Railway Engineers Forum Scotland Young Railway Professionals’ Presentation Competition Northwich Diversion Gauge Clearance William Storey Graduate Civil.

Similar presentations


Presentation on theme: "Railway Engineers Forum Scotland Young Railway Professionals’ Presentation Competition Northwich Diversion Gauge Clearance William Storey Graduate Civil."— Presentation transcript:

1 Railway Engineers Forum Scotland Young Railway Professionals’ Presentation Competition Northwich Diversion Gauge Clearance William Storey Graduate Civil Engineer - Babcock

2 Contents Project background Works overview Delivery plan –Track works –Drainage My role

3 Project background The Northwich Diversion route was cleared to W8 gauge to enable freight traffic to be diverted allowing for access on the Liverpool to Manchester line to carry out electrification works. This involved 5 track lowers at 4 bridges.

4 Project contracts GRIP 3-8 –NR4 for GRIP 3-5 –NR9 for GRIP 6-8 Project came off the back of Liverpool to Manchester (phase 1) which was a number of track lowers on the line being electrified Contract value –Northwich Diversion circa £600k –Total value of Liverpool to Manchester and Northwich Diversion circa £1million Project awarded 17 weeks before 1 st core possession The work was delivered in November 2011

5 Track lowering works StructureOB07OB08OB45OB46 LineUp MainDn MainUp MainDn MainUp Main Max Lower (vertical) 300mm34mm198mm263mm148mm Lower extents (horizontal) 230m110m with 540m of realignment 230m240m250m Rail50% - reused 50% - renewed renewed reused Sleepers50% - reused 50% - renewed reusedrenewed

6 Delivery plan Wk 29 –Sun 00:10 – Sun 09:15 (Prep) –Tue 00:30 – Tue 05:30 (CWR drop) Wed 00:30 – Wed 05:30 (Prep / Drainage investigation) –Thur 00:30 Thur 05:30 (Prep / Drainage investigation) Wk 34 –Sat 00:05 – Mon 06:30 (Core works – Up main) Wk 35 –Sat 00:05 – Mon 06:30 (Core works - Dn main) –Midweek Speed off tamps 00:30 – 05:30 (Mon, Tue, Wed & Thur night) Wk 36 –00:15 Sun – 06:00 Mon –Follow up works (Welding, Stressing, Snagging for TOC)

7 OB08 (Dn Main) Effectively a single line under the bridge KIROW 250 used to Panel out and in 60ft sections

8 OB08 Staging Hale Crossover UM DM ← Ashley StationHale Station → 6Y16 Sat 00:15 - Sat 22:00 LOCO,10 LD Autohopper 6Y17 Sat 01:00 - Sun 15:00 LOCO, Support, KIROW, Runner, 3MT Salmons, 1MT Tench, 10MT Falcons, LOCO (from site only) 1.Trains access from Northenden 2.KIROW lifts out panels onto 6Y17 3.Scarify, grade and compact using 2 X PC138, D41 Dozer and Triple Whacker. Load into 6Y17 (10MT Falcons) 4.KIROW relay panels from 6Y17 5.Unload bottom stone from 6Y17 and profile using 2 X PC138 and RRV 6.Tamper site 7.Re-rail panelled section using McCulloch 8.Welding & Stressing operations 6Y16 6Y176Y18 KIROW

9 Bridge 8 – Ashley Road 9 Hale Crossover UM DM ← Ashley StationHale Station → 6Y16 Sat 00:15 - Sat 22:00 LOCO,10 LD Autohopper 6Y17 Sat 01:00 - Sun 15:00 LOCO, Support, KIROW, Runner, 3MT Salmons, 1MT Tench, 10MT Falcons, LOCO (from site only) 1.Trains access from Northenden 2.KIROW lifts out panels onto 6Y17 3.Scarify, grade and compact using 2 X PC138, D41 Dozer and Triple Whacker. Load into 6Y17 (10MT Falcons) 4.KIROW relay panels from 6Y17 5.Unload bottom stone from 6Y17 and profile using 2 X PC138 and RRV 6.Tamper site 7.Re-rail panelled section using McCulloch 8.Welding & Stressing operations 6Y16 6Y17

