Bond Construction Update Citizens Oversight Committee Long Beach Community College District August 8, 2011 EDUCATE  ENGAGE  EMPOWER 1.

Similar presentations


Presentation on theme: "Bond Construction Update Citizens Oversight Committee Long Beach Community College District August 8, 2011 EDUCATE  ENGAGE  EMPOWER 1."— Presentation transcript:

1 Bond Construction Update Citizens Oversight Committee Long Beach Community College District August 8, 2011 EDUCATE  ENGAGE  EMPOWER 1

2 Agenda Completed Construction Projects LAC South Walkway Extension LAC Infrastructure Improvements Project and District Wide – Energy Efficiency Project Current Construction Projects LAC Building A – Student Services Retrofit LAC Building I (Bookstore) LAC W Trailers Demo LAC Master Landscape PCC MDAB (Multi-Disciplinary Academic Building) PCC Tech 1 (Sheet Metal) Upcoming Construction Projects LAC Stadium Parking Lot Lights and Stadium Lights PCC Building CC Retrofit LAC Math Technology Building PCC Building GG LAC Building C Retrofit Q & A 2

3 Completed Construction Projects LAC South Walkway Extension Measure E 2008 Measure E 2008 3 Project complete Palm trees to be replaced August 2011 Continues Master Plan pedestrian corridor

4 4 LAC Infrastructure Improvement Project and District Wide Energy Efficiency Project Measure E 2008 Completed Construction Projects Total annual estimated savings of 1.5 mil. Kwh Project started Fall 2009; currently hydro seeding all affected areas(All phases) Majority of existing building HVAC systems to be upgraded and connected to the Central Plant Buildings B,C,D,E,G, & H are connected Exterior lighting and controls upgrades All parking lots north of Lew Davis are on new system New Reclaimed Water tie-ins to irrigation connected New gas lines installed for Buildings B, C, D, E, G, H, J, M, N, and P New domestic lines installed for Buildings B, C, D, E, F, G, H, I Trailers, J, K,L, M, N, P Construction completed Summer 2011

5 Current Construction Projects LAC Building A – Student Services Retrofit Measure E 2008 5 New home for A&R, Counseling, Health Services, Cashier, Transfer Center Project currently in structural upgrade End of construction anticipated Summer 2012

6 Current Construction Projects 6 Adds additional 4,000 square feet to existing building Architecture to match LAC Mediterranean Theme Work on framing and utilities underway End of Construction anticipated Fall 2011 LAC Building I - Measure E 2008

7 Current Construction Projects 7 Grading of lot and paving to be completed this month Project will address storm run off issues with bio swales Site to be converted to a parking lot Estimated project completion Summer 2011 LAC W Trailers Demo - Measure E 2008

8 Current Construction Projects 8 Currently in Design Phase(Finalizing design) Plans to be submitted to DSA in August Quad areas North and South of Bldg. A will bid Fall 2011 Remaining areas designed at 25% Scope includes new hardscape/landscape and pedestrian pathways LAC Master Landscape - Measure E 2008

9 Current Construction Projects PCC MDAB (Multi-Disciplinary Academic Building) Measure E 2008 9 MDAB building remodel project Phase 1 of 2 currently under construction Project currently in demolition and structural reinforcement Phase 1 Project to be completed Summer 2012

10 Current Construction Projects 10 Construction started Summer 2011 Equipment and utilities currently being installed Projected to be completed before start of Fall semester 2011 PCC Tech 1 (Sheet Metal) - Measure E 2008

11 11 Stadium Parking Lot Lights and Stadium Lighting Measure E 2008 Upcoming Construction Projects Stadium parking lot lights and Stadium lighting retrofit Awaiting final DSA approval Estimated start of construction Fall 2011

12 Upcoming Construction Projects PCC Building CC Retrofit - Measure E 2008 12 Houses the Fitness Center, Gymnasium, Weight Room, and Faculty and Staff Offices Swing space located on PCC Campus (Bldg. GG) Approved by DSA on 1/27/11. Currently in bid process To be completed concurrently with MDAB project phase 1 Anticipated end of construction Fall 2012

13 Upcoming Construction Projects Will house Math and Culinary Arts instructional program as well as Reprographics Design Build delivery method Currently Requesting Qualifications (RFQ) Due 8/3 Shortlist and interview 5 respondents (TBD) Select 3 and request for proposals Anticipated start of construction 2013 LAC Math Technology Building – Measure E 2008 13

14 Upcoming Construction Projects PCC Building GG - Measure E 2008 14 Design Build delivery method Request for Qualifications (RFQ) Start in September and due late October Building to house Health Services, EOPS, DSPS, Financial Aid, Cashier, A&R, and Counseling Estimated start of construction December 2013

15 Upcoming Construction Projects LAC Building C Retrofit - Measure E 2008 15 Hired Architect to do design work Currently in schematic phase Work includes modernization of structure, classrooms spaces, and office areas

16 l i b e r a l a r t s Liberal Arts Campus Site Plan

17 p a c i f i c c o a s t Pacific Coast Campus Site Plan