Environmental Impact Assessment
Frank van Gemert NRG, Radiation & Environment The Netherlands
2
Eundetraf II - Environmental Impact Assessment
3
Eundetraf II - Environmental Impact Assessment
Contents Introduction Why ? How ? Who ? When ? €, £, $ ? Conclusions Eundetraf II - Environmental Impact Assessment
4
Introduction EIA Environmental Impact Assessment =
Eundetraf II - Environmental Impact Assessment
5
Eundetraf II - Environmental Impact Assessment
Why ? Regulatory requirements Public Involvement Eundetraf II - Environmental Impact Assessment
6
Regulatory requirements
COUNCIL DIRECTIVE 97/11/EC of 3 March 1997 amending DIRECTIVE 85/337/EEC of 27 June 1985 on the assessment of the effects of certain public and private projects on the environment. … See Chapter 5 Eundetraf II - Environmental Impact Assessment
7
Eundetraf II - Environmental Impact Assessment
Public involvement Takes a lot of time Creates additional burdens Environmental issues are for experts But: Eundetraf II - Environmental Impact Assessment
8
Eundetraf II - Environmental Impact Assessment
Public involvement Brings additional expertise in the decision making process Results in better implemented and respected decisions Makes environmental legislation more effective Eundetraf II - Environmental Impact Assessment
9
Eundetraf II - Environmental Impact Assessment
How ? A phased process Screening Scoping Impact Evaluation Impact Statement Review and decision Eundetraf II - Environmental Impact Assessment
10
Eundetraf II - Environmental Impact Assessment
How ? A phased process Screening Scoping Impact Evaluation Impact Statement Review and decision Eundetraf II - Environmental Impact Assessment
11
Eundetraf II - Environmental Impact Assessment
Screening Determine if an EIA is required EU guidance to facilitate the screening process Eundetraf II - Environmental Impact Assessment
12
Steps in screening EIA X X EIA X EIA Annex I or II ? Mandatory list ?
Exclusion list ? Case-by-case; sign. effect ? yes no no no yes yes no yes Natura 2000; sign. effect ? EIA X X EIA no yes Record the decision X EIA Eundetraf II - Environmental Impact Assessment
13
Selection criteria case by case screening
Characteristics of projects Location of Projects Characteristics of the potential impact Eundetraf II - Environmental Impact Assessment
14
Eundetraf II - Environmental Impact Assessment
Screening tools Screening checklist Checklist of criteria for evaluating the significance of environmental effects Eundetraf II - Environmental Impact Assessment
15
Eundetraf II - Environmental Impact Assessment
Screening checklist Characteristics of projects Location of Projects Characteristics of the potential impact Eundetraf II - Environmental Impact Assessment
16
Characteristics of projects
Size of the project Cumulation with other projects Use of natural resources Production of waste Pollution and nuisances Risk of accidents Eundetraf II - Environmental Impact Assessment
17
Eundetraf II - Environmental Impact Assessment
Location of projects Existing land use Relative abundance, quality and regenerative capacity if natural resources in the area Absorption capacity of the natural environment Eundetraf II - Environmental Impact Assessment
18
Characteristics of the potential impact
Extent of the impact (area, size of population) Transfrontier nature of the impact Magnitude and complexity of the impact Probability of the impact Duration, frequency and reversibility of the impact Eundetraf II - Environmental Impact Assessment
19
Eundetraf II - Environmental Impact Assessment
How ? A phased process Screening Scoping Impact Evaluation Impact Statement Review and decision Eundetraf II - Environmental Impact Assessment
20
Eundetraf II - Environmental Impact Assessment
Scoping Must ensure that the environmental studies provide all the relevant information on: The (most important) impacts The alternatives to the project Any other matter to be included Eundetraf II - Environmental Impact Assessment
21
Eundetraf II - Environmental Impact Assessment
Scoping On request of the developer or Mandatory (in some member states) Eundetraf II - Environmental Impact Assessment
22
Eundetraf II - Environmental Impact Assessment
Requested scoping Only when requested by the EIA developer Is undertaken by the Competent Authority Requires consulting of environmental authorities May involve consultation of other interested parties and the general public Results in a “Scoping Opinion” which forms the terms of reference for the EIA Eundetraf II - Environmental Impact Assessment
23
Eundetraf II - Environmental Impact Assessment
Mandatory scoping Is undertaken by: (a) the Competent Authority or (b) the EIA developer Eundetraf II - Environmental Impact Assessment
24
Mandatory scoping by developer
A draft “Scoping Report” is prepared Requires consulting of environmental authorities May involve consultation of other interested parties and the general public Results in a “Scoping Report” which forms the terms of reference for the EIA Eundetraf II - Environmental Impact Assessment
25
Mandatory scoping by CA
