Download presentation
Presentation is loading. Please wait.
Published byElaina Hinman Modified over 10 years ago
1
3 - 1 Course Title: Production and Operations Management Course Code: MGT 362 Course Book: Operations Management 10 th Edition. By Jay Heizer & Barry Render
2
3 - 2 Chapter 3: Project Management
3
3 - 3 Project Planning The Project Manager Work Breakdown Structure Project Scheduling Project Controlling Project Management Techniques: PERT and CPM The Framework of PERT and CPM Summary Of The Previous Presentation
4
3 - 4 Outline Project Planning The Project Manager Work Breakdown Structure Project Scheduling Project Controlling Project Management Techniques: PERT and CPM The Framework of PERT and CPM Network Diagrams and Approaches Activity-on-Node Example Activity-on-Arrow Example
5
3 - 5 Outline - Continued Determining the Project Schedule Forward Pass Backward Pass Calculating Slack Time and Identifying the Critical Path(s) Variability in Activity Times Three Time Estimates in PERT Probability of Project Completion Cost-Time Trade-Offs and Project Crashing A Critique of PERT and CPM Using Microsoft Project to Manage Projects
6
3 - 6 A Comparison of AON and AOA Network Conventions Activity onActivityActivity on Node (AON)MeaningArrow (AOA) A comes before B, which comes before C. (a) A B C BAC A and B must both be completed before C can start. (b) A C C B A B B and C cannot begin until A is completed. (c) B A C A B C Figure 3.5
7
3 - 7 A Comparison of AON and AOA Network Conventions Activity onActivityActivity on Node (AON)MeaningArrow (AOA) C and D cannot begin until both A and B are completed. (d) A B C D B AC D C cannot begin until both A and B are completed; D cannot begin until B is completed. A dummy activity is introduced in AOA. (e) CA BD Dummy activity A B C D Figure 3.5
8
3 - 8 A Comparison of AON and AOA Network Conventions Activity onActivityActivity on Node (AON)MeaningArrow (AOA) B and C cannot begin until A is completed. D cannot begin until both B and C are completed. A dummy activity is again introduced in AOA. (f) A C DB AB C D Dummy activity Figure 3.5
9
3 - 9 AON Example ActivityDescription Immediate Predecessors ABuild internal components— BModify roof and floor— CConstruct collection stackA DPour concrete and install frameA, B EBuild high-temperature burnerC FInstall pollution control systemC GInstall air pollution deviceD, E HInspect and testF, G Milwaukee Paper Manufacturing's Activities and Predecessors Table 3.1
10
3 - 10 ActivityDescriptionTime (weeks) ABuild internal components2 BModify roof and floor3 CConstruct collection stack2 DPour concrete and install frame4 EBuild high-temperature burner4 FInstall pollution control system 3 GInstall air pollution device5 HInspect and test2 Total Time (weeks)25
11
3 - 11 Activit yDescriptionImmediate Predecessors ABuild internal components — BModify roof and floor— CConstruct collection stack A DPour concrete and install frame A, B EBuild high-temperature burner C FInstall pollution control system C GInstall air pollution deviceD, E HInspect and testF, G
12
3 - 12 AON Network for Milwaukee Paper G E F H C A Start DB Arrows Show Precedence Relationships Figure 3.8
13
3 - 13 H (Inspect/ Test) 7 Dummy Activity AOA Network for Milwaukee Paper 6 F (Install Controls) E (Build Burner) G (Install Pollution Device) 5 D (Pour Concrete/ Install Frame) 4 C (Construct Stack) 1 3 2 B (Modify Roof/Floor) A (Build Internal Components) Figure 3.9
14
3 - 14 Determining the Project Schedule Perform a Critical Path Analysis The critical path is the longest path through the network The critical path is the shortest time in which the project can be completed Any delay in critical path activities delays the project Critical path activities have no slack time
15
3 - 15 Determining the Project Schedule Perform a Critical Path Analysis Table 3.2 ActivityDescriptionTime (weeks) ABuild internal components2 BModify roof and floor3 CConstruct collection stack2 DPour concrete and install frame4 EBuild high-temperature burner4 FInstall pollution control system 3 GInstall air pollution device5 HInspect and test2 Total Time (weeks)25
16
