1 Advanced Construction Technology
By Professor Chris Gorse , Joseph Kangwa & Ian Dickinson – licensed under the Creative Commons Attribution – Non-Commercial – Share Alike License

2 Skeleton frames: Assembling
Chris Gorse, Joseph Kangwa and Ian Dickinson These slides should be read in conjunction with Emmitt, S. and Gorse, C. (2010) Barry’s Advanced Construction of Buildings. Oxford, Blackwell Publishing

3 Multi-story skeleton frame

4 Skeleton frames The following drawing shows a three dimensional view of a steel frame

5

6 Actual frame

7

8

9 The completed building

10 precast stairs are provide a fast and safe installation into the steel frame

11 Lining the building up The building will twist slightly as it is erected. Before casting any concrete any movement in the structure needs to be corrected. Winches are used to pull the building back in line.

12 As the building is erected it will need to be pulled into line.

13 Bracing Triangulation and solid infill walls are used to hold the structure rigid and resist horizontal loads such as wind.

14 Wind bracing

15 Roof bracing and composite floor provide lateral resistance against wind loads

16 Fixing the frame together

17 Roof beam to column connection

18 Column to column – spliced and bolted connection
Universal column Column prefabricated with end plate All holes for bolts are accurately predrilled off site Splice plate bolted to both top and bottom column End plates welded to the end of each column and bolted together

19 Splice fixing ready to receive next column

20 Column to column splice fixing

21 Column base and holding down bolts
Steel wedge holds the base in the correct line (position) Base plate welded to column (plate minimum 12mm thick) Steel packing shims fix column at correct level Temporary bund wall (sand) None shrinkable grout fills void left below plate (liquid grout poured into voids) Void formed by cardboard or polystyrene cones, which allows +/- 20mm horizontal tolerance is filled with grout Large washer fixed to bolt to prevent pull out

22 Holding down bolts cast in concrete

23 Holding down bolt in temporary frame which would be cast into a concrete base

24 Beam connection using end plates welded to the beam
Universal column Beam prefabricated with end plate welded to the beam. End plate Holes for bolts predrilled in column and beam end plate ensuring accurate fixing

25 Beam to column connection

26 Further information supporting these slides can be found in the following publication and websites.
Emmitt, S. and Gorse, C. (2010) Barry’s Introduction to Construction of Buildings. Oxford, Blackwell Publishing Emmitt, S. and Gorse, C. (2010) Barry’s Advanced Construction of Buildings. Oxford, Blackwell Publishing Virtual Site (2010) Virtual Site at Leeds Met University Virtual Site Gallery (2010) Virtual Site Gallery at Leeds Met University


Download ppt "Advanced Construction Technology"