South Maple Street Sanitary & Storm Sewer System Improvements Project October 14, 2014
2
Project Area... 400 block South Maple Street 400 block South Maple Street 12 & 24 College Street 12 & 24 College Street 200 block Boone Avenue (east side of Boone) 200 block Boone Avenue (east side of Boone) 101 & 117 Belmont Avenue 101 & 117 Belmont Avenue
3
Project Area…..
5
Area Impact... 27 +/- Residences and Properties 27 +/- Residences and Properties
6
Project Disruptions…. Road Closures / Detours Road Closures / Detours Noise Noise Dust Dust No expected customer sewer service impacts No expected customer sewer service impacts Construction in back yards Construction in back yards Closure of alley way during construction period Closure of alley way during construction period
7
Project Purpose… US EPA Consent Decree (Not a defined project) US EPA Consent Decree (Not a defined project) Inflow / Infiltration Reduction Inflow / Infiltration Reduction Eliminates any combined sewer connections Eliminates any combined sewer connections Eliminates “Private” Sanitary Sewer Service connections; Publicly owned and maintained Eliminates “Private” Sanitary Sewer Service connections; Publicly owned and maintained Reduces Public Health Risks Reduces Public Health Risks Reduces amount and time period of Storm Water in back yards and alley* Reduces amount and time period of Storm Water in back yards and alley*
8
Scope of Work for Maple Street Project… 741 ft. of 8-inch sanitary sewer 750ft. of 6-inch sanitary sewer 750 ft. of 6-inch sanitary sewer Six (6) sanitary sewer manholes Six (6) sanitary sewer manholes 1,740ft. of storm sewer pipe 24” - 12” 1,740 ft. of storm sewer pipe 24” - 12” 13 storm sewer boxes and other structures Other necessary construction activities Other necessary construction activities
9
Maple Street Project Costs... Design Design$100,000 Construction (Preliminary Cost Estimate) Construction (Preliminary Cost Estimate)$562,000 Construction Admin./Inspection Construction Admin./Inspection$50,000 Additional Site Restoration (Estimated) Additional Site Restoration (Estimated)$50,000 Total Project Cost ( Estimated ) $762,000
10
Maple Street Project Funding… Winchester Municipal Utilities Private Sewer and Main Replacement Funds Winchester Municipal Utilities Private Sewer and Main Replacement Funds - Sanitary Sewer Portion of Work City of Winchester General Fund City of Winchester General Fund - Storm Sewer Portion of Work - Storm Sewer Portion of Work
11
Maple Street Project Schedule (Anticipated) Advertisement Date Advertisement Date November 2, 2014 Bid Opening Bid Opening November 22, 2014 Bid Award (Estimated; bid amounts) Bid Award (Estimated; bid amounts) December 2, 2014 Construction Start Construction Start Construction Time Construction Time Estimated Completion Estimated Completion January 2, 2015 6 months July 31, 2015
12
Easements… Temporary and Permanent Easements Required Temporary and Permanent Easements Required New easement – Not in flood plain – $4.00/ft. New easement – In the flood plain – $3.00/ft. Existing easement (Increase width) – $2.00/ft. Temporary (all) – $1.00/ft.
13
Summary… Eliminate combined sanitary sewer and storm connections (if any) Eliminate combined sanitary sewer and storm connections (if any) Eliminate “Private” sanitary sewer connections Eliminate “Private” sanitary sewer connections Reduce amount and time period of storm water on private property Reduce amount and time period of storm water on private property Reduce public health risks Reduce public health risks
14
Key Contacts…. Mike Flynn/Duke Dryden Matt Belcher/Joe Tincher WMU WMU City of Winchester Winchester Municipal UtilitiesCity of Winchester 150 North Main Street32 Wall Street PO Box 4177PO Box 40 Winchester, KY 40392-4177Winchester, KY 40392-0040 Phone: (859) 744-5434(859) 744-2821 Fax: (859) 745-4146(859) 745-4590