BCC Public Hearing Concrete & Asphalt Plants Ordinance ZONING DIVISION December 2, 2014
2
Overview Background Draft Regulations Next Step
3
Background September 9, 2014 BCC requested review of existing regulations regarding concrete plant type uses. September 23, 2014 BCC approved a moratorium on new permits for concrete plant type uses(SIC Group 14). November 20, 2014 LPA approved and found the ordinance to be consistent with the Comprehensive Plan.
4
Background Nuisance Factors Noise Air Quality Hours of Operation Types of Machinery Overall Compatibility
5
Background The following uses listed in the Zoning Use Table shall be affected by the proposed regulations: SIC #1422-Cement, rock, limestone, crushing and grinding of asphalt, concrete & cement Cement, concrete, asphalt plants SIC #1442-Operation of sand & gravel pits for construction, sand & gravel mining SIC #1446-Operation of sand & gravel pits for glassmaking, molding, & abrasives SIC #1475-Preparation of phosphate rock
6
Background As part of staff analysis, fieldwork was conducted to ascertain appropriate distance separations for noisy activities at three active sites. The following results were identified: Site #1-Downtown Orlando – @485 ft. 73 DB – @630 ft. 71 DB – @375 ft. 68 DB
7
Background Site #2 South Apopka – @503 ft. 64 DB – @950 ft. 55 DB – @1200 ft. 62 DB Site #3 North Pine Hills – @750 ft. 58 DB Based on the results staff recommends a 1,000 ft. distance separation to deter/limit noise issues.
8
Draft Regulations In A-1 & A-2 Zoning Districts the subject uses shall be approved with special exception based on meeting the following standards: Separation distance from residential uses and schools of 1,000 feet Separation distance applies to mobile crusher, stockpiles, and loading/unloading activity Emissions of particular matter need to be controlled by water suppression system as approved by EPD
9
Draft Regulations Type A Buffer requirements per Ch.24 Stockpiles shall be limited to 35 feet above finished grade elevation Hours of operation shall be limited to – Monday thru Friday 7am-7pm – Saturday 8am-3pm
10
Draft Regulations In the I-2/I-3 and I-4 zoning districts, the use shall be a permitted use which shall meet the same standards as A-1 & A-2, with the exception of the limit on hours of operation. The I-1/I-5 zoning district shall prohibit any of the subject uses.
11
Draft Regulations Expansion of existing facilities to I-1/I-5 shall be considered, if the facility meets all the new standards and demonstrates compatibility to the surrounding area. Expansions on I-1/I-5 zoning districts shall only be considered until Dec. 2015.
12
PZC Recommendation The Planning and Zoning Commission unanimously recommended approval with the following comments: Address setbacks for buildings adjacent to residential uses Clarify that operation shall not occur on Sundays for A-1 & A-2 zoned properties Clarify what standards apply to applications in the queue
13
Next Step No action necessary. 2 nd BCC Public Hearing to be held on Dec. 16 th.
14
BCC PUBLIC HEARING Concrete & Asphalt Plants Ordinance ZONING DIVISION December 2, 2014
15
New/Expansion Options 1.New facilities which applied on I-1/I-5 zoned property before Sept. 26, 2014 shall be approved if all standards of this ordinance are met. 2.Expansions on I-1/I-5 zoned properties may also be approved, until Jan. 2016, if expansions occur on I-1/I-5 zoned property that was commonly owned prior to Sept. 26, 2014 and they meet standards.