BUILDING STRONG ® US Army Corps of Engineers BUILDING STRONG ® Portland & Walla Walla Districts Columbia-Snake River System Extended Navigation Lock Outage December 2010 – March 2011 Matt Cutts, P.E., CFM Critical Infrastructure Program Manager Portland District, U.S. Army Corps of Engineers Pacific Northwest Waterways Association 2011 Mid-Year Meeting June 27, 2011 1
2
BUILDING STRONG ® 2
3
Overview Coordination started 18 months before the outage. Estimated 12-16 week outage, took 15 weeks. Timing arranged to minimize impacts as much as possible. Locks had to be open by 1 April to allow Fish Barging per BiOp. Main Commodities affected: ► Wheat ► Fuel/gas transport up river ► Garbage ► Commercial - recreation cruise liners 3
4
BUILDING STRONG ® Outage Work Plan Bonneville: Routine maintenance & emergency repair The Dalles: Downstream gate replacement John Day: Downstream gate & sheave replacement McNary: 5 Year Lock inspection and maintenance Ice Harbor: Downstream Gate picking eye repair Lower Monumental: Downstream gate replacement, Phase 2 concrete repairs Little Goose: Routine maintenance Lower Granite: Upstream & downstream gate repairs 4
5
BUILDING STRONG ® Damaged Top Girder (both leaves) Damaged Diagonals (both leaves) Bonneville Dam Navigation Lock Upstream Gate Emergency Repair 5
6
BUILDING STRONG ® The Dalles Navigation Lock Outage The downstream gate and both pintle bearings were replaced Dix Corporation of Spokane, WA was the prime contractor Subcontractor Thompson Metal Fab was the steel fabricator, along with Oregon Iron Works Fabrication started in April 2010, completed by Feb 2011 6
7
BUILDING STRONG ® The Dalles old gate removal 7
8
BUILDING STRONG ® The Dalles gate hardware 8
9
BUILDING STRONG ® John Day Navigation Lock Downstream gate & sheave replacement Replaced downstream gate & friction sheaves Prime: Advanced American Construction Subcontractor: Oregon Iron Works of Clackamas Fabrication: Dec 2009 - Oct 2010 9
10
BUILDING STRONG ® McNary Navigation Lock Outage Duration 6-Weeks Routine work 5 Year Major Inspection Detailed maintenance and lubrication Repair work Non Routine work Rehab stop logs Replace Tainter Valve Trash Racks Repair Navlock Armor steel Completed Rehab of Navlock Cranes 10
11
BUILDING STRONG ® McNary: 5 Year Inspection 11
12
BUILDING STRONG ® Ice Harbor Navigation Lock Outage Duration 9-Weeks Routine Work: 5 Year Major Inspection Detailed maintenance and lubrication Repair work Non-Routine work D/S Gate Cable/ Connectors - included cable replacement. Scheduled but not completed. 12
13
BUILDING STRONG ® Longitudinal cracks in top slab of culvert Large crack in joint between top slab & sides. Collapse of concrete into culvert Ice Harbor: Emptying Lateral Damage Damage found after unwatering lock Repairs critical to prevent concrete from entering fill/drain culvert Fast tracked contract to repair 13
14
BUILDING STRONG ® 14 BUILDING STRONG ® Ice Harbor: Downstream cable connection/upstream trunnion hubs Trunnion pin backed out, keeper plate failed Plan to complete cable connections in FY12. Monitoring gate for cracks, made interim repairs, requested add’l FY13 funding 14
15
BUILDING STRONG ® Lower Monumental Navigation Lock Outage Duration 15-Weeks Routine Upstream gate and ancillary equipment inspections Detailed maintenance and lubrication Repair work Non-Routine Replace downstream gate, cables and gear boxes Navlock Concrete Repairs Phase 2 Replace U/S gate seal 15
16
BUILDING STRONG ® Lower Monumental downstream gate replacement 16
17
BUILDING STRONG ® Extremely complex heavy-lifting Coordinated between project & contractors to minimize disruption to operations Coordinated with State and County road departments for mob and de-mob Lower Monumental: Downstream Gate Replacement 17
18
BUILDING STRONG ® Next Steps - Hoist Machinery Upgrades LOMO Existing EquipmentJohn Day New Equipment Lower Monumental: Downstream Gate Replacement 18
19
BUILDING STRONG ® Lower Monumental: Concrete Repair Phase 1 Phase 2 Phase 3 19
20
BUILDING STRONG ® Little Goose Navigation Lock Outage Duration 5-Weeks Routine work Lock/gate and ancillary equipment inspections Detailed maintenance and lubrication Repair work 20
21
BUILDING STRONG ® Lower Granite Navigation Lock Outage Duration 8-Weeks Routine Work Lock/gate and ancillary equipment inspections Detailed maintenance and lubrication Repair work Non Routine Work U/S gate detailed inspection and skin plate repairs/painting Tainter drain valve #1 skin plate repair 21
22
BUILDING STRONG ® Outcomes from 2010 - 2011 Extended Navigation Lock Outage Took major steps to restore the reliability of the Columbia – Snake River Navigation System Completed backlog of Navigation Lock maintenance work Updated Navigation Operational Condition Assessments. Established a coordinated and collaborative process for current and future work on the System. 22
23
BUILDING STRONG ® Planning and communication with stakeholders before and during outage Coordination between NWP and NWW before and during outage Aggressive schedule and ARRA funding Market research and contractor selection Design and contract development Team building and partnerships Challenges & Keys To Success 23
24
BUILDING STRONG ® Future Outages Potential work: Replacement of The Dalles & Ice Harbor upstream gates Little Goose & McNary miter gate repairs Lower Monumental electrical/mechanical systems repairs Interim repairs at other navigation locks 24
25
BUILDING STRONG ® Installation of New Gate Sections 15 Jan – 24 Feb 2011 John Day Navigation Lock D/S Gate and Sheave Replacement 25
26
BUILDING STRONG ® Questions? Portland District Public Affairs Office (503) 808-4510 cenwp-pa@usace.army.mil http://www.nwp.usace.army.mil/ Portland District Critical Infrastructure Program Manager Matt Cutts (503) 808-4697 Walla Walla District Public Affairs Office (509) 527-7020 cenww-pa@usace.army.mil http://www.nww.usace.army.mil/ Navigation System Questions: Ann Glassley (509) 527-7115 26