Undertaken by the Competent authority or by an independent body on behalf of the CA Requires consulting of environmental authorities by the CA May involve consultation of other interested parties and the general public Results in a “Scoping Opinion” which forms the terms of reference for the EIA Eundetraf II - Environmental Impact Assessment
26
Scoping Reports and Opinions
Identify the types of environmental impacts to be investigated and reported and may also cover: Alternatives to consider Baseline surveys & investigations to carry out Methods & criteria to be used for prediction & evaluation of effects Mitigation measures to consider Organisations to consult Structure, content and length of the Environmental Information (EIS) Eundetraf II - Environmental Impact Assessment
27
Eundetraf II - Environmental Impact Assessment
but: The provision of a Scoping Opinion does not preclude the competent authority from subsequently requiring the developer to submit further information if the CA considers that it is necessary. Eundetraf II - Environmental Impact Assessment
28
Eundetraf II - Environmental Impact Assessment
Good scoping: Will involve the CA and the developer in a dialogue about the project and the issues it raises. Does not end with the delivery of the Scoping Report or Opinion. Eundetraf II - Environmental Impact Assessment
29
Information for scoping
Preliminary data collection and field work; Checklists; Scoping checklist part 1 & 2; Criteria for evaluation the significance of impacts; Potential alternatives and mitigation measures. Eundetraf II - Environmental Impact Assessment
30
Scoping checklist part 1 – project characteristics
Physical changes in the locality; Use of natural resources; Harmful materials or substances; Produce of wastes; Emissions to air; Noise, light, electromagnetic radiation etc.; Contamination of land or ground or surface water; Risk of accidents; Social changes; Other factors. Eundetraf II - Environmental Impact Assessment
31
Eundetraf II - Environmental Impact Assessment
Scoping checklist Eundetraf II - Environmental Impact Assessment
32
Eundetraf II - Environmental Impact Assessment
Include: Secondary or higher order effects Indirect effects Cumulative effects Temporary or intermittent effects Effects resulting from abnormal events Eundetraf II - Environmental Impact Assessment
33
Scoping checklist part 2 – characteristics of the environment
Protected or sensitive species or fauna; Routes or facilities used by the public; Location to extreme climatic conditions; Employment; Community cohesion; Plans for future land use around the location; …. Eundetraf II - Environmental Impact Assessment
34
Eundetraf II - Environmental Impact Assessment
35
Eundetraf II - Environmental Impact Assessment
36
Eundetraf II - Environmental Impact Assessment
Consultation Environmental authorities Regional, local Pollution control Health & safety…….. Interested parties Environmental & social interest groups Employees’ organisations (e.g. unions) Research institutes… General public Residents Local community groups…. Eundetraf II - Environmental Impact Assessment
37
Effective consultation
Provide enough information; Make clear scoping is not about selling a project, but about hearing and understanding views; Provide sufficient time; The scoping stage does not preclude from making comments in a later stage; Ensure that views expressed are taken into account. Eundetraf II - Environmental Impact Assessment
38
Scoping - key questions
What effects could this project have on the environment? Which effects need particular attention in the environmental studies? Which alternatives and mitigating measures ought to be considered? Eundetraf II - Environmental Impact Assessment
39
Eundetraf II - Environmental Impact Assessment
How ? A phased process Screening Scoping Impact Evaluation Impact Statement Review and decision Eundetraf II - Environmental Impact Assessment
40
Environmental impact evaluation
Description of the environmental baseline Impact identification Assessment of significance of impacts Mitigation measures Monitoring plan Eundetraf II - Environmental Impact Assessment
41
Environmental baseline
Describes the environment prior to decommissioning: Natural environment (e.g. air and water quality, flora and fauna) Socio-economic factors (e.g. land use, infrastructure, economy) Eundetraf II - Environmental Impact Assessment
42
Impact identification
Actions in the decommissioning project (with potential to cause impact) Environmental factors (potentially affected by these impacts) Identification matrix Eundetraf II - Environmental Impact Assessment
43
Impact identification matrix (example)
Eundetraf II - Environmental Impact Assessment
44
Assessment of significance of impacts
Impact weighting schemes Take account of opinions of stakeholder groups Risk perception Professionals: probabilistic approach Other stakeholders: consequences of potential effects (even with very low probability Eundetraf II - Environmental Impact Assessment
45
Eundetraf II - Environmental Impact Assessment
