CASE STUDY OF WADI LABA AND WADI MAI ULE (ELWDP – ERITREA) Lesson 5 ianmcanderson@aol.com
6
Wadi Laba Initial Areas for examination/concern: – Sediment Basin/Gravel Trap – She’eb Khethin Culvert – Breaching Bund – Capacity of Main Intake – Supply to She’eb Khethin Area – Supply to Id Abay
7
Wadi Labi Gravel Trap
8
Gravel Trap Planned to clean after every big flood and about 10 times per year Floods in 2004 = 15; 2005 = 39 Cleaned 3 times since 2003 Cost this year Nfa 600,000 or Nfa 170/ SFA member for one cleaning Farmers want no cleaning & silt to field Prepared for extra canal cleaning and farm levelling
9
She’eb Kethin Culvert - Both Barrels blocked at outlet after cleaning of d/s canal
10
She’eb Kethin Culvert Designed for 7.5 cumecs Only works for medium floods and above Farmers not getting enough water – max 4 cumecs & for less period Downstream weir levels too high – only 0.3 m below culvert invert compared with design of 1.03 m = 0.7 m too high Silted up due as velocity drops One barrel completely blocked; other seasonally blocked Farmers built temporary Agim to get enough water
12
Temporary Agim for She’eb Khethin
13
Main Intake Designed for 35 cumecs Takes full flow with zero flow over weir Flood flow to be restricted to 50 cumecs In practice no gate operation so Q rises to 83 cumecs Thus can get enough water into intake for command area
14
Breaching Bund Breaks about once a year
15
Impact of Breaching of Bund Reduced surcharge on intake Force of impact breaks She’eb Khethin temporary Agim Water available to Ide Abay downstream Increased O & M cost Greatest impact on She’eb Khethin
16
What do farmers Want Solution to temporary Agim Reliable supply for She’eb Khethin – New intake for She’eb Khethin on right bank by breaching bund (will replace culvert) – Will overcome lack of capacity of intake as supplies large area separately – Do not clean sediment basin
17
Proposals - Immediate Sediment Basin/Gravel Trap Check Weir Structure in sedimentation basin She’eb Khethin Culvert Breaching Bund Flow Recording
18
Proposals – Next 12 Months Re-examine Supply to She’eb Khethin Command area with FULL farmer involvement. New Right bank intake Monitor Gravel Trap and Check Weir Structure Record flow data and monitor against flood occurrences
20
Layout in Staff Appraisal Report 1995
21
WADI LABA Farmers Discuss way forward and options in the immediate and longer term
22
Wadi Mai Ule Areas for examination/concern: – New Right Bank intake of Farmers – Breaching Bund – Capacity of Main Intake – Supply to Tiluk Area – Flood diversion canals and embankments – Current design and capacity to contain flood peaks – Liability and risk associated with the design
23
Floods Experienced 2004 = 6 (small: 2; Medium: 1; High; 3) 2005 = 13 (small: 4; Medium: 6; High; 3) Small – not over weir Medium – over weir before breaching High – Leads to breaching Duration medium & large : 3 hrs
24
Problems Floods of short duration and reach peak quickly Flows passing through breaching bund, scour sluice or over weir lost to all system Capacity of gates not sufficient for short peak before breach about 1 hour Gibathr area 300 ha – largest and not getting water Farmers built own offtake d/stream of weir
25
Farmers new Intake
26
Concerns with new intake Cannot take design flood flow Approach flow encouraged to go to left and right bank New channel completely blocked Left bank of intake will not withstand large flood
27
Inadequate left bank protection – liable to overturn and scour
28
What Farmers Want Reliable supply to all areas to use excess flow over weir and through bund Increased opening downstream to 100 metres Not to use new flood channel
29
Proposals – Short term Improvement of New Right Bank Farmers Offtake to withstand floods Allow extra flood to pass down new flood channel Flow Recording
30
Proposals – Next 12 Months Re-examine Supply to all Command area with FULL farmer involvement. Monitor performance of improved Farmers offtake this flood season Second Right bank offtake similar to farmers Record flow data and monitor against flood occurrences
32
WADI MAI ULE Farmers Discuss way forward and options in the immediate and longer term
33
Next Steps - Immediate Prepare programme for immediate works Prepare cost estimates for works MOA to mobilise resources to complete in one month – Force account – Hire extra machinery Involve SFA where possible
34
Next Steps – next 12 months Complete design modifications with full farmer involvement Request funding Start construction next season
35
END RESULT Farmers content with final result Can irrigate more area in good years Suffering stream bank erosion and damage Content to accept this Process made Farmers Association more cohesive Solution not ideal from Investors or Engineers viewpoint Many lessons learnt…………