WASTE MANAGEMENT HIERARCHY Cleaner Production / Waste Minimisation Treatment Reuse / Recover / Recycle Disposal
4
Challenges Quality requirements Energy requirements Land requirements Operation and Maintenance
6
Advanced Biological Treatments Include Membrane Bioreactor (MBR) Sequential Batch Reactor (SBR) Moving Bed Bioreactor (MBBR) Pure Oxygen Technology Biological Heavy Metal Removal ADVANCED BIOLOGICAL TREATMENTS
7
Typical Volumetric Loading and Removal Efficiency for Various Systems System Rate (kg BOD/m 3.d) Typical Loading Removal Efficiency (%) Complete Mix ASP0.3 – 1.685 - 92 Extended Aeration0.1 – 0.395 -98 Membrane Bioreactor1.8 – 5.796 - 99 Moving Bed Bioreactor1.0 – 1.491 - 98 Sequencing Bioreactor0.1 – 0.397 – 99 High Purity Oxygen1.3 - 3.296 - 98
8
FLOW TO CONVENTIONAL ETP : 750 M 3 /HR (435 M 3 /HR DISCHARGED AFTER TREATMENT ALONGWITH 66 M 3 /HR OF RO REJECT) FLOW TO FILTRATION UNIT & UF : 315 M 3 /HR UF PERMEATE : 315 M 3 /HR (218 M 3 /HR IS SUBJECTED TO RO & 97 M 3 /HR IS BLENDED WITH RO PERMEATE & EVENTUALLY USED FOR COOLING TOWER MAKE UP) FLOW TO RO SYSTEM : 218 M 3 /HR RO PERMEATE RECOVERED : 152 M 3 /HR BLENDED WITH UF PERMEATE & USED AS COOLING WATER MAKE UP RO REJECT : 66 M 3 /HR IS DISCHARGED ALONGWITH BIOLOGICALLY TREATED WASTEWATER WATER RECOVERED = 97 + 152 = 249 M 3 /HR USED AS COOLING TOWER MAKE UP REFINERY WASTEWATER BALANCE
9
DETAILS OF WASTEWATER TREATMENT - REFINERY PRIMARY TREATMENT TERTIARY TREATMENT - IS SUMP - FILTER FEED / CHLORINATION SUMP - SS SUMP - DMF & ACF - SURGE TANKS - HRSCC - SPLITTER BOX - MULTIGRADE FILTER - API - BASKET STRAINER - TPI - ULTRA FILTRATION - DAF - REVERSE OSMOSIS - CHEMICAL DOSING SYSTEMS - CHEMICAL DOSING SYSTEM SECONDARY TREATMENT - BIOTOWER FEED SUMP - BIOTOWER - AERATION TANK - SECONDARY CLARIFIER -GUARD POND -CHEMICAL DOSING SYSTEMS PRELIMINARY TREATMENT UNITS FOR SPENT CAUSTIC - SPENT CAUSTIC TANK, REACTION TANK, H 2 O 2 DOSING SYSTEM TREATMENT UNITS FOR COMBINED WASTEWATER
10
EMULSIONS PLANT- WATER BALANCE TOTAL WATER REQUIREMENT - 253 M 3 /DAY TOTAL EFFLUENT FROM PLANT FLOWING TO ETP -128 M 3 /DAY (Including reject from WTP RO) PERMEATE RECOVERED FROM ETP – 99 M 3 /DAY (87 M 3 /DAY USED AS WTP FEED & 12 M 3 /DAY USED AS BOILER MAKE UP) RO REJECT (28 M 3 /DAY) FROM ETP SUBJECTED TO EVPORATION (CONDENSATE RECOVERD : 28 M 3 /DAY USED AS WTP FEED) SOLID WASTE FROM ETP (1 M 3 /DAY) & RMS : 0.5 TPD (85% DRY SOLIDS) FOR LANDFILL LIQUID EFFLUENT DISCHARGE – ZERO WATER RECOVERED = 127 M 3 /DAY, 115 M 3 /DAY USED AS WTP FEED & 12 M 3 /DAY USED AS BOILER FEED FRESH RAW WATER REQUIREMENT - 126 M 3 /DAY
11
REJECT MANAGEMENT SYSTEM (RMS) WATER TREATMENT PLANT (WTP) WASTEWATER TREATMENT PLANT (WWTP) COOLING TOWER MAKE UP FLOOR WASH DOMESTIC PROCESS & UTILITIES 103 M 3 /D 88 M 3 /D 48 M 3 /D 10 M 3 /D 45 M 3 /D RO PERMEATE FOR UF BACKWASH BOILER & CT BLOWDOWN 15 M 3 /D 8 M 3 /D DOMESTIC EFFLUENT PROCESS EFFLUENT 55 M 3 /D RO REJECT PF BACKWASH MGF BACKWASH SOLIDS FOR DISPOSAL RO PERMEATE TO BOILER MAKEUP 12 M 3 /D 99 M 3 /D 87 M 3 /D RAW WATER FROM BOREWELL 126 M 3 /D RO PERMEATE TO SECURED LANDFILL 1M 3 /D DRY SLUDGE SLUDGE 25 M 3 /D 6 M 3 /D5 M 3 /D 3 M 3 /D RO REJECT 28 M 3 /D CONDENSATE 28 M 3 /D 11 M 3 /D WATER BALANCE DIAGRAM- EMUSIONS PLANT
12
DETAILS OF WTP - EMULSIONS PLANT -RAW WATER STORAGE TANK -HRSCC -PRESSURE SAND FILTER (PSF) - ULTRA VIOLET UNIT (UV) - REVERSE OSMOSIS UNIT (RO) - CHEMICAL DOSING SYSTEM
13
TOTAL WATER REQUIREMENT - 4030 M 3 /DAY TOTAL EFFLUENT FLOWING TO ETP - 3178 M 3 /D 100 M 3 /D CTBD USED FOR GREEN BELT DIRECTLY 250 M 3 /D NEUTRALISED DM REG. USED FOR GREEN BELT 1070 M 3 /D OF UF PERMEATE RECYCLED TO DM PLANT 1025 M 3 /D OF UF PERMEATE RECYCLED AS CT MAKEUP 786 M 3 /D RO PERMEATE RECYCLED TO PROCESS RO REJECT (197 M 3 /D) & SLUDGE (100 M 3 /D) FROM ETP SUBJECTED TO EVPORATION (290 M 3 /D OF CONDENSATE RECOVERED USED FOR PROCESS) SOLIDWASTE FROM RMS : 5.8TPD (85% DRY SOLIDS) FOR LANDFILL LIQUID EFFLUENT DISCHARGE – ZERO WATER RECOVERED = 100+250+1070+1025+786+290 = 3521 M 3 /D FRESH RAW WATER REQUIREMENT - 509 M 3 /D PVC PLANT – WATER BALANCE
14
WATER RECOVERY PLANT FLOWSHEET FOR PVC PLANT