Mitigation measures Determine potential effectiveness for each scenario Demonstrate that further improvements are not justified Re-assess the environmental impact of the project Eundetraf II - Environmental Impact Assessment
46
Development of a monitoring plan
Objective : Measure the impact of the decommissioning project Real impact vs. estimated impact Effectiveness of mitigating measures Parameters Methods Frequency Expected values Eundetraf II - Environmental Impact Assessment
47
Eundetraf II - Environmental Impact Assessment
How ? A phased process Screening Scoping Impact Evaluation Impact Statement Review and decision Eundetraf II - Environmental Impact Assessment
48
Environmental impact statement (EIS)
Provide information to: Decision makers People potentially effected by the project Eundetraf II - Environmental Impact Assessment
49
EIS = tool to communicate
Clear structure Description of procedure Concise, comprehensive and objective Consistent terminology, glossary References to information sources Description of methods used for studies Clear discussion of alternatives Non-technical summary Eundetraf II - Environmental Impact Assessment
50
Eundetraf II - Environmental Impact Assessment
How ? A phased process Screening Scoping Impact Evaluation Impact Statement Review and decision Eundetraf II - Environmental Impact Assessment
51
Review before decision making
Mandatory or ‘only’ good practice By competent authority or by independent organisation Aims: Information adequate for decision making? Complies with requirements of legislation? Eundetraf II - Environmental Impact Assessment
52
Eundetraf II - Environmental Impact Assessment
Review checklist Description of the project Objectives and physical characteristics of the project Size of the project Production processes and resources used Residues and emissions Risks of accidents and hazards Other questions Eundetraf II - Environmental Impact Assessment
53
Eundetraf II - Environmental Impact Assessment
Review checklist Consideration of alternatives Description of the environment likely to be affected Aspects of the environment Data collection and survey methods Other questions Eundetraf II - Environmental Impact Assessment
54
Eundetraf II - Environmental Impact Assessment
Review checklist Description of the likely effects Scoping of effects Prediction of direct effects Prediction of other effects Evaluation of significance of effects Impact assessment methods Other questions Eundetraf II - Environmental Impact Assessment
55
Eundetraf II - Environmental Impact Assessment
Review checklist Description of mitigation Non technical summary Quality of presentation Eundetraf II - Environmental Impact Assessment
56
Use of review checklist
Briefly overview the EIS Decide which questions are relevant for the project Indicate special features not identified in the checklist Review the EIS for the relevant questions Specify missing information Eundetraf II - Environmental Impact Assessment
57
Eundetraf II - Environmental Impact Assessment
EIS decision Competent authority: Are the environmental implications of the planned decommissioning project acceptable? Eundetraf II - Environmental Impact Assessment
58
Eundetraf II - Environmental Impact Assessment
Who ? Eundetraf II - Environmental Impact Assessment
59
Eundetraf II - Environmental Impact Assessment
When ? Typical duration of EIA preparation for NPP decommissioning: Detailed assessment and preparation of EIS: 9-15 months Full EIA: 1-3 years To reduce the overall level of resources: Involvement of competent authorities as soon as possible Initial feasibility studies as soon as possible Eundetraf II - Environmental Impact Assessment
60
Eundetraf II - Environmental Impact Assessment
€, £, $ ? Depends on e.g.: Size and complexness of the installation Approach to scoping Number of options in detailed assessment Identification of key impacts Approach to public involvement Availability of existing data Eundetraf II - Environmental Impact Assessment
61
Eundetraf II - Environmental Impact Assessment
€, £, $ ? EIA costs are typically 1 % of the total project costs Range: 0.01 – 5 % Typical cost of an EIA for NPP decommissioning: M€ 1 – 1.5 Up to M€ 5 if existing information is inadequate or significant environmental monitoring is required Eundetraf II - Environmental Impact Assessment
62
Eundetraf II - Environmental Impact Assessment
Conclusions Why ? Regulatory requirements Public involvement How ? Phased process Screening Scoping Impact evaluation and EI Statement Review (and decision) Eundetraf II - Environmental Impact Assessment
63
Eundetraf II - Environmental Impact Assessment
Conclusions Who ? Competent authorities Project developer Independent organisation Stakeholders General public Dialogue to reach consensus Eundetraf II - Environmental Impact Assessment
64
Eundetraf II - Environmental Impact Assessment
Conclusions When ? Start dialogue early Typical duration for NPP 1-3 years Costs ? Depends on project scale, available information, dialogue 1 % (0.01 – 5 %) of project costs Typical costs for NPP M€ 1 – 1.5 Eundetraf II - Environmental Impact Assessment
65
Frank van Gemert NRG Radiation & Environment