10 Bridge 8 – Ashley Road 10 Hale Crossover UM DM ← Ashley StationHale Station → 6Y16 Sat 00:15 - Sat 22:00 LOCO,10 LD Autohopper 6Y17 Sat 01:00 - Sun 15:00 LOCO, Support, KIROW, Runner, 3MT Salmons, 1MT Tench, 10MT Falcons, LOCO (from site only) 1.Trains access from Northenden 2.KIROW lifts out panels onto 6Y17 3.Scarify, grade and compact using 2 X PC138, D41 Dozer and Triple Whacker. Load into 6Y17 (10MT Falcons) 4.KIROW relay panels from 6Y17 5.Unload bottom stone from 6Y17 and profile using 2 X PC138 and RRV 6.Tamper site 7.Re-rail panelled section using McCulloch 8.Welding & Stressing operations 6Y16 6Y17

11 Bridge 8 – Ashley Road 11 Hale Crossover UM DM ← Ashley StationHale Station → 6Y16 Sat 00:15 - Sat 22:00 LOCO,10 LD Autohopper 6Y17 Sat 01:00 - Sun 15:00 LOCO, Support, KIROW, Runner, 3MT Salmons, 1MT Tench, 10MT Falcons, LOCO (from site only) 1.Trains access from Northenden 2.KIROW lifts out panels onto 6Y17 3.Scarify, grade and compact using 2 X PC138, D41 Dozer and Triple Whacker. Load into 6Y17 (10MT Falcons) 4.KIROW relay panels from 6Y17 5.Unload bottom stone from 6Y17 and profile using 2 X PC138 and RRV 6.Tamper site 7.Re-rail panelled section using McCulloch 8.Welding & Stressing operations 6Y16 6Y17

12 Bridge 8 – Ashley Road 12 Hale Crossover UM DM ← Ashley StationHale Station → 6Y16 Sat 00:15 - Sat 22:00 LOCO,10 LD Autohopper 6Y17 Sat 01:00 - Sun 15:00 LOCO, Support, KIROW, Runner, 3MT Salmons, 1MT Tench, 10MT Falcons, LOCO (from site only) 1.Trains access from Northenden 2.KIROW lifts out panels onto 6Y17 3.Scarify, grade and compact using 2 X PC138, D41 Dozer and Triple Whacker. Load into 6Y18 (20MT Falcons) 4.KIROW relay panels from 6Y17 5.Unload bottom stone from 6Y17 and profile using 2 X PC138 and RRV 6.Tamper site 7.Re-rail panelled section using McCulloch 8.Welding & Stressing operations 6Y16 6Y17

13 Bridge 8 – Ashley Road 13 Hale Crossover UM DM ← Ashley StationHale Station → 6Y16 Sat 00:15 - Sat 22:00 LOCO,10 LD Autohopper 6Y17 Sat 01:00 - Sun 15:00 LOCO, Support, KIROW, Runner, 3MT Salmons, 1MT Tench, 10MT Falcons, LOCO (from site only) 1.Trains access from Northenden 2.KIROW lifts out panels onto 6Y17 3.Scarify, grade and compact using 2 X PC138, D41 Dozer and Triple Whacker. Load into 6Y18 (20MT Falcons) 4.KIROW relay panels from 6Y17 5.Unload top stone from 6Y16 and profile using RRV 6.Tamper site 7.Re-rail panelled section using McCulloch 8.Welding & Stressing operations 6Y16 6Y17

14 Bridge 8 – Ashley Road 14 Hale Crossover UM DM ← Ashley StationHale Station → 6Y16 Sat 00:15 - Sat 22:00 LOCO,10 LD Autohopper 6Y17 Sat 01:00 - Sun 15:00 LOCO, Support, KIROW, Runner, 3MT Salmons, 1MT Tench, 10MT Falcons, LOCO (from site only) 1.Trains access from Northenden 2.KIROW lifts out panels onto 6Y17 3.Scarify, grade and compact using 2 X PC138, D41 Dozer and Triple Whacker. Load into 6Y18 (20MT Falcons) 4.KIROW relay panels from 6Y17 5.Unload top stone from 6Y16 and profile using RRV 6.Tamper site 7.Re-rail panelled section using McCulloch 8.Welding & Stressing operations 6Y16 6Y17

