1 6 th Street Water Main And Street Reconstruction 2013

2 2013 6 th Street Reconstruction Contacts City of Jesup – Chris Even, Public Works City of Jesup – Chris Even, Public Works Dick Quackenbush, Mayor Dick Quackenbush, Mayor LeAnn Even, City Clerk LeAnn Even, City Clerk AECOM – Mark Durbahn, Engineer AECOM – Mark Durbahn, Engineer Questions or concerns, please call city hall at 827-1522. Questions or concerns, please call city hall at 827-1522.

3 2013 6 th Street Reconstruction What’s Included Remove and replace existing 6 th Street surface from Hawley Street to Prospect Street with new 8” concrete. Remove and replace existing 6 th Street surface from Hawley Street to Prospect Street with new 8” concrete. Widen 6 th Street from 27 feet to 40 feet from Hawley Street to Prospect Street. Widen 6 th Street from 27 feet to 40 feet from Hawley Street to Prospect Street. Install new 8” water main on 6 th Street from Hawley Street to Church Street. Install new 8” water main on 6 th Street from Hawley Street to Church Street. Install new storm sewer intakes at 6 th Street and Hawley Street intersection Install new storm sewer intakes at 6 th Street and Hawley Street intersection

4 2013 6 th Street Reconstruction What’s Included Connect water customers to new larger mains on 6 th Street from Hawley Street to 235 6 th Street and on Hawley Street from 5 th Street to 7 th Street. Connect water customers to new larger mains on 6 th Street from Hawley Street to 235 6 th Street and on Hawley Street from 5 th Street to 7 th Street. Install new sidewalks and driveway approaches. Install new sidewalks and driveway approaches. Install sump pump connections to subdrain for each residence. Install sump pump connections to subdrain for each residence.

5 2013 6 th Street Reconstruction What’s Included Relocate utility poles on east side of 6 th Street further away from the street Relocate utility poles on east side of 6 th Street further away from the street Remove four trees in city parking on west side of 6 th Street. Remove four trees in city parking on west side of 6 th Street. Temporarily relocate mail boxes. Temporarily relocate mail boxes. Hydro-seed disturbed areas Hydro-seed disturbed areas

6 2013 6 th Street Reconstruction Provided by AECOM

7 2013 6 th Street Reconstruction Provided by AECOM

8 2013 6 th Street Reconstruction Provided by AECOM

9 2013 6 th Street Reconstruction Provided by AECOM

10 2013 6 th Street Reconstruction Provided by AECOM

11 2013 6 th Street Reconstruction Provided by AECOM

12 6 th Street Reconstruction Schedule February 26 – Bid Opening February 26 – Bid Opening March 5 – Award Contract March 5 – Award Contract April/May – Anticipated Start Date April/May – Anticipated Start Date May 22 – 1 st Day to Close Prospect Street May 22 – 1 st Day to Close Prospect Street August 9 – Substantial Completion Date August 9 – Substantial Completion Date September 30 – Final Completion Date September 30 – Final Completion Date

13 2013 6 th Street Reconstruction Detour South to North: 6 th Street to 6 th Street to Douglas Street to Douglas Street to Main Street to Main Street to County V62 County V62 North to South: County V62 to County V62 to Main Street to Main Street to Douglas Street to Douglas Street to 6 th Street 6 th Street

14 2013 6 th Street Reconstruction Access 6 th Street Water Main Construction 6th Street closed to through traffic, open to local traffic 6th Street closed to through traffic, open to local traffic Driveways temporarily unavailable Driveways temporarily unavailable 6 th Street Road Construction: 6th Street closed to all traffic 6th Street closed to all traffic Alleys available Alleys available Temporary drive constructed west side from Hawley to 534 6 th St. Temporary drive constructed west side from Hawley to 534 6 th St.

15 2013 6 th Street Reconstruction Access Sidewalk & Driveway Construction 6 th Street closed to through traffic, open to local traffic 6 th Street closed to through traffic, open to local traffic Temporary drive removed Temporary drive removed Parking available on street Parking available on street

16 2013 6 th Street Reconstruction Subdrain Connections What’s Allowed: –Sump pumps, buried drainage tiles What’s Not Allowed: –Downspouts, surface drain Provided by AECOM

17 6 th Street Reconstruction Temporary Easements 5 to 15 feet across front yard 5 to 15 feet across front yard All improvements within city right of way All improvements within city right of way Water service connection, sidewalk and driveway construction, ingress/egress Water service connection, sidewalk and driveway construction, ingress/egress Terminate upon completion of project Terminate upon completion of project

18 6 th Street Reconstruction Questions or Comments?

19 6 th Street Reconstruction Chris Even City Hall Phone: 319-827-1522 City Hall Phone: 319-827-1522 Cell Phone: 319-404-3893 Cell Phone: 319-404-3893 Email: jesuppwd@jtt.net Email: jesuppwd@jtt.net Also keep up to date on the city’s website: Also keep up to date on the city’s website: www.jesupiowa.com www.jesupiowa.com –Look under the “News” Tab