Why code was updated ◦ Procurement code was old ◦ Various high-profile procurement-related issues Update process ◦ 2012 Legislative Session ◦ 2013 Legislative Session ◦ 2014 Legislative Session Effective Date: May 1, 2013 4
5
Procurement code declares Board of Regents as Rulemaking Authority New Regent’s policy delegates this rulemaking authority to each institution 5
6
Currently in Stage 3 Posted on the Policy website New policies ◦ 241, University Procurement ◦ 242, Solicitation and Award of Procurement Contracts ◦ 243, Small Purchases ◦ 244, Requisitions and Purchase Orders ◦ 245, Receiving Goods and Services ◦ 246, Surplus Property 6
7
Other affected policies ◦ 204, Appropriateness of Expenditures Updating references to procurement policies Updating format Fixing some minor grammatical and syntax errors Not changing expenditure procedures ◦ 421, Property and Equipment Removing Surplus section only Not updating format 7
8
8
9
Split Purchases Unethical behavior ◦ Accepting Gratuities Inflating contracts Bid Rigging 9
10
Under the Utah Procurement Code, it is illegal to divide, split, parcel, or manipulate a procurement, with the intent of making a larger purchase appear to qualify as a small- dollar purchase or to avoid an established dollar threshold. Revocation of privileges (P-card, LPC) Disciplinary action Report to AG 10
11
All individuals participating in a procurement, including contract administration, must adhere to the ethical requirements outlined in the Utah Procurement Code ◦ Gratuities ◦ Kickbacks ◦ Fairness ◦ Impropriety 11
12
Know and obey the letter and spirit of laws, regulations, and policies Prevent the appearance of unethical behavior Protect confidential information Avoid conflicts of interest Do not accept gifts, gratuities, or kickbacks from vendors which may appear to influence purchasing decisions. 12
13
Requisitions should have a good estimated amount ◦ No $1.00 requisitions Change Orders submitted through website form Additional items will not be added from invoice Analyzed to ensure compliance with policies, procedures, and applicable contracts 13
14
During a procurement process, no communication with vendors Vendors must be directed to Purchasing 14
15
Mishandling money Lax control environment Personal Reimbursements “Intentional and willful disregard by certain employees for compliance with appropriate practices and policies.” 15
16
“Any expenditure external to UVU that cannot be purchased with a limited purchase check or purchasing card must be obtained using a requisition through the Purchasing Department” (Policy 204.V.A.1.g). Sales Tax. Lack of proper controls. 16
17
Should only be used if the expenditure cannot be feasibly made using an LPC, P- Card, or PO as determined by FaBS and PS. Include a detailed explanation on the check request. Check Requests received for reimbursement may be sent to the VP as a violation. ◦ See Policy 204. Questions regarding Check Requests are referred to Scott Wood. 17
18
Protest on I-15 CORE Project ◦ Criteria weighting was changed to favor a vendor ◦ Evaluation factors included in the RFP were not adhered to Settlement: $13 million 18
19
Specifications shall not be unduly restrictive or appear to favor one vendor over another Rating criteria should be clear and concise Rules can’t be changed during the process Analysis on expenditures to ensure fairness 19
20
20
21
Emergency procurements are procurements needed due to an emergency situation ◦ Threat to public health or welfare ◦ Serious threat to the functioning of the institution ◦ Procurements made at Purchasing’s discretion Urgent procurements are procurements that are needed due to a lack of planning or circumstances beyond the control of the requestor. ◦ All procurement policies and procedures must still be followed. 21
22
22
23
An unauthorized purchase is a purchase made without following the authorized procurement processes. An after-the-fact purchase occurs when a University employee places an order without first completing a requisition and receiving a purchase order. 23
24
Result in duplicate payments to the vendor, for which the department is responsible. Result in higher costs for goods and services Lead to significant vendor payment issues that can result in problems for other departments on campus. Bypass the appropriate approval process. Place the University at financial risk and create potential personal liability. Create additional, often unnecessary, work for administrative support staff. 24
25
Ways to Avoid Violations: If you have to place an order, create the requisition right away. Work with the Purchasing Office if you need the order expedited. You must arrange a payment method BEFORE placing an order. “I didn’t know…,” is not a valid excuse for violating policy. 25
26
What to do if a violation occurs: If a violation occurs, fill out all sections of the Purchase Violation Form. ◦ An explanation of why policy was not followed ◦ Future corrective action Attach invoice and send for authorizing signatures Vendor is paid DO NOT enter a requisition. 26
27
27
28
OldNew Bid Limit ◦ $3,000 ◦ $5,000 (Construction) Advertised Limit ◦ $30,000 ◦ $50,000 (Construction) Small-Dollar Purchase Threshold ◦ $5,000 ◦ $15,000 (Construction) Large-Dollar Purchase Threshold ◦ $50,000 28
29
29
30
Methods: ◦ Purchasing Card (P-Card) Must comply with P-Card usage guidelines Default Limit: $1,000 per purchase ◦ Limited Purchase Check (LPC) Must comply with LPC usage guidelines Limits: $150 and $500 ◦ Requisition/Purchase Order Process 30
31
Default limit: $1,000 Auditing process ◦ New preliminary audit report ◦ Clearer deadlines ◦ Adjustment to the point system 31
32
Ordered using a Stores Requisition ◦ Do not mix with regular stores items Return documentation within five business days Don’t return unused checks via intra-campus mail Fewer violations 32
33
Requisitions (Req) are not Purchase Orders (PO) ◦ Orders cannot be placed with requisitions PO must be completed and approved before orders are placed Orders placed before a PO is completed and approved are violations 33
34
Must include all necessary information for purchasing and vendors to understand what is being procured ◦ Minimum specifications ◦ Product numbers and descriptions ◦ Names of individuals and Dates Memberships, conferences, hotels, presenters, performers 34
35
Reqs over the small-dollar purchase threshold Performed by the Purchasing Office Quotes gathered from at least two known vendors Order placed with vendor providing the lowest price Not required if items are available through a contract 35
36
36
37
Requisition/Purchase Order Invitation for Bid Process Enhanced Procurement Methods 37
38
Publically advertised through BidSync.com ◦ Time frame set by buyer Minimum ten calendar days Minimum specifications listed in requisition ◦ Not brand specific ◦ Not unduly restrictive Awarded to vendor providing lowest price 38
39
39
40
Multi-Stage Bid (MSB) Request for Proposals (RFP) Multi-Year Pricing Agreement/Contract Requires justification ◦ Fill out Justification for Enhanced Procurement Method 40
41
41
42
Equipment needed to perform specific experiment Specialized software needed to perform specific function Specialized services 42
43
An MSB is used when potential bidders or potential products must be pre-qualified before requesting priced bids. Objective criteria (pass/fail, quantitative) is used to determine if a potential bidder or potential product meets the minimum qualifications or specifications needed. 43
44
Enter a requisition. ◦ Indicate MSB in the comments field Fill out the Justification for Enhanced Procurement Method If approved, buyer will provide an MSB Statement of Needs and Rating Criteria document Work with the buyer to complete the document 44
45
Bids performed in two stages ◦ Stage 1: Technical/Qualification Allows vendors to submit technical (no cost) written bids outlining capabilities and qualifications. May include demonstrations, presentations, trials, etc. Bids are rated pass/fail based on meeting qualifications and specifications ◦ Stage 2: Cost bids Cost bids are requested from vendors that successfully pass Stage 1 Awarded to vendor providing lowest price in Stage 2 45
46
Technical bids are evaluated by at least three individuals ◦ Acceptable, Potentially Acceptable, Unacceptable Discussions with vendors to clarify technical bids may be held during the evaluation process Minimum timeframe: Two weeks – Stage 1 ◦ Timeframe set by buyer 46
47
47
48
In an RFP process, vendors are asked to submit proposals outlining how they would meet or exceed our needs. A committee evaluates the proposals and rates each proposal based on the criteria contained in the RFP. Following the technical evaluation, a cost evaluation is performed. The award is made to the vendor that will provide the best value to the University. 48
49
Enter a requisition. ◦ Indicate RFP in the comments field Fill out the Justification for Enhanced Procurement Method If approved, buyer will provide an RFP Statement of Needs and Rating Criteria document Work with the buyer to complete the document Timeframe: Four to six weeks ◦ Timeframe set by buyer 49
50
Evaluation is a three stage process ◦ Stage 1: Technical Evaluation Proposals are evaluated subjectively by at least three individuals Each weighted criterion receives a score 1-5 Technical points are combined for each proposal Committee cannot have access to cost information 50
51
Stage 2: Cost Evaluation ◦ The buyer calculates the cost score based on the formula 40 x (2 – Proposed Price / Lowest Proposed Price) ◦ The buyer may work with the committee to clarify proposed costs 51
52
Stage 3 – Composite Score ◦ The technical and cost scores are combined to form the composite score Cost is approx. 30% of total composite score ◦ The contract is awarded to the vendor whose proposal receives the highest composite score May require a cost-benefit analysis 52
53
53
54
The purpose of an RFI is to obtain information, comments, or suggestions from potential bidders before issuing a solicitation. It can also be used to determine whether a solicitation should be issued or to generate interest in a future solicitation. RFIs are not considered a procurement process, but an information gathering process. 54
55
55
56
Bid or RFP Completed by the State or WSCA No additional competition needed Purchase directly 56
57
Department ◦ Elevator Maintenance ◦ Uniforms Campus-wide ◦ Buses 57
58
58
59
Computers ◦ Computer Shop Printers ◦ HP Audio/Visual Equipment ◦ Contact Media Services Furniture 59
60
Software, including apps ◦ Software Ordering System Campus-owned cellphones/aircards Office Supplies 60
61
61
62
Not allowed Exceptions determined by Purchasing ◦ Deposits ◦ Progress Payments 62
63
63
64
This is how it works regardless of: Fund source Sourcing method 64
65
65
66
Sole source procurement may be used when a requirement is only reasonably available from a single supplier ◦ Availability ◦ Compatibility ◦ Transition costs Require justification ◦ New Sole Source Justification Form Not reasons: price, time 66
67
Services performed by individuals. ◦ No product ◦ No companies Requires Responsible Party signature. Second Level approval required for payments $1000 or more. 67
68
Deemed “Independent” by FaBS and Human Resources. Guest Speakers/Performers are always considered independent. Form can be downloaded from the Finance and Business Services Website. ◦ http://uvu.edu/finance/reports-forms-files/ http://uvu.edu/finance/reports-forms-files/ 68
69
Personal reimbursement program No P-Card or LPC Travel Office 69
70