be advantageous” because of the “probable scope, complexity or urgency of the project” or “risk sharing, added value, an increase in funding or economic benefit from the project that would not otherwise be available”

9 PPEA Process Private entity secures confidentiality agreement for FOIA protection Private entity submits a conceptual proposal for review (qualifications and experience, conceptual schedule and cost, public benefit) Open competition period of not less than 45 days (no minimum for solicited projects) Public body determines whether or how to proceed If public body moves forward, asks for a detailed submission (accelerated process permitted) At this phase, schedule and price become defined One proposer is elevated to the interim/comprehensive agreement stage

10 PPEA Benefits Project selection based on a variety of factors, not just price Achieve cost and schedule benefits of design-build Single point of responsibility for complex projects Enhances public participation in procurement decisions Augments in-house staff capabilities to meet infrastructure needs

11 PPEA Implementation What Makes Projects Go Well Open and collaborative process between public and private sectors Atmosphere that encourages innovation and creativity Include public, press and other stakeholders Objectives (cost savings, time, limits on risk) are clear from the beginning

12 PPEA Implementation What Makes Projects Go Bad Unnecessary closed door discussions Public sector shifts all risk, not willing to pay for it Staff objections to process Cost overruns and scope creep Public sentiment turns away from development Negotiations never end Project is overly defined or restricted

13 THE END Business Expansion Services | Constituency Development | Economic Development | Federal Budgeting and Contracting Advice | Federal Legislative Assistance | Grassroots Contact Program | Issue Advocacy | PAC Consulting | Public Infrastructure Finance | Public- Private Partnerships | Referendum Campaigns | State Government Relations ATLANTA BUCHAREST CHICAGO SPRINGFIELD RALEIGH RICHMOND TYSONS CORNER WASHINGTON, D.C. www.mcguirewoodsconsulting.com


Download ppt "Solving Challenges Others Cannot PPEA Primer Southampton County Board of Supervisors Christopher D. Lloyd November 26, 2007."