15 Bridge 8 – Ashley Road 15 Hale Crossover UM DM ← Ashley StationHale Station → 6Y16 Sat 00:15 - Sat 22:00 LOCO,10 LD Autohopper 6Y17 Sat 01:00 - Sun 15:00 LOCO, Support, KIROW, Runner, 3MT Salmons, 1MT Tench, 10MT Falcons, LOCO (from site only) 1.Trains access from Northenden 2.KIROW lifts out panels onto 6Y17 3.Scarify, grade and compact using 2 X PC138, D41 Dozer and Triple Whacker. Load into 6Y18 (20MT Falcons) 4.KIROW relay panels from 6Y17 5.Unload top stone from 6Y16 and profile using RRV 6.Tamper site 7.Re-rail panelled section using McCulloch 8.Welding & Stressing operations 6Y16

16 Bridge 8 – Ashley Road 16 Hale Crossover UM DM ← Ashley StationHale Station → 6Y16 Sat 00:15 - Sat 22:00 LOCO,10 LD Autohopper 6Y17 Sat 01:00 - Sun 15:00 LOCO, Support, KIROW, Runner, 3MT Salmons, 1MT Tench, 10MT Falcons, LOCO (from site only) 1.Trains access from Northenden 2.KIROW lifts out panels onto 6Y17 3.Scarify, grade and compact using 2 X PC138, D41 Dozer and Triple Whacker. Load into 6Y18 (20MT Falcons) 4.KIROW relay panels from 6Y17 5.Unload top stone from 6Y16 and profile using RRV 6.Tamper site 7.Re-rail panelled section using McCulloch 8.Welding & Stressing operations

17 Bridge 8 – Ashley Road 17 Hale Crossover UM DM ← Ashley StationHale Station → 6Y16 Sat 00:15 - Sat 22:00 LOCO,10 LD Autohopper 6Y17 Sat 01:00 - Sun 15:00 LOCO, Support, KIROW, Runner, 3MT Salmons, 1MT Tench, 10MT Falcons, LOCO (from site only) 1.Trains access from Northenden 2.KIROW lifts out panels onto 6Y17 3.Scarify, grade and compact using 2 X PC138, D41 Dozer and Triple Whacker. Load into 6Y18 (20MT Falcons) 4.KIROW relay panels from 6Y17 5.Unload top stone from 6Y16 and profile using RRV 6.Tamper site 7.Re-rail panelled section using McCulloch 8.Welding & Stressing operations

18 Bridge 8 – Ashley Road 18 Hale Crossover UM DM ← Ashley StationHale Station → 6Y16 Sat 00:15 - Sat 22:00 LOCO,10 LD Autohopper 6Y17 Sat 01:00 - Sun 15:00 LOCO, Support, KIROW, Runner, 3MT Salmons, 1MT Tench, 10MT Falcons, LOCO (from site only) 1.Trains access from Northenden 2.KIROW lifts out panels onto 6Y17 3.Scarify, grade and compact using 2 X PC138, D41 Dozer and Triple Whacker. Load into 6Y18 (20MT Falcons) 4.KIROW relay panels from 6Y17 5.Unload top stone from 6Y16 and profile using RRV 6.Tamper site 7.Re-rail panelled section using McCulloch 8.Welding & Stressing operations

19 OB45 & OB46 – Up Main OB45OB46 The Track Lower at both OB45 & 46 on the Up main was carried out during the same 54hr possession This allowed for efficiencies in both Engineering Trains, Tamping resource and Plant

20 Bridge 45 & 46 UM DM ← AltrinchamStockport → 6Y20 Sat 00:15 - Sun 18:00 LOCO, 1MT Bass, 16LD Coalfish, 3LD Parr, 19LD Coalfish 6Y21 Sat 00:45 - Sun 08:00 LOCO, 14LD Coalfish, 2LD Salmon, 18LD Coalfish, 4MT Coalfish 6Y22 Sat 01:15 - Sat 12:00 LOCO, 40MT Coalfish, LOCO Br 45 & 46 Convectional track renewal at both bridges utilising the same plant, engineering trains and tamper Br 45Br 46 6Y206Y216Y22

21 Drainage works Installation of a new drainage to bypass a previously installed drainage run allowing the water level under OB08 to be lowered

22 My role Developing the engineering plan around the available resource Production of engineering and safety documentation –Construction Phase Plan –Work Package Plans –Task Briefing Sheets –Deliverability presentation for the client Assisting the Project Manager –Internal and Client progress meetings –Change Control Working as a ‘Engineer’ during the works Hand back of the sites, compiling the Health and Safety files

23 Questions?