1
CAST IRON INVENTORY DARIN BURK PIPELINE SAFETY PROGRAM MANAGER, IL COMMERCE COMMISSION PAST CHAIRMAN, NATIONAL ASSOCIATION OF PIPELINE SAFETY REPRESENTATIVES
2
NATIONAL INVENTORY DECEMBER 2013 CAST IRON GAS MAIN EXISTS IN 35 STATES 30,905 MILES 11,991 CAST IRON SERVICE LINES
3
CAST IRON MAIN INVENTORY REDUCTION
4
CAST IRON SERVICE LINE REDUCTION
5
BARE STEEL PIPE INVENTORY DECEMBER 2013 56,883 MILES OF BARE STEEL MAIN NATION WIDE 2,361,093 INDIVIDUAL BARE STEEL SERVICE LINES NATION WIDE
6
BARE STEEL MAIN REDUCTION
7
BARE STEEL SERVICE LINE REDUCTION
8
STATES WITH COST RECOVERY MECHANISMS AS OF SEPTEMBER 2012
9
EXCAVATION DAMAGE REMAINS THE NO. 1 CAUSE OF SIGNIFICANT INCIDENTS
10
SIGNIFICANT DISTRIBUTION INCIDENTS
11
DISTRIBUTION INCIDENT FATALITIES
12
GAS DISTRIBUTION INCIDENTS 2013
13
CAST IRON REPLACEMENT CHALLENGES RISK BASED REPLACEMENT PROGRAMS QUALIFIED WORKFORCE SCHEDULE CONFLICTS WITH MUNICIPALITIES EXPANSION VS. REPLACEMENT
14
RISK BASED REPLACEMENT PROGRAMS IDENTIFICATION OF HIGHEST RISK PIPE BASED ON DIMP PROGRAM CAST IRON MAY NOT BE THE HIGHEST RISK PIPE IN THE SYSTEM BARE STEEL COPPER VINTAGE PLASTICS
15
VERIFICATION OF IMPLEMENTATION MUNICIPAL PROJECT DEVIATIONS ROAD OPENING PROHIBITIONS BUDGET CONSTRAINTS UNFORESEEN FINANCIAL ISSUES MAY DELAY PROJECTS
16
RISK BASED PROGRAM SHOULD IDENTIFY CORROSION / GRAPHITIZATION LEAK PRONE PIPE SPECIFIC RISKS TO PIPE THIRD PARTY DAMAGE OUTSIDE FORCES MATERIAL FAILURE ETC.
17
QUALIFIED WORKFORCE LIMITATIONS NEW CONSTRUCTION IS NOT A COVERED TASK UNDER OPERATOR QUALIFICATION CONTRACTED LABOR CAN INSTALL NEW PIPE BUT CANNOT PERFORM TIE IN TO LIVE GAS OPERATOR QUALIFIED WORKFORCE CANNOT KEEP UP WITH CONTRACTOR CREWS MOVE OUT OF METER SETS LINE STOPPING MAIN TIE INS
18
SCHEDULE CONFLICTS MUNICIPAL INFRASTRUCTURE REPLACEMENT PROGRAMS CI OFTEN REPLACED IN CONJUNCTION WITH SEWER REPLACEMENT OR ROAD RENEWAL MUNICIPAL PERMITTING EXCAVATION PERMITS MUNICIPAL LINE LOCATING TRAFFIC ROUTING ISSUES
19
SYSTEM EXPANSION VS. REPLACEMENT POPULATION GROWTH IN SOME AREAS PULL RESOURCES FROM REPLACEMENT PROJECTS OPERATORS FOCUSED ON OBTAINING NEW REVENUE SOURCES EXPANSION OF NATURAL GAS AVAILABILITY
20
INTERIM CUSTOMER AND PUBLIC PROTECTION PUBLIC AWARENESS PROGRAMS (PA) INNOVATIVE, ROBUST PA PROGRAMS TO ENSURE RISKS ARE KNOWN TO ALL STAKEHOLDERS ENHANCED PA EFFECTIVENESS EVALUATIONS USE OF NEW INTERACTIVE PROGRAMS AS PIPELINE WATCH TO ENGAGE PUBLIC GA EMERGENCY RESPONDER TRAINING PROGRAM
21
ENHANCED DIMP CAN REDUCE RISK PROGRAMS THAT FULLY IMPLEMENT THE INTENT OF THE CODE NOT SIMPLY COMPLIANT ENHANCED KNOWLEDGE OF THE SYSTEM CAPTURING INFORMATION AT EVERY OPPORTUNITY ENSURING THAT THE DATA COLLECTED FOR NEW PIPING IS APPROPRIATE AND USEFUL
22
API RP 1173 PIPELINE SAFETY MANAGEMENT SYSTEMS CAN REDUCE RISK ENGAGE ENTIRE WORKFORCE FROM TOP MANAGEMENT TO FRONT LINE FIELD EMPLOYEES COMMUNICATION OF RISKS IMPLEMENTATION OF OPERATIONAL CONTROLS INCIDENT AND NEAR MISS INVESTIGATIONS SAFETY CULTURE VS. COMPLIANCE CULTURE