Final Program Environmental Impact Report Gillespie Field Development Council January 17, 2012 Item #5
2
Gillespie Field 70-acre Redevelopment Project: Vicinity Map 2
3
Redevelopment of the vacant 70-acre site County – Infrastructure Improvements Private Developers – Aviation Use Development 3
4
Meet existing unmet and forecast market demand Comply with Federal grant assurances Revenue-generating asset to the County and the surrounding communities 4
5
Biological Resources Hazardous Materials Traffic & Transportation 5
6
Public Review of Draft Program EIR September 15 – November 7, 2011 Gillespie Field Development Council supported project on September 20, 2011 Draft Program EIR Public Review Open House on October 5, 2011 6
7
87 public comment letters received 70 in favor of Proposed Project Expansion of aviation facilities Economic growth 7 against Proposed Project Noise and safety concerns under flight path 10 neutral ( responsible agencies and stakeholders ) Program EIR analysis 7
8
March 14, 2012 – CEQA Final Program EIR certification by Board of Supervisors NEPA Draft EA Public review tentatively anticipated February 2012 FAA EA completion tentatively anticipated May 2012 8
9
PhaseDescription Cost (millions)ACIP FAA Grants received to date$0.4Past AEF spent on Environmental and Preliminary Engineering$1.0Past IEnvironmental and Design$2.72012-2013 II Grading, Drainage and Street Improvements$15.02014 III Taxiways, Ramps and Utilities for first 4 Parcels$11.52015 Total$30.6 FAA contribution $27.9 mil AEF contribution $ 2.7 mil 9
10
4 parcels in initial private development phase - Total 19.82 Acres Remaining 4 parcels developed in future Timing dependant on funding and need 10
11
RFP to GFDCSep 2013 Publish RFPNov 2013 Select Semi-finalists Jul 2014 Select DevelopersJan 2015 BOS ApprovalAug 2015 Private Construction Start Jan 2016 11
12
Meets forecasted growth, regional goals, TAF Increased facilities for General Aviation Annual revenue - $285K initial/$792K project Private investment - $27M initial/$67M project Annual tax increment- $272K initial/$670K project Cajon Air Center project jobs Construction - 700 initial/1,200 project Aviation - 200 initial/440 project 12
13
Economic Impact Study prepared by CIC Research Annual Gillespie Field Economic Benefit Direct $403M / 3,164 jobs Total Economic Activity $919M / 6,250 jobs Gov Revenue $9.9M local /$51.2M federal/state 2025 (After Development) Annual Projection Direct $530M / 4,190 jobs Total Economic Activity $1.2B / 8,250 jobs Gov Revenue $13M local /$67.2M federal/state 13
14
The Gillespie Field Development Council recommends the County of San Diego Board of Supervisors approve the Gillespie Field 70-Acre Redevelopment Project, certify the Program Level Environmental Impact Report and authorize DPW to apply for and accept grant funds for construction of the project. 14
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.