Neil Shewry Project Manager Janet6 Update. Background Procurement What we’re building How we’re getting on Strategic Research Facilities Plans for the.

Similar presentations


Presentation on theme: "Neil Shewry Project Manager Janet6 Update. Background Procurement What we’re building How we’re getting on Strategic Research Facilities Plans for the."— Presentation transcript:

1 Neil Shewry Project Manager Janet6 Update

2 Background Procurement What we’re building How we’re getting on Strategic Research Facilities Plans for the future Agenda

3 Background Janet6: Project to replace the UK wide Janet backbone, SuperJanet5 Requirements gathering & analysis2010 to 2011 Procurement Fibre infrastructure Optical transmission equipment Oct 2011 to Sept 2012 RolloutSept 2012 to April 2013 Transition SJ5 to J6May 2013 to July 2013 SJ5 ‘turned-off’Oct 2013 SuperJanet5: 2006 to 2013

4 Fibre infrastructure contract signed: 31 st July 2012 Scottish & Southern Energy Telecoms (SSET) 4 year framework 10 (+5) year contract £30M Optical transmission contract signed: 6 th September 2012 Ciena Inc. 7 year framework Order for supply and 5 years support £12.8M Procurement

5 What we’re building 5 delivery phases  Core  4 Regional RNs connect at multiples of 10G Most are getting an upgrade

6 What we’re building I could go into more detail… …but how good is your eyesight?

7 What we’re building - Points of Presence Vacating the Verizon Business PoPs – Except for small presence in Glasgow and Reading Existing Provider-Neutral PoPs – Telehouse North, Telecity Harbour Exchange – Telecity Manchester, Scolocate New Provider-Neutral PoPs – Telecity Powergate, Telehouse West, Leeds (aql) SSET Core PoPs – Bradley Stoke, Erdington, Lowdham, Glasgow SSET Transmission PoPs – Multiplex circuits from regional fibres onto the backbone SSET In-Line Amplifier PoPs – Single rack, small amplifier shelf RNEPs

8 What we’re building - Lightpath Increase bandwidth between backbone nodes to 100GE Topology reflects what is currently required

9 Acceptance of core infrastructure February 2013 Acceptance of regional infrastructure March 2013 How we’re getting on – fibre

10 How we’re getting on – DWDM equipment Ciena 6500 platform All kit is in the country  40% on site  60% in staging Deployment began in January  Staging  Delivery  Installation  Commissioning Completion end April 2013

11 Upgrade: Juniper T1600 Juniper T4000 How we’re getting on – IP routing equipment Professional Services

12 Regional Network Readiness  Space & power  RNEP router capability Transition Planning Operational Readiness  PoP Control  Fault Management  Network Management Service Management  SSET  Ciena Decommissioning How we’re getting on – other stuff

13 Government e-Infrastructure initiative – £26m funding to Janet £10m for Janet6 backbone £12m for phase 1 (below) £4m for ‘industrial connectivity’ Phase 1 – Met Office, Exeter – Norwich Research Park – Hinxton Campus, Cambridge – (Francis Crick Institute, St Pancras) Strategic Research Facilities

14 LOTS of bandwidth – 100Gbit/s x 88 channels = 8.8Tbit/s – 400Gbit/s? Strategic Research Facilities – possible phase 2 Thames Valley Network South Region (formerly LeNSE) Other regional networks? Individual customers? Plans for the future

15 Janet, Lumen House Library Avenue, Harwell Oxford Didcot, Oxfordshire t: +44 (0) 1235 822200 f: +44 (0) 1235 822399 e: Service@ja.net Questions?


Download ppt "Neil Shewry Project Manager Janet6 Update. Background Procurement What we’re building How we’re getting on Strategic Research Facilities Plans for the."