DSG Database Administration Projects Presentation July 09, 2003 CD Projects Status Meeting
2
CDF Offline Hardware Replacement Abstract and Goals Replace the cdf offline sun machine Leader(s) : N.Stanfield, R.Jetton, S.Kovich Stakeholder Orgs: cdf, cd Participants and Effort: cdf applications users, dsg Timeline & Schedule: fall 2003 Deliverables: Sun v880 to replace fcdfora1 Plans: http://www- css.fnal.gov/dsg/external/cdfdbmtgs/cdfdbmtgs/ hardware_replacement_CDF_plan. Comment: Page 2 July 9, 2003 by J.Trumbo
3
D0 Offline Hardware Replacement Abstract and Goals – this project is ½ done. D0ora1 was replaced by d0ora2 6/24. Move d0ora3 to d0ora1 upgrading to oracle 9i, operating system to 2.9 to match d0ora2. Leader(s) : D.Bonham, S.Kovich, S.Vessili Stakeholder Orgs: d0, cd Participants and Effort: d0 applications users, dsg Timeline & Schedule: aug. 2003 Deliverables: Sun v880 to replace d0ora1, move d0ora3 to d0ora1 Plans: to be started after d0ora2 has been in place http://www- css.fnal.gov/dsg/internal/d0_ofl_dbs/D0_swap.h tml Comment: Page 3 July 9, 2003 by J.Trumbo
4
Implement Oracle Streams Abstract and Goals – replace oracle's basic replication process with the oracle streams process for replication of cdf online and offline data. Leader(s) : A.Kumar, N.Stanfield Stakeholder Orgs: cdf, cd Participants and Effort: cdf applications users, dsg Timeline & Schedule: was june 2003, has been extended due to bugs in the streams software when running in conjunction with basic replication. Deliverables: several instances of oracle streams for cdf, replacing basic replication. Plans: http://www- css.fnal.gov/dsg/internal/ora_repl/stream_rep_d ev_strategy.htm Comment: Page 4 July 9, 2003 by J.Trumbo
5
Maintenance and continuing support of sam for d0 and cdf Abstract and Goals – sam database and schema. Leader(s) : A.Kumar, D.Bonham Stakeholder Orgs: cdf, d0, cd Participants and Effort: cdf & d0 applications users, dsg Timeline & Schedule: ongoing Deliverables: current project is to update the schema to allow for additional functionality for multiple run numbers per file, and new luminosity capabilities for both cdf and d0 Plans: continue working with the sam development team. Comment: Page 5 July 9, 2003 by J.Trumbo
6
D0 calibration db server implementation and maintenance Abstract and Goals – deployment of d0 calibration servers. put the product in kits, install on various platforms, configure setup. maintaining web logs for the server diagnostics, training sam shifters and documentation. implemented the failover solution on linux. Leader(s) : A.Kumar Stakeholder Orgs: d0, cd Participants and Effort: d0 applications users, dsg Timeline & Schedule: ongoing Deliverables: packaged calibration server with configuration functions and failover. Plans: continue working with the d0 development team. Potential additional failover scenarios to be implemented. Comment: Page 6 July 9, 2003 by J.Trumbo
7
Implementation of standby database for cdf online Abstract and Goals – implementation of a stand by database using oracle’s data guard, for cdf online, to provide failover for the cdf online processes. Leader(s) : N.Stanfield, A.Kumar, J.Schmitt Stakeholder Orgs: cdf, cd Participants and Effort: cdf applications users, dsg Timeline & Schedule: jan. 2004 Deliverables: a standby database instance for cdf onprd. Plans: http://www- css.fnal.gov/dsg/internal/standby_database/inde x.html Comment: Page 7 July 9, 2003 by J.Trumbo
8
Reverse engineer ATLAS SCT DB ddl provided by cdf into oracle designer Abstract and Goals – reverse engineer of atlas ddl provided by cdf into oracle designer. Leader(s) : N.Stanfield Stakeholder Orgs: cdf, cd Participants and Effort: cdf database team, dsg Timeline & Schedule: july 2003 Deliverables: an entity relationship diagram, a database schema in development, consulting to cdf as needed. Plans: Comment: Page 8 July 9, 2003 by J.Trumbo
9
Implement Oracle Advanced Security Option Abstract and Goals – implement oracle advance security option to run II and miscomp databases. Leader(s) : ?? Stakeholder Orgs: Organizations using oracle databases. Participants and Effort: dsg Timeline & Schedule: late fall 2003 to start planning and testing. Deliverables: a kerberized database logon procedure Plans: a consultant from oracle provided proof of product last fall. will try to get resources to continue work after oct 1. See http://www- css.fnal.gov/dsg/internal/ora_adm/index.htm Comment: Page 9 July 9, 2003
10
Update Matrix v7 to v10 Abstract and Goals – upgrade matrix to matrix 10 using factory upgrade process performed by matrix. Leader(s) : N.Stanfield, J.Trumbo, S.Jones Stakeholder Orgs: cd Participants and Effort: dsg Timeline & Schedule: late summer 2003 to start planning and testing. Deliverables: webized version of matrix in a supportable, certified configuration. Plans: http://www- css.fnal.gov/dsg/internal/matrix/matrix7- 10-upgrade/index.htm Comment: Page 10 July 9, 2003
11
Implement Web Express for Matrix 10 Abstract and Goals – implement web express for matrix 10 on oem dev and the extra nt on wh7 for prod. Leader(s) : N.Stanfield, J.Trumbo, S.Jones Stakeholder Orgs: cd Participants and Effort: dsg Timeline & Schedule: late summer 2003 to purchase, plan and testing. Deliverables: a web server for matrix 10 running in dev/int/prod. Plans: http://www- css.fnal.gov/dsg/internal/matrix/matrix7- 10-upgrade/index.htm Comment: Page 11 July 9, 2003
12
Node Registration Rewrite Abstract and Goals – rewrite node registration to improve functionality and maintainability. Leader(s) : S.Jones Stakeholder Orgs: all who use the network at fermi. Participants and Effort: dsg Timeline & Schedule: started may 2003, to be complete end of 2003. Deliverables: new improved forms for tracking new nodes, sysadmins, and equipment. Plans: http://www- css.fnal.gov/dsg/internal/node_registration/ index.html Comment: Page 12 July 9, 2003
13
Upgrade applications on g1 & h1 to Oracle 9i Abstract and Goals – upgrade of applications on fncdug1 and fncduh1 to oracle 9i. Leader(s) : S.Jones Stakeholder Orgs: cd departments using miscomp. Participants and Effort: dsg, aps Timeline & Schedule: not yet determined. Deliverables: upgrade of all oracle products to v9i including forms, reports, application server, and database. Plans: no plans yet Comment: Page 13 July 9, 2003
14
Minos Abstract and Goals – implement a dev/int/prd database for minos, including the writing of an mou between minos and cd. Leader(s) : J.Trumbo, N.Stanfield Stakeholder Orgs: cd, minos Participants and Effort: dsg, minos Timeline & Schedule: mou to be written this summer. Deliverables: an mou that details the longer term maintenance agreement between cd and minos involving the support and maintenance of minos databases. Plans: Comment: Page 14 July 9, 2003
15
CMS Abstract and Goals – support for cms for calibration Leader(s) : A.Kumar Stakeholder Orgs: cd, cms Participants and Effort: dsg, cms Timeline & Schedule: Apr.2003 to present Deliverables: consulting and training for oracle designer, and relational database concepts to support the cms calibration prototype. provide an oracle instance for testing. Plans: meeting in cern july 2003 to determine direction of prototype implementation and responsibilities. Comment: Page 15 July 9, 2003