1 Herndon Station - North Pavilion Construction Town of Herndon – Town Council August 6, 2014

2 Overview of Project Schedule

3 Existing Site and Traffic Pattern 198 Van Buren Parcel #226 575 Herndon Parkway Parcel #225 593 Herndon Parkway Parcel 227 Pavilion Site

4 Existing Underground SWM 198 Van Buren Parcel #226 575 Herndon Parkway Parcel #225 593 Herndon Parkway Parcel 227 Pavilion Site

5 Install Fence PHASE 1.1 - Target Start: February 2016, Duration: 1 Month 198 Van Buren Parcel #226 575 Herndon Parkway Parcel #225 593 Herndon Parkway Parcel 227 Pavilion Site

6 Install Fence Clear & Grade PHASE 1.1 - Target Start: February 2016, Duration: 1 Month 198 Van Buren Parcel #226 575 Herndon Parkway Parcel #225 593 Herndon Parkway Parcel 227

7 Install Fence Clear & Grade Demo Staircase PHASE 1.1 - Target Start: February 2016, Duration: 1 Month 198 Van Buren Parcel #226 575 Herndon Parkway Parcel #225 593 Herndon Parkway Parcel 227 Laydown

8 Install Fence Clear & Grade Demo Staircase Install Retaining Wall PHASE 1.1 - Target Start: February 2016, Duration: 1 Month 198 Van Buren Parcel #226 575 Herndon Parkway Parcel #225 593 Herndon Parkway Parcel 227 Laydown

9 Install Fence Clear & Grade Demo Staircase Install Retaining Wall Build Construction Access PHASE 1.1 - Target Start: February 2016, Duration: 1 Month Construction Access 198 Van Buren Parcel #226 575 Herndon Parkway Parcel #225 593 Herndon Parkway Parcel 227 Laydown

10 Install Fence Clear & Grade Demo Staircase Install Retaining Wall Build Construction Access Install Fence PHASE 1.2 - Target Start: February 2016, Duration: 1 Month 198 Van Buren Parcel #226 575 Herndon Parkway Parcel #225 593 Herndon Parkway Parcel 227 Construction Access Laydown

11 Install Fence Clear & Grade Demo Staircase Install Retaining Wall Build Construction Access Install Fence Demo Median PHASE 1.2 - Target Start: February 2016, Duration: 1 Month 198 Van Buren Parcel #226 575 Herndon Parkway Parcel #225 593 Herndon Parkway Parcel 227 Construction Access Laydown

12 PHASE 1.3 - Target Start: February 2016, Duration: 1 Month Install Fence Clear & Grade Demo Staircase Install Retaining Wall Build Construction Access Install Fence Demo Median Construct New Aisle 198 Van Buren Parcel #226 575 Herndon Parkway Parcel #225 593 Herndon Parkway Parcel 227 Construction Access Laydown

13 PHASE 1.3 - Target Start: February 2016, Duration: 1 Month Install Fence Clear & Grade Demo Staircase Install Retaining Wall Build Construction Access Install Fence Demo Median Construct New Aisle Relocate Dumpster Pave to Existing Permanent Traffic Shift 198 Van Buren Parcel #226 575 Herndon Parkway Parcel #225 593 Herndon Parkway Parcel 227 Construction Access Laydown

14 PHASE 2 - Target Start: March 2016, Duration: 2 Months Relocate Existing Utilities Install New Utilities Relocate Transformer 198 Van Buren Parcel #226 575 Herndon Parkway Parcel #225 593 Herndon Parkway Parcel 227 Construction Access Laydown

15 PHASE 3 - Target Start: May 2016, Duration: 4 Months Erect Service Crane Excavate Install Footings Install FDN/SOG Concrete Columns/Beams Install Precast Concrete Crane Pavilion 198 Van Buren Parcel #226 575 Herndon Parkway Parcel #225 593 Herndon Parkway Parcel 227 Construction Access Laydown

16 PHASE 4 - Target Start: September 2016, Duration: 5 Months Install Escalators Erect Pedestrian Bridge Crane Pavilion 198 Van Buren Parcel #226 575 Herndon Parkway Parcel #225 593 Herndon Parkway Parcel 227 Construction Access Laydown

17 PHASE 4 - Target Start: September 2016, Duration: 5 Months Install Escalators Erect Pedestrian Bridge Install Curb & Gutter Install Pavers Install Sidewalks Install Finishes Crane Pavilion 198 Van Buren Parcel #226 575 Herndon Parkway Parcel #225 593 Herndon Parkway Parcel 227 Construction Access Laydown

18 PHASE 5 - Target Start: February 2017, Duration: 2 Months Remove Service Crane Pavilion 198 Van Buren Parcel #226 575 Herndon Parkway Parcel #225 593 Herndon Parkway Parcel 227 Pavilion Site Construction Access

19 PHASE 5 - Target Start: February 2017, Duration: 2 Months Remove Service Crane Install Sidewalk Pavilion 198 Van Buren Parcel #226 575 Herndon Parkway Parcel #225 593 Herndon Parkway Parcel 227 Pavilion Site

20 PHASE 5 - Target Start: February 2017, Duration: 2 Months Remove Service Crane Install Plaza & Sidewalk Install Landscaping Pavilion 198 Van Buren Parcel #226 575 Herndon Parkway Parcel #225 593 Herndon Parkway Parcel 227 Pavilion Site

21 PHASE 5 - Target Start: February 2017, Duration: 2 Months Remove Service Crane Install Plaza & Sidewalk Install Landscaping Remove Fencing Pavilion 198 Van Buren Parcel #226 575 Herndon Parkway Parcel #225 593 Herndon Parkway Parcel 227 Pavilion Site

22 Parking Impacts – Parcels 225 and 227 Pavilion 198 Van Buren Parcel #226 575 Herndon Parkway Parcel #225 593 Herndon Parkway Parcel 227 Pavilion Site