3 - 16 Determining the Project Schedule Perform a Critical Path Analysis Table 3.2 ActivityDescriptionTime (weeks) ABuild internal components2 BModify roof and floor3 CConstruct collection stack2 DPour concrete and install frame4 EBuild high-temperature burner4 FInstall pollution control system 3 GInstall air pollution device5 HInspect and test2 Total Time (weeks)25 Earliest start (ES) =earliest time at which an activity can start, assuming all predecessors have been completed Earliest finish (EF) =earliest time at which an activity can be finished Latest start (LS) =latest time at which an activity can start so as to not delay the completion time of the entire project Latest finish (LF) =latest time by which an activity has to be finished so as to not delay the completion time of the entire project
17
3 - 17 Determining the Project Schedule Perform a Critical Path Analysis Figure 3.10 A Activity Name or Symbol Earliest Start ES Earliest Finish EF Latest Start LS Latest Finish LF Activity Duration 2
18
3 - 18 Forward Pass Begin at starting event and work forward Earliest Start Time Rule: If an activity has only a single immediate predecessor, its ES equals the EF of the predecessor If an activity has multiple immediate predecessors, its ES is the maximum of all the EF values of its predecessors ES = Max {EF of all immediate predecessors}
19
3 - 19 Forward Pass Begin at starting event and work forward Earliest Finish Time Rule: The earliest finish time (EF) of an activity is the sum of its earliest start time (ES) and its activity time EF = ES + Activity time
20
3 - 20
21
3 - 21 E4E4 F3F3 G5G5 H2H2 481315 4 813 7 D4D4 37 C2C2 24 ES/EF Network for Milwaukee Paper B3B3 03 Start 0 0 0 A2A2 20 Figure 3.11
22
3 - 22 Backward Pass Begin with the last event and work backwards Latest Finish Time Rule: If an activity is an immediate predecessor for just a single activity, its LF equals the LS of the activity that immediately follows it If an activity is an immediate predecessor to more than one activity, its LF is the minimum of all LS values of all activities that immediately follow it LF = Min {LS of all immediate following activities}
23
3 - 23 Backward Pass Begin with the last event and work backwards Latest Start Time Rule: The latest start time (LS) of an activity is the difference of its latest finish time (LF) and its activity time LS = LF – Activity time
24
3 - 24 LS/LF Times for Milwaukee Paper E4E4 F3F3 G5G5 H2H2 481315 4 813 7 D4D4 37 C2C2 24 B3B3 03 Start 0 0 0 A2A2 20 LF = EF of Project 1513 LS = LF – Activity time
25
3 - 25 LS/LF Times for Milwaukee Paper E4E4 F3F3 G5G5 H2H2 481315 4 813 7 15 D4D4 37 C2C2 24 B3B3 03 Start 0 0 0 A2A2 20
26
3 - 26 LS/LF Times for Milwaukee Paper E4E4 F3F3 G5G5 H2H2 481315 4 813 7 15 1013 8 48 D4D4 37 C2C2 24 B3B3 03 Start 0 0 0 A2A2 20 42 84 20 41 00
27
3 - 27 Computing Slack Time After computing the ES, EF, LS, and LF times for all activities, compute the slack or free time for each activity Slack is the length of time an activity can be delayed without delaying the entire project Slack = LS – ES or Slack = LF – EF
28
3 - 28 Computing Slack Time Table 3.3 EarliestEarliestLatestLatestOn StartFinishStartFinishSlackCritical ActivityESEFLSLFLS – ESPath A02020Yes B03141No C24240Yes D37481No E48480Yes F4710136No G8138130Yes H131513150Yes
29
3 - 29 Critical Path for Milwaukee Paper E4E4 F3F3 G5G5 H2H2 481315 4 813 7 15 1013 8 48 D4D4 37 C2C2 24 B3B3 03 Start 0 0 0 A2A2 20 42 84 20 41 00
30
3 - 30 ES – EF Gantt Chart for Milwaukee Paper ABuild internal components BModify roof and floor CConstruct collection stack DPour concrete and install frame EBuild high- temperature burner FInstall pollution control system GInstall air pollution device HInspect and test 12345678910111213141516
31
3 - 31 LS – LF Gantt Chart for Milwaukee Paper ABuild internal components BModify roof and floor CConstruct collection stack DPour concrete and install frame EBuild high- temperature burner FInstall pollution control system GInstall air pollution device HInspect and test 12345678910111213141516
32
3 - 32 Summary Project Management Techniques: PERT and CPM The Framework of PERT and CPM Network Diagrams and Approaches Activity-on-Node Example Activity-on-Arrow Example Determining the Project Schedule Forward Pass Backward Pass Calculating Slack Time and Identifying the Critical Path(s)
33
3 - 33
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.