Download presentation
Presentation is loading. Please wait.
Published byDomenic Tilden Modified over 9 years ago
1
The Hearst Tower 959 Eighth Avenue New York, NY
Jessica Lucas Mechanical Option
2
The Hearst Tower New York, NY
Presentation Outline Introduction Background Current System Proposed System Cost Analysis Electrical Breadth Structural Breadth Conclusions Background Current System Proposed System Cost Analysis Electrical Breadth Structural Breadth Conclusions Jessica Lucas Mechanical Option
3
The Hearst Tower New York, NY
Site and Location Located along 8th Avenue between 56th & 57th Street in Midtown Manhattan Constructed through the center of the original Hearst Headquarters (1928) Landmark building will be hollowed with new Tower constructed through center Introduction Background Current System Proposed System Cost Analysis Electrical Breadth Structural Breadth Conclusions Jessica Lucas Mechanical Option
4
The Hearst Tower New York, NY
Project Team Building Owner: Hearst Corporation Architect: Foster and Partners Associate Architect: Adamson Associates MEP: Flack+Kurtz CM: Turner Construction Introduction Background Current System Proposed System Cost Analysis Electrical Breadth Structural Breadth Conclusions Jessica Lucas Mechanical Option
5
The Hearst Tower New York, NY
Size and Architecture 42 stories 856,000 SF 2000 Hearst Employees Introduction Background Current System Proposed System Cost Analysis Electrical Breadth Structural Breadth Conclusions Architectural Program Open Office Auditorium Test Kitchens Television Studio Most notable features: Diagrid Facade LEED Gold certification Jessica Lucas Mechanical Option
6
The Hearst Tower New York, NY
Existing Mechanical System Central Chilled Water Plant serving a low temperature Variable Air Volume system Waterside System ton cooling towers on roof level ton & ton electric chillers in basement chiller plant Airside System 4-110,000 CFM AHU’s, serve office tower Indoor Design Conditions 75F for cooling/50% RH cooling 70F for heating Air supplied to spaces at 45F Introduction Background Current System Proposed System Cost Analysis Electrical Breadth Structural Breadth Conclusions Jessica Lucas Mechanical Option
7
The Hearst Tower New York, NY
Proposed Mechanical System: Combining Steam Driven Absorption Cooling with a Dedicated Outdoor Air/ Radiant Floor System Introduction Background Current System Proposed System Cost Analysis Electrical Breadth Structural Breadth Conclusions Replace electric chillers with double effect steam driven absorption Replace the central VAV AHU’s with dedicated outdoor air (DOAS) units Install radiant floors to parallel DOAS for both heating & cooling Jessica Lucas Mechanical Option
8
The Hearst Tower New York, NY
Goals of Proposed System Ensure ASHRAE Std compliance Obtain the LEED point for IAQ Lessen the Tower’s dependence on an overextended electric grid Lower annual operating cost Meet the original criteria to create a reliable Class “A” office building Introduction Background Current System Proposed System Cost Analysis Electrical Breadth Structural Breadth Conclusions Jessica Lucas Mechanical Option
9
The Hearst Tower New York, NY
Proposed Mechanical System: Dedicated Outdoor Air System (DOAS) What is DOAS? 100% OA unit based on ASHRAE Std.62.1 Decouples Sensible & Latent Loads Utilizes Energy Recovery DOAS for Hearst: Std % OA for IAQ LEED point Utilize an Enthalpy Wheel for total energy recovery Maintain 45F supply air temperature Introduction Background Current System Proposed System Cost Analysis Electrical Breadth Structural Breadth Conclusions Jessica Lucas Mechanical Option
10
The Hearst Tower New York, NY
Proposed Mechanical System: The resulting DOAS Design: 3-40,000 CFM Semco units with a molecular sieve desiccant coated enthalpy wheel Chiller plant downsized by 30% Cooling coil load decreased from 44 tons to tons Supply Air at 45F and saturation Introduction Background Current System Proposed System Cost Analysis Electrical Breadth Structural Breadth Conclusions Jessica Lucas Mechanical Option
11
The Hearst Tower New York, NY
Proposed Mechanical System: Radiant Floor Heating and Cooling Optimize layout based on daylighting study using AGI32 software Introduction Background Current System Proposed System Cost Analysis Electrical Breadth Structural Breadth Conclusions Jessica Lucas Mechanical Option
12
The Hearst Tower New York, NY
Proposed Mechanical System: Absorption Chillers 3-600 ton Double-effect chillers arranged in parallel Lithium Bromide/Water- no CFC’s or HCFC’s New chiller plant requires 60 kW of electric input, compared to 1,941 kW used in the electric chiller plant Con Edison offers incentives for steam driven cooling during the cooling season Introduction Background Current System Proposed System Cost Analysis Electrical Breadth Structural Breadth Conclusions Jessica Lucas Mechanical Option
13
The Hearst Tower New York, NY
Proposed Mechanical System: Additional Alternative Can I save even more with an Electric Chiller Plant w/DOAS System? Still 30% reduction in chiller plant size Still only minimum CFM Higher COP with vapor compression cycle Introduction Background Current System Proposed System Cost Analysis Electrical Breadth Structural Breadth Conclusions Jessica Lucas Mechanical Option
14
The Hearst Tower New York, NY
Proposed Mechanical System: Cost Analysis Electric w/VAV Electric w/DOAS Absorption w/DOAS Total Electricity $93.1 M $41.2 M $33.9 M Total Steam $31 M $29.4 M $39.4 M Total O&M $25.6 M $14.5 M $15.9 M 20 year LCC $156.4 M $93.4 M $98.8 M Introduction Background Current System Proposed System Cost Analysis Electrical Breadth Structural Breadth Conclusions Jessica Lucas Mechanical Option
15
The Hearst Tower New York, NY
Proposed Mechanical System: Mechanical Summary Electric/DOAS Lowest LCC Lowest Operating Cost Higher COP However… Still dependent on electric grid Black-outs = diminished reliability Recommendation: Absorption/DOAS Radiant Introduction Background Current System Proposed System Cost Analysis Electrical Breadth Structural Breadth Conclusions Jessica Lucas Mechanical Option
16
The Hearst Tower New York, NY
Electrical System Breadth Current Electrical System: amp service take-offs Each takeoff is served by amp service switch Each takeoff provides 480/277 V 3 phase service from primary transformers Daylighting & Occupancy sensors used throughout for energy conservation High efficiency ballasts, helped obtain rebates from NYSERDA Introduction Background Current System Proposed System Cost Analysis Electrical Breadth Structural Breadth Conclusions Jessica Lucas Mechanical Option
17
The Hearst Tower New York, NY
Electrical System Breadth Existing Chiller Plant Chiller 1&2: 2000 A fuses, 6 sets of MCM with 1-#3/0 ground in 3”conduit Chiller 3: 800 A fuse, 2 sets of MCM with 1-#2/0 ground in 3.5” conduit Cost of wiring & conduit: $932.00/LF Introduction Background Current System Proposed System Cost Analysis Electrical Breadth Structural Breadth Conclusions New Plant Chiller 1,2,3: 40 A fuses, 1 set of 3-#6 with 1-#10 ground in 1”conduit Cost of wiring & conduit: $46.80/LF Jessica Lucas Mechanical Option
18
The Hearst Tower New York, NY
Electrical System Breadth Existing VAV System 8 supply fans- 124 FLA 4 return fans- 65 FLA MCC total connected load of 1,697 FLA Introduction Background Current System Proposed System Cost Analysis Electrical Breadth Structural Breadth Conclusions Proposed DOAS System 3 supply fans- 77 FLA 3 return fans- 65 FLA MCC total connected load of 632 FLA Jessica Lucas Mechanical Option
19
The Hearst Tower New York, NY
Electrical System Breadth: Conclusions Downsizing equipment results in: Introduction Background Current System Proposed System Cost Analysis Electrical Breadth Structural Breadth Conclusions First cost savings for wire & conduits Decreased switch sizes Increased distribution board space Allows for easier installation Jessica Lucas Mechanical Option
20
The Hearst Tower New York, NY
Structural System Breadth: Current System Half of the foundation is supported by spread footings, half by caissons Primary lateral support provided by the perimeter Diagrid Secondary lateral system defined by braced frame at the service core Structure below 10th floor uses a mega-column system to support a large unbraced height Introduction Background Current System Proposed System Cost Analysis Electrical Breadth Structural Breadth Conclusions Jessica Lucas Mechanical Option
21
The Hearst Tower New York, NY
Structural System Breadth: Effect of Radiant Floors International Fire Code hour fire rating Vulcraft Deck 6” slab Radiant tubes 1.5” concrete cover Check deck, beams, girders with additional concrete load LRFD Manual example for Composite W-shape flexural member design (unshored construction) Introduction Background Current System Proposed System Cost Analysis Electrical Breadth Structural Breadth Conclusions Jessica Lucas Mechanical Option
22
The Hearst Tower New York, NY
Structural System Breadth: Conclusion Allowable Shear Stud Capacity greater than Maximum shear under applied loading Vu < ΣQn i.e k < 451 k Allowable Flexural Capacity exceeds Maximum moment under the applied factored loading Mu < ФMn i.e. 428 ft-k < 450 ft-k No changes needed to member sizes! Introduction Background Current System Proposed System Cost Analysis Electrical Breadth Structural Breadth Conclusions Jessica Lucas Mechanical Option
23
The Hearst Tower New York, NY
Conclusions Proposed mechanical system satisfied criteria set forth at the beginning of the design process: Lower annual operating costs Obtain LEED point for IAQ Lessen dependence on electric grid Increase reliability Maintain Class “A” market status Positively impact electrical system by lowering first cost & allowing for easier installation No nominal impact on Structural system Introduction Background Current System Proposed System Cost Analysis Electrical Breadth Structural Breadth Conclusions Jessica Lucas Mechanical Option
24
The Hearst Tower New York, NY
Acknowledgements A huge Thank You to: JJ, Dr. Freihaut, Dr. Bahnfleth, Dr. Mumma, Dr. Srebric and the rest of the AE Faculty. My fellow classmates especially Jenny, Jayme, Yulien, Dave, Bryan, and Adam. Paul Reitz of Flack+Kurtz Introduction Background Current System Proposed System Cost Analysis Electrical Breadth Structural Breadth Conclusions Jessica Lucas Mechanical Option
25
The Hearst Tower New York, NY
Introduction Background Current System Proposed System Cost Analysis Electrical Breadth Structural Breadth Conclusions Questions?? Jessica Lucas Mechanical Option
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.