North Central Region Construction Conference March 7, 2013
2
Overview Utility unit staff Utility unit can help – Wisconsin Statute 182.0175 – Conflict or Means and Methods – Compensable utility relocations – Non-compensable utility relocations – Process – Documentation
3
Utility Unit Staff Wis. Rapids Office Mike Maurer 715-421-8059 michael.maurer@dot.wi.gov Richard Rogers 715-421-8078 richard.rogers@dot.wi.gov Bryan Magnuson (DTSD Consultant) 920-609-3703 bryan.magnuson@dot.wi.gov
4
Utility Unit Staff Rhinelander Office Terry Catlin 715-365-5763 terry.catlin@dot.wi.gov Josh Gerrits (DTSD Consultant) 715-846-8401 josh.gerrits@dot.wi.gov Steve Kienitz 715-365-5762 stephen.kienitz@dot.wi.gov
5
Utility Unit Staff Permitting Terry Catlin (Rhinelander) 715-365-5763 terry.catlin@dot.wi.gov Keith Rutkowski (Wis. Rapids) 715-421-8035 keith.rutkowski@dot.wi.gov
6
Utility Unit Staff Wis. Rapids and Rhinelander Mike Baumann (Utility Engineer) 715-421-7393 michael.baumann@dot.wi.gov Jordan Kelbley (Utility Supervisor) 715-421-8041 jordan.kelbley@dot.wi.gov
7
Utility Unit Can Help Navigating laws Conflict resolution – Conflict or Means and Methods – Compensable or Non-Compensable Assist determining compensability Coordinate approvals Create documents – Process – Documentation
8
Wisconsin Statute 182.0175 The contractor must expose (pot-hole) the underground utility facility at reasonable intervals Note: The utility company is not responsible to expose underground utility facilities
9
Conflict or Means and Methods Underground facility with 18 inches of excavation limits Overhead facility too close to crane Above ground facility with two feet of face of curb Underground facility cannot withstand weight of equipment Soil not stable so underground facility requires protection
10
Conflict or Means and Methods How was contractor anticipated to build project? What equipment was contractor anticipated to use? Specific equipment required to avoid utility conflict? Are plans and special provisions consistent? Contractor follow plan or did changes occur? Issue based upon law/engineering or convenience?
11
Plan calls for non-integral curb and gutter Contractor chooses to do integral curb and gutter Utility facilities two feet or more from face of curb No conflict so contractor responsible for all costs associated with adjusting utility facilities or working around them Example Conflict or Contractor’s Means and Methods
12
Work Plans approved with overhead wires over a bridge deck Special provisions and plan developed with the overhead wires over the bridge deck Bridge can be built with 10 feet of clearance between adequate equipment and overhead wires No conflict so contractor responsible for all costs associated with adjusting utility facilities or working around them
13
Compensable Utility Relocations Utility has a land right – Easement – Prescriptive rights – Previous Conveyance of Rights document – Other Second Move State Statue 84.295 (4m)
14
Non-Compensable Utility Relocations In right-of-way by permit – Have not relocated – Second Move due to utility company error Construction Permit
15
Process Who has authority – Compensable – Non-Compensable Who to inform – Utility company – Project manager – Utility engineer/coordinator
16
Documentation Diary entries – Who, what, where, when – Utilities marked – Potholing locations and utility elevations – Controlling item affected – Delay or inconvenience – Other information as needed Pictures – Make sure has some scale to it – Make sure get whole area Documentation reports – Project Manager/Leader – Utility Company
17
Project Manager/Leader Documentation Report
18
Utility Company Documentation Report
19
Questions or Comments? Mike Baumann 715-421-7393 michael.baumann@dot.